Question

2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 an
5. You are working on a large project and have determined that your cost variance is $50,000 and your earned value is $125,00
PC-EVM Handy Formulas EVM Techniques Planned Value (PV): The budgeted cost of what was planned to be done. Also called BCWS,
0 0
Add a comment Improve this question Transcribed image text
Answer #1

2. The formula for calculating estimate at completion or EAC is as follows,

Estimate at completion(EAC) = actual cost (AC) + Budget at completion (BAC) - Earned value (EV)

We know that actual cost(AC) is $10,000 and budget at completion (BAC) is $12,000 and earned value (EV) is equal to $8,500. Putting these values in our formula we get,

EAC = $10,000 + $12,000 - $8,500

EAC = $22,000 - $8,500

EAC =$13,500.

So the estimate at completion is equal to $13,500.

3. The formula to calculate schedule variance is given as,

schedule variance (SV) = Earned value (EV) - Planned value (PV)

And we know earned value is $15,000 and planned value is $20,000

So the schedule variance will be,

SV = EV - PV

SV = $15,000 - $20,000

SV = -$5,000

So the schedule variance is -$5,000.

5. Now to calculate actual cost when we are given that the cost variance is $50,000 and earned value is $125,000 we can use the following formula,

Cost variance (CV) = Earned value (EV) - Actual cost (AC)

We already know cost variance (CV) and earned value (EV) we can easily calculate actual cost (AC). putting the values of CV and EV in our formula we get,

$50,000 = $125,000 - AC

AC = $125,000 - $50,000

AC = $75,000.

So the actual cost is $75,000.

Add a comment
Know the answer?
Add Answer to:
2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

  • to chapter 1. Given the following information for a one-year project, answer the following questions. Recall...

    to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • Canyouhelpme with this questionYou are managing a project to expand a major county road in your...

    Canyouhelpme with this questionYou are managing a project to expand a major county road in your area. The project is expected to take 1 year and the expenses are budgeted to be $12,500 per month. Six months after the project started, you find out that the project is 50% complete, and that you have spent $70,000. Fill in the information in the table below: Item Value BAC PV EV AC CV = EV-AC SV = EV – PV CPI =...

  • Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question...

    Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) = $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Sketch (free-hand sketch acceptable) a graph to show the relationship between PV, AC, EV, BAC, and EAC. Interpret the sketch explaining on-budget (cost) and on-time (schedule) progress of the project. [75-150-word response.]

  • You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) = $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Sketch (free-hand sketch acceptable) a graph to show the relationship between PV, AC, EV, BAC, and EAC. Interpret the sketch explaining on-budget (cost) and on-time (schedule) progress of the project. [75-150-word response.]

  • You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Answer each of the questions below to complete your assignment. Use the same numbers as the assignment when you give your answer, I only grade answers that correspond the assignment questions. 1. For this one-year project calculate: a. cost variance, b. schedule variance, C. cost performance index (CPI),...

  • Using the below information answer only part e bolded. Given the following information for a one-year...

    Using the below information answer only part e bolded. Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a.What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? (CV) is -$5,000 (SV)...

  • At week 10 of a project below to improve distance learning platform, assume that the planned...

    At week 10 of a project below to improve distance learning platform, assume that the planned values (PV) are based on time proportionality but the “% Complete” values for earned values (EV) are from the workers actually doing the tasks. ACTIVITY PRE- DECESSORS DURATION (WEEKS) BUDGET ($) ACTUAL COST ($) % COMPLETE A - 5 500 640 100 B A 3 300 400 100 C B 4 320 310 80 D B 6 600 250 60 E C,D 3 300...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT