Question

#1. A project in its 26th week has an actual cost of $270,000. It was scheduled...

#1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI? What is your assessment of the project from a cost and schedule perspective?

#2. A project has just completed the 87th item in its plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The foreman estimates that the value of the work actually finished is about $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI? What is your assessment of the project from a cost and schedule perspective?

#3. The following project is at the end of its sixth week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations.

Activity

Predecessors

Duration (wks)

Budget ($)

Actual Cost ($)

% Complete

a

-

2

300

400

100

b

-

3

200

180

100

c

a

2

250

300

100

d

a

5

600

400

20

e

b,c

4

400

200

20

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Actual cost (AC) = 270,000

Earned value (EV) = 272000

Planned value (budget (PV) = 261000

Cost variance = EV (earned value) – AC (actual cost) = $272,000 - $270,000 = $2,000

Schedule variance = EV – PV (planned cost) = $272,000 - $261,000 = $11,000

CPI (cost performance index) = EV/AC =$272,000 / $270,000 = 1.0074

SPI (schedule performance index) = EV/ PV =$272,000 / $261,000 = 1.0421

Both CV and SV are positive i.e. project is running faster than schedule and at a lower cost. CPI & SPI Ratios >1 confirm the same.

2. Actual cost (AC) = 156000

Earned value (EV) =162000

Planned value (budget (PV) = 168000

Cost variance =162000 - 156000 = 6000

Schedule variance = 162000 - 168000 = -6000

CPI = 162000 / 156000 = 1.038

SPI = 162000 / 168000 = 0.964

CV is positive and SV is negative: The project is behind schedule but under budget. Less tasks have been performed than were scheduled at this point, but the tasks that have been performed are at a cost lesser than budgeted.

3. By week 6 , Activity a is completed, b is completed, c is completed, d would have completed 4 weeks and e would have completed 2 weeks.

Planned value = 300 + 200 + 250 + 4/5 * 600 + 1/2 * 400 = 1430 (Note - D has completed 4 weeks and E has two weeks, hence we take proportion of cost)

Earned value = Actual complete * PLanned values = 300 + 200 + 250 + 20%*600 + 20%*400 = 950

Actual cost = 400 + 180 + 300 + 400 +200 =1480

Cost variance = EV (earned value) – AC (actual cost) = 950 - 1480 = - 530

Schedule variance = EV – PV = 950 - 1430 = -480

CPI = 950/1480 = 0.64

SPI = 950 / 1430 = 0.66

Project is behind schedule and over budget.

Critical ratio = SPI * CPI = 0.426

Add a comment
Know the answer?
Add Answer to:
#1. A project in its 26th week has an actual cost of $270,000. It was scheduled...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A project has just completed its 87th task of a total of 150 tasks in its...

    A project has just completed its 87th task of a total of 150 tasks in its project plan. The project has a total budget of $1,500,000. It was scheduled to have spent $500,000 at this point in the plan, but has actually spent only $400,000. The project manager estimates that the value of the work actually finished is $300,000. What are the spending and schedule variances for the project? What are the SPI and CPI? What is the EAC, assuming...

  • For the following table assume we are at the end of week 7, find the cost...

    For the following table assume we are at the end of week 7, find the cost and schedule variances. Also find CPI and SPI. Finally, calculate the ETC and EAC for the project. Activity | Predecessors | Duration | Budget. S | Actual Cost. | % Complete | (weeks) 300 600 400 450 540 340 40020 20020 100 100 100 none none 400 b, c

  • 14. The following project is at the end of its sixth week. Find the cost and...

    14. The following project is at the end of its sixth week. Find the cost and schedule variances. Also find the CPI. SPI ETC, and EAC for the project. Duration Budget, Actual Cost, $ 400 180 decessors (weeks) Complete 100 100 100 20 20 250 600 400 200

  • PLEASE SHOW ALL CALCULATIONS. PLEASE DRAW A NETWORK DIAGRAM AS WELL. The following project is at...

    PLEASE SHOW ALL CALCULATIONS. PLEASE DRAW A NETWORK DIAGRAM AS WELL. The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods. Activity Predecessor Duration (wks) Budget      ($) Actual Cost ($) %Complete a - 2 600 400 100 b - 3 150 180...

  • please answer in details, thank you The Project below is currently at the end of Week...

    please answer in details, thank you The Project below is currently at the end of Week 6. Use the table below to find the PV, EV, CPI, SPI, and CSI. Use the % Complete column where applicable for these calculations. What conclusions can you make on the project given your calculated CPI, SPI, and CSI values? Activity Predecessors Duration (weeks) Budget, $ $350 $550 $250 $400 $450 $600 Actual Cost, $ $400 $550 $200 $300 $150 А % Complete 100%...

  • 8. For the following test marketing project at week 6: (a) Ignore the far right .%...

    8. For the following test marketing project at week 6: (a) Ignore the far right .% Complete" column and using the 50-50 percent completion rule for PV and EV calculate the cost, schedule, and time variances. Also calculate the CPI, SPI, CSI, and the ETC and EAC (b) Repeat the calculations in a, but now using the ..% Complete" column. Assume that the PV values are based on time propo values for EV are from the workers actually doing the...

  • 2. A sales project at month 5 had an actual cost of $34,000, a planned cost...

    2. A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and a value completed of $39,000. Find the cost and schedule variances and the CPI and SPI

  • At week 10 of a project below to improve distance learning platform, assume that the planned...

    At week 10 of a project below to improve distance learning platform, assume that the planned values (PV) are based on time proportionality but the “% Complete” values for earned values (EV) are from the workers actually doing the tasks. ACTIVITY PRE- DECESSORS DURATION (WEEKS) BUDGET ($) ACTUAL COST ($) % COMPLETE A - 5 500 640 100 B A 3 300 400 100 C B 4 320 310 80 D B 6 600 250 60 E C,D 3 300...

  • 5. A consulting project has an actual cost in month 10 of $23.000, a scheduled cost...

    5. A consulting project has an actual cost in month 10 of $23.000, a scheduled cost of $17,000, and a value com pleted of $20,000. Find the schedule and cost variances and the three indexes.

  • A project is scheduled to be completed within 16 months and the total cost of the...

    A project is scheduled to be completed within 16 months and the total cost of the project is 500,000 USD. Eight months have passed and 220,000 USD has been spent. After a closer review, you (as a project leader) found that only 40% of the work has been completed so far, while 50% work was expected. Complete the following? Find the following values: PV = _______                                                                     EV = _______ SPI= _______                                                                      CPI = _______

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT