Question

14. The following project is at the end of its sixth week. Find the cost and schedule variances. Also find the CPI. SPI ETC, and EAC for the project. Duration Budget, Actual Cost, $ 400 180 decessors (weeks) Complete 100 100 100 20 20 250 600 400 200
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Actual oostwert Pene Budgeted cost-of eoor Goo $95o.oo Budget Ccost of work sche duled (ecs 黍 1, 43o.oo uance 冫RCWP-Acto P cost/spending va 虫 S 20.00 480.00Schedele PenGemanc Index Gp 250 BcwP/Acup 드 950/14RO cost pen fomana Index CCP小 Budget af canpletion30ot2ao tiset+y00 estimated bemaining cest)to complehon (eTo) 书1,246.32 pvejected Gotal est) estimated at canplehan po10

Add a comment
Know the answer?
Add Answer to:
14. The following project is at the end of its sixth week. Find the cost and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • For the following table assume we are at the end of week 7, find the cost...

    For the following table assume we are at the end of week 7, find the cost and schedule variances. Also find CPI and SPI. Finally, calculate the ETC and EAC for the project. Activity | Predecessors | Duration | Budget. S | Actual Cost. | % Complete | (weeks) 300 600 400 450 540 340 40020 20020 100 100 100 none none 400 b, c

  • #1. A project in its 26th week has an actual cost of $270,000. It was scheduled...

    #1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI? What is your assessment of the project from a cost and schedule perspective? #2. A project has just completed the 87th item in its plan. It was scheduled to have spent $168,000 at...

  • PLEASE SHOW ALL CALCULATIONS. PLEASE DRAW A NETWORK DIAGRAM AS WELL. The following project is at...

    PLEASE SHOW ALL CALCULATIONS. PLEASE DRAW A NETWORK DIAGRAM AS WELL. The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods. Activity Predecessor Duration (wks) Budget      ($) Actual Cost ($) %Complete a - 2 600 400 100 b - 3 150 180...

  • 8. For the following test marketing project at week 6: (a) Ignore the far right .%...

    8. For the following test marketing project at week 6: (a) Ignore the far right .% Complete" column and using the 50-50 percent completion rule for PV and EV calculate the cost, schedule, and time variances. Also calculate the CPI, SPI, CSI, and the ETC and EAC (b) Repeat the calculations in a, but now using the ..% Complete" column. Assume that the PV values are based on time propo values for EV are from the workers actually doing the...

  • please answer in details, thank you The Project below is currently at the end of Week...

    please answer in details, thank you The Project below is currently at the end of Week 6. Use the table below to find the PV, EV, CPI, SPI, and CSI. Use the % Complete column where applicable for these calculations. What conclusions can you make on the project given your calculated CPI, SPI, and CSI values? Activity Predecessors Duration (weeks) Budget, $ $350 $550 $250 $400 $450 $600 Actual Cost, $ $400 $550 $200 $300 $150 А % Complete 100%...

  • At week 10 of a project below to improve distance learning platform, assume that the planned...

    At week 10 of a project below to improve distance learning platform, assume that the planned values (PV) are based on time proportionality but the “% Complete” values for earned values (EV) are from the workers actually doing the tasks. ACTIVITY PRE- DECESSORS DURATION (WEEKS) BUDGET ($) ACTUAL COST ($) % COMPLETE A - 5 500 640 100 B A 3 300 400 100 C B 4 320 310 80 D B 6 600 250 60 E C,D 3 300...

  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • Canyouhelpme with this questionYou are managing a project to expand a major county road in your...

    Canyouhelpme with this questionYou are managing a project to expand a major county road in your area. The project is expected to take 1 year and the expenses are budgeted to be $12,500 per month. Six months after the project started, you find out that the project is 50% complete, and that you have spent $70,000. Fill in the information in the table below: Item Value BAC PV EV AC CV = EV-AC SV = EV – PV CPI =...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT