Question

As the project manager of a large project, you have just completed the Estimate Costs process....

As the project manager of a large project, you have just completed the Estimate Costs process. As you begin the Determine Budget process, which of the following would you require as inputs?

A.

Activity cost estimates, Basis of estimates

B.

Activity cost estimates, Activity resource estimates

C.

Resource breakdown structure, Agreements

D.

Activity cost estimates, Staff management plan

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The answer is option B. Activity cost estimates, Activity resource estimates.

Activity cost estimates gives information on the total budget at each activity that can be put, resource estimates gives information on the break up of the budget that needed to be kept at intervals for the resources that are being utilized

Add a comment
Know the answer?
Add Answer to:
As the project manager of a large project, you have just completed the Estimate Costs process....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You are the project manager for a power plant project. You have completed project initiation activities...

    You are the project manager for a power plant project. You have completed project initiation activities and you are now creating a document that describes processes to document the scope, decompose deliverables into work packages, verify that all work is complete and manage changes to the baseline. What process plan would you choose to perform? A. Develop project management plan B. Develop project management life cycle C. Develop WBS and define scope D. Develop project charter

  • IT Project Management: Chapter 7 Project Cost Management: 1. If the cost estimate will be the...

    IT Project Management: Chapter 7 Project Cost Management: 1. If the cost estimate will be the basis for contract awards and performance reporting, it should be a ____ and as accurate as possible. a. budgetary estimate b. definitive estimate c. rough order of magnitude estimate d. final estimate 2. The main outputs of the ____________________ process are activity cost estimates, basis of estimates, and project document updates. 3. It’s important for the team to ____________________ assumptions they made when developing...

  • 4. You are the project finance manager on a project that is coming in over budget...

    4. You are the project finance manager on a project that is coming in over budget and requires a cost change through the cost change control system. You know all of the following statements are true regarding the Control Costs process except A description of how cost changes should be managed and controlled is found in the cost management plan. Approved cost changes are reflected in the cost baseline. The equation, (BAC-AC)/(BAC-EV) is used to determine the cost performance that...

  • Project Description: Student groups will select an industrial project to be developed throughout the semester. Students...

    Project Description: Student groups will select an industrial project to be developed throughout the semester. Students groups will select an appropriate project and define measurable project objectives and requirements. A project plan and schedule will be generated as well as resources allocated to accomplish project objectives. Prepare a group project for the class. Use as your model one of the following Construction project Software development project Events management project ( e.g. Awards banquet) New product development Project Components: Using the...

  • (TCO B) You are the project manager for three projects. You are about to estimate costs...

    (TCO B) You are the project manager for three projects. You are about to estimate costs for these three projects. Given the below information on each project, recommend an appropriate estimation method and justify your answer for each. Project A: The work of this project has not likely been done before by anyone. You are breaking technological barriers in this project. As such, it is imperative you get accurate cost estimates. Project B: This project will be a scale-up of...

  • NO EXPLANATION NEEDED, JUST ANSWER. A senior manager is in the process of selecting a project...

    NO EXPLANATION NEEDED, JUST ANSWER. A senior manager is in the process of selecting a project manager for a new initiative that is very important for the company’s future. What is the key factor in choosing a project manager? The project manager should be the most technically competent person on the team The PM works well with various levels of management The project manager should be the functional manager of the most people on the team The project manager must...

  • A project has just completed its 87th task of a total of 150 tasks in its...

    A project has just completed its 87th task of a total of 150 tasks in its project plan. The project has a total budget of $1,500,000. It was scheduled to have spent $500,000 at this point in the plan, but has actually spent only $400,000. The project manager estimates that the value of the work actually finished is $300,000. What are the spending and schedule variances for the project? What are the SPI and CPI? What is the EAC, assuming...

  • You work for a manufacturing company and have just completed the budget process for the upcoming...

    You work for a manufacturing company and have just completed the budget process for the upcoming business year. At the end of the first quarter you take the actuals and compare them to the budget. You notice there are differences which need explanation and create the static and flexible budget variances. You present this to management and they request you to explain the variances in more detail. You go and create the Flexible Budget Performance Report and present this. You...

  • i am making project on logan motoway enhancement project . this project is completed by wood...

    i am making project on logan motoway enhancement project . this project is completed by wood and grieves company. and the questions are ...Identify a specific (engineering) project that is core to this company’s operations—you are tasked with the management of this project. Your job is to write a report detailing your initial project management plan proposal (before the project begins), which includes the following criteria: I. Project definition, scope management (0.5 page) 5 Marks II. Work Breakdown Structure (WBS)...

  • 1 Which of the following is true regarding the code of accounts? a It allows one...

    1 Which of the following is true regarding the code of accounts? a It allows one to easily identify the breakdown level of the item in the resource structure. b It describes the coding structure used by the performing organization to report financial information in its general ledger. c It is the collection of unique identifiers generally assigned to WBS items. d It defines ethical behavior in the project and the responsibilities to the customer and the profession. 2 You...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT