Using the below information answer only part e bolded. Given the following information for a one-year...

Using the below information answer only part e bolded.

Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion.

PV = $22,000

EV = $20,000

AC = $25,000

BAC = $120,000

a.What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(CV) is -$5,000

(SV) is -$2,000

(CPI) is 80%

(SPI) is 90.909%

b.How is the project doing? Is it ahead of or behind schedule? Is it under or over budget?

Both CV and SV are negative numbers, the project is both behind schedule and over budget. Therefore, the project is not doing well.

c.Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?

$150,000 than planned $120,000, so the project is performing worse than planned.

d.Use the SPI to estimate how long it will take to finish this project?

It will take 13.2 months to finish this project.

e.Sketch the earned value chart for this project,

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Using the below information answer only part e bolded. Given the following information for a one-year...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • to chapter 1. Given the following information for a one-year project, answer the following questions. Recall...

    to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...

  • Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question...

    Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....

  • You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Answer each of the questions below to complete your assignment. Use the same numbers as the assignment when you give your answer, I only grade answers that correspond the assignment questions. 1. For this one-year project calculate: a. cost variance, b. schedule variance, C. cost performance index (CPI),...

  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. 2. Explain your assessment on how the project is doing: Is it ahead or behind schedule? Is it under or over budget? Use calculated variances and indexes to support your argument. [50- 100-word response. 3. Use the CPI to calculate the estimate at completion (EAC) for this project....

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • Please a clear and understandable answer , i posted this question before and no one answered yet !!!

    please a clear and understandable answer , i posted this question before and no one answered yet !!! Suppose a project X is half completed by the end of first month. Upto this duration the rate of performance is 50 percent. Complete the below table by using given values and explain about the budget and schedule on the basis of calculations. Earned value calculations for project X after 1 month are as follows: PV-8000 SR AC-20000 SR RP=50% Project X...

  • Canyouhelpme with this questionYou are managing a project to expand a major county road in your...

    Canyouhelpme with this questionYou are managing a project to expand a major county road in your area. The project is expected to take 1 year and the expenses are budgeted to be $12,500 per month. Six months after the project started, you find out that the project is 50% complete, and that you have spent $70,000. Fill in the information in the table below: Item Value BAC PV EV AC CV = EV-AC SV = EV – PV CPI =...

  • At week 10 of a project below to improve distance learning platform, assume that the planned...

    At week 10 of a project below to improve distance learning platform, assume that the planned values (PV) are based on time proportionality but the “% Complete” values for earned values (EV) are from the workers actually doing the tasks. ACTIVITY PRE- DECESSORS DURATION (WEEKS) BUDGET ($) ACTUAL COST ($) % COMPLETE A - 5 500 640 100 B A 3 300 400 100 C B 4 320 310 80 D B 6 600 250 60 E C,D 3 300...

  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT