Question

At week 10 of a project below to improve distance learning platform, assume that the planned...

At week 10 of a project below to improve distance learning platform, assume that the planned values (PV) are based on time proportionality but the “% Complete” values for earned values (EV) are from the workers actually doing the tasks.

ACTIVITY

PRE-
DECESSORS

DURATION
(WEEKS)

BUDGET ($)

ACTUAL
COST ($)

%
COMPLETE

A

-

5

500

640

100

B

A

3

300

400

100

C

B

4

320

310

80

D

B

6

600

250

60

E

C,D

3

300

0

0

F

E

5

500

0

0

(a) Find the cost variance (CV), schedule variance (SV), and time variance (TV).

(b) Find the three indexes, namely cost performance index (CPI), schedule performance index (SPI), and cost schedule index (CSI). Is this project favorable or not, please comment.

(c) Find the budget at completion (BAC), estimated cost to complete (ETC), and estimated cost at completion (EAC) for the project.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Given that,

At week 10 of a project below to improve distance learning platform, assume that the planned values (PV) are based on time proportionality but the “% Complete” values for earned values (EV) are from the workers actually doing the tasks.

ACTIVITY

PRE-
DECESSORS

DURATION
(WEEKS)

BUDGET ($)

ACTUAL
COST ($)

%
COMPLETE

A

-

5

500

640

100

B

A

3

300

400

100

C

B

4

320

310

80

D

B

6

600

250

60

E

C,D

3

300

0

0

F

E

5

500

0

0

\rightarrow First, I have prepared a Gantt chart based on the above table as shown in the question, Budget is distributed per day and per activity basis.

1 B C D E F G H I J K L
2 Activity Predecessors Duration Budget 1 2 3 4 5 6 7
3 A .... 5 500 100 100 100 100 100
4 B A 3 300 100 100
5 C B 4 320
6 D B 6 600
7 E C, D 3 300
8 F E 5 500
9 Total Budget per day 100 100 100 100 100 100 100
10 Cumulative Budget 100 200 300 400 500 600 700

Formula:

1 B C D E F G H
2 Activity Predecessors Duration Budget 1 2 3
3 A .... 5 500 100 100 100
4 B A 3 300
5 C B 4 320
6 D B 6 600
7 E C, D 3 300
8 F E 5 500
9 Total Budget per day =SUM(F3-F8) =SUM(G3-G8) =SUM(H3-H8)
10 Cumulative Budget =F9 =F10+G9 =G10+H9

(a).

At the end of Day 10,

Total Planned Value = 1160 (Ref- Gantt chart)

Total actual cost=640+400+310+250

=1600

Total earned value=(500 \times 100%)+(300 \times 100%)+(320 \times 80%)+(600 \times 60%)

=1416

Cost Variance= Total earned value- Total actual cost

=1416-1600

=-184(Negative)

Schedule Variance= Total earned value- Total Planned Value

=1416-1160

=256

Time Variance=((10 \times 1416)/1160)-10

=12.207-10

=2.207

(b).

Cost performance Index= Total earned value/Total actual cost

=1416/1600

=0.885

We are getting 88.50 worth of work out of every 100 spent. It is actually bad.

Schedule performance Index= Total earned value/Total Planned Value

=1416/1160

=1.22

We are progressing at 122% of the rate that we have planned, it is actually good.

Cost schedule Index= Cost performance Index \times Schedule performance Index

=0.885 \times 1.22

=1.08

As value is more than 1, hence, it is good for the project.

(c).

Budget at completion or BAC= Total Planned Value for 22 weeks

=2520 (Ref- Gantt chart)

Estimated cost at completion at current CPI=2520/0.885

=2487

Estimated cost to complete at current CPI= Estimated cost at completion at current CPI- Total actual cost

=2487-1600

=887

Estimated cost at completion (considered that current variances are atypical of the future) = Total actual cost +( Budget at completion - Total earned value)

=1600+(2520-1416)

=2704

Estimated cost to complete= Estimated cost at completion- Total actual cost

=2704-1600

=1104

Add a comment
Know the answer?
Add Answer to:
At week 10 of a project below to improve distance learning platform, assume that the planned...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question...

    Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....

  • Using the below information answer only part e bolded. Given the following information for a one-year...

    Using the below information answer only part e bolded. Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a.What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? (CV) is -$5,000 (SV)...

  • to chapter 1. Given the following information for a one-year project, answer the following questions. Recall...

    to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...

  • You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Answer each of the questions below to complete your assignment. Use the same numbers as the assignment when you give your answer, I only grade answers that correspond the assignment questions. 1. For this one-year project calculate: a. cost variance, b. schedule variance, C. cost performance index (CPI),...

  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

  • Canyouhelpme with this questionYou are managing a project to expand a major county road in your...

    Canyouhelpme with this questionYou are managing a project to expand a major county road in your area. The project is expected to take 1 year and the expenses are budgeted to be $12,500 per month. Six months after the project started, you find out that the project is 50% complete, and that you have spent $70,000. Fill in the information in the table below: Item Value BAC PV EV AC CV = EV-AC SV = EV – PV CPI =...

  • PLEASE SHOW ALL CALCULATIONS. PLEASE DRAW A NETWORK DIAGRAM AS WELL. The following project is at...

    PLEASE SHOW ALL CALCULATIONS. PLEASE DRAW A NETWORK DIAGRAM AS WELL. The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods. Activity Predecessor Duration (wks) Budget      ($) Actual Cost ($) %Complete a - 2 600 400 100 b - 3 150 180...

  • please answer in details, thank you The Project below is currently at the end of Week...

    please answer in details, thank you The Project below is currently at the end of Week 6. Use the table below to find the PV, EV, CPI, SPI, and CSI. Use the % Complete column where applicable for these calculations. What conclusions can you make on the project given your calculated CPI, SPI, and CSI values? Activity Predecessors Duration (weeks) Budget, $ $350 $550 $250 $400 $450 $600 Actual Cost, $ $400 $550 $200 $300 $150 А % Complete 100%...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT