Question

A project has just completed its 87th task of a total of 150 tasks in its...

A project has just completed its 87th task of a total of 150 tasks in its project plan. The project has a total budget of $1,500,000. It was scheduled to have spent $500,000 at this point in the plan, but has actually spent only $400,000. The project manager estimates that the value of the work actually finished is $300,000. What are the spending and schedule variances for the project? What are the SPI and CPI? What is the EAC, assuming the remaining work will be completed as budgeted? Is this likely?

a. CV =

b. SV =

c. SPI =

d. CPI =

e. EAC =

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Project cost control is nothing but the process by which the status of the project is monitored so that the project costs are updated and changes to the cost baseline are managed. Project cost control include: -

  • Factors that result in changes to the authorized cost baseline are influenced.
  • To ensure all change request are managed in timely manner.
  • To ensure the cost expenditure is less than authorized funding.
  • Monitoring cost performance
  • Monitoring work performance
  • Expected cost overrun are kept in acceptable limits.

Plannid vales $ 500,000 Eaxnud value $400,000 Actral cest 4.300, 000 a Cv EU-4C -400,000-80o,000 $100,000 Sinc cV is paxave,esl AC t ETC EAC AAC-EU) ETC B C PI 400, 000 1500,000 846 154 46, 153 84

Add a comment
Know the answer?
Add Answer to:
A project has just completed its 87th task of a total of 150 tasks in its...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • #1. A project in its 26th week has an actual cost of $270,000. It was scheduled...

    #1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI? What is your assessment of the project from a cost and schedule perspective? #2. A project has just completed the 87th item in its plan. It was scheduled to have spent $168,000 at...

  • You are a software project manager for a software firm budgeted at 650,000$. As of today,...

    You are a software project manager for a software firm budgeted at 650,000$. As of today, the project should be 42% complete, but after reviewing the status of the scheduled tasks involved in the project, it is clear that only 30% of the work has been completed. The team has spent 425,000$ thus far. What is the current status of the project? 1)calculate PV, AC, EV, SPI, CPI, CV, CV%, SV, SV%, EAC, ETC. 2)write a short description of what...

  • A project is scheduled to be completed within 16 months and the total cost of the...

    A project is scheduled to be completed within 16 months and the total cost of the project is 500,000 USD. Eight months have passed and 220,000 USD has been spent. After a closer review, you (as a project leader) found that only 40% of the work has been completed so far, while 50% work was expected. Complete the following? Find the following values: PV = _______                                                                     EV = _______ SPI= _______                                                                      CPI = _______

  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

  • Task Date Budgeted Amount Build forms April 1 $10,000 Pour foundation April 1 $50,000 May 1...

    Task Date Budgeted Amount Build forms April 1 $10,000 Pour foundation April 1 $50,000 May 1 $100,000 Frame walls May 1 $30,000 June 1 $30,000 Remaining tasks July 1 and beyond $500,000 SV as of May 1. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1. Schedule performance index (SPI) Cost performance index (CPI) Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs Estimate at completion...

  • Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question...

    Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....

  • Question 1: The following data and table illustrate a small project: Activity A was completed on...

    Question 1: The following data and table illustrate a small project: Activity A was completed on schedule • Activity B started as planned but it is expected to take four weeks more Activity C started as planned but finished one week later • %age of completion of activity D is 60% ACWP at the end of week 10 = SR 90400 Activity Original Planned Start Time Original Planned Finish Time Wage Complete Amount Completed BCWP Amount Scheduled BCWS Amount Spent...

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • A given task was estimated to cost $15,750 to complete. Currently, the project team has completed approximately 65% of t...

    A given task was estimated to cost $15,750 to complete. Currently, the project team has completed approximately 65% of the task, and have spent $10,500. a. Determine the indices: AC, PV, and EV b. Derive the values for cost and schedule variances, as well as cost performance and schedule performance indices. Is this project ahead or behind on schedule, and is it ahead or behind on budget? c. How much additional money will be required to finish this project? d....

  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT