PLEASE SHOW ALL CALCULATIONS. PLEASE DRAW A NETWORK DIAGRAM AS WELL.
The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods.
Activity |
Predecessor |
Duration (wks) |
Budget ($) |
Actual Cost ($) |
%Complete |
a |
- |
2 |
600 |
400 |
100 |
b |
- |
3 |
150 |
180 |
100 |
c |
a |
2 |
250 |
300 |
100 |
d |
a |
5 |
500 |
400 |
20 |
e |
b, c |
4 |
400 |
200 |
20 |
Critical path = A-C-E = 8 weeks. 75% complete schedule at 6 weeks
Actual Cost (AC)$ 1,480.00
Earned Value (EV)$ 1,180.00
Planned Value (PV)$ 1,600.00
Budget at Completion (BAC)$ 1,900.00
a.Cost Variance (CV) = EV – AC = $1,180 – 1,480 = -$300
b.Schedule Variance (SV) = EV – PV = $1,180 - $1,600 = -$420
c.SPI = EV / PV = $1,180 / $1,600 = 0.738
d.CPI = EV / AC = $1,180 / $1,480 = 0.8
e.Critical Ratio (CR) = CPI * SPI = 0.8 * 0.738 = 0.588
f.EAC= AC + (BAC – EV)/(CPI*SPI) = $1,480 + {($1,900 - $1,180)/(0.738*0.8)} = $2,704.48
EAC = BAC / CPI = $1,900 / .8 = $2,383.05
EAC = AC + [(BAC-EV)/CPI] = $1,480 + [($1,900-$1,180)/0.8)] = $2,383.05
EAC = AC + (BAC-EV) = $1,480 + ($1,900- 1180) = $2200
PLEASE SHOW ALL CALCULATIONS. PLEASE DRAW A NETWORK DIAGRAM AS WELL. The following project is at...
#1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI? What is your assessment of the project from a cost and schedule perspective? #2. A project has just completed the 87th item in its plan. It was scheduled to have spent $168,000 at...
14. The following project is at the end of its sixth week. Find the cost and schedule variances. Also find the CPI. SPI ETC, and EAC for the project. Duration Budget, Actual Cost, $ 400 180 decessors (weeks) Complete 100 100 100 20 20 250 600 400 200
For the following table assume we are at the end of week 7, find the cost and schedule variances. Also find CPI and SPI. Finally, calculate the ETC and EAC for the project. Activity | Predecessors | Duration | Budget. S | Actual Cost. | % Complete | (weeks) 300 600 400 450 540 340 40020 20020 100 100 100 none none 400 b, c
Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...
At week 10 of a project below to improve distance learning platform, assume that the planned values (PV) are based on time proportionality but the “% Complete” values for earned values (EV) are from the workers actually doing the tasks. ACTIVITY PRE- DECESSORS DURATION (WEEKS) BUDGET ($) ACTUAL COST ($) % COMPLETE A - 5 500 640 100 B A 3 300 400 100 C B 4 320 310 80 D B 6 600 250 60 E C,D 3 300...
please a clear and understandable answer , i posted this question before and no one answered yet !!! Suppose a project X is half completed by the end of first month. Upto this duration the rate of performance is 50 percent. Complete the below table by using given values and explain about the budget and schedule on the basis of calculations. Earned value calculations for project X after 1 month are as follows: PV-8000 SR AC-20000 SR RP=50% Project X...
Earned value calculation Based on the following Project data, answer the questions a and b. Activity Duration Predecessors Task Budget A 7 days -- $16,850 B 10 days -- $22,500 C 8 days B $16,000 D 10 days A $12,790 E 7 days B $8,500 F 4 days D $10,550 At the end of Day 10, the status of the project is as follows. Activity % Complete Actual Cost A 100% $18,000 B 100% $23,000 C 0% $0 D 10%...
Using the below information answer only part e bolded. Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a.What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? (CV) is -$5,000 (SV)...
3) You are in charge of the Aurora Project. Given the following project network, baseline, and status information, (40 Points) B DI OA E • Develop status reports for periods 7 and complete the performance indices table. . Calculate the EAC, and VAC. Based on your data, what is the current status of the project? At completion? Rule 1 0% complete 2-50/50 3 - 0/100 ID LF SL Schedule information Total 0 1 2 PV 3 4 30 5 6...
Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....