Canyouhelpme with this questionYou are managing a project to expand a major county road in your area. The project is expected to take 1 year and the expenses are budgeted to be $12,500 per month. Six months after the project started, you find out that the project is 50% complete, and that you have spent $70,000. Fill in the information in the table below:
Item | Value |
BAC | |
PV | |
EV | |
AC | |
CV = EV-AC | |
SV = EV – PV | |
CPI = EV/AC | |
SPI = EV/PV | |
EAC = BAC/CPI | |
ETC = EAC-AC | |
VAC = BAC-EAC | |
TCPI (Cost) = (BAC-EV)/(BAC-AC) |
Based on the values you computed, is the project ahead of schedule or behind schedule? Will the project be completed under budget or will it exceed the budget?
BAC = 12500 * 12 = 150,000
PV = 50% of BAC = 75,000
EV = 50% of BAC = 75,000
AC = 70,000
CV = EV-AC = 5,000
SV = EV-PV = 0
CPI = EV/AC = 1.071
SPI = EV/PV = 1
EAC = BAC/CPI = 140,000
ETC = EAC-AC = 70,000
VAC = BAC-EAC = 10,000
TCPI = (BAC-EV)/(BAC-AC) = 0.9375
NOTE:
BAC:
BAC is the estimated value of what the project will cost.
PV:
The formula to calculate Planned Value is simple. Take the planned
percentage of the completed work and multiply it by the project
budget and you will get Planned Value.
Planned Value = (Planned % Complete) X (BAC)
AC:
This is the second element of earned value management. Actual Cost
is the total cost incurred for the actual work completed to date.
Simply put, it is the amount of money you have spent to date.
EV:
As per the PMBOK Guide, “Earned Value (EV) is the value of work
performed expressed in terms of the approved budget assigned to
that work for an activity or WBS component.”
Earned Value = % of completed work X BAC
I hope this helped you. Let me know if you need any assistance or help. I shall be glad to help you.
Canyouhelpme with this questionYou are managing a project to expand a major county road in your...
Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...
Using the below information answer only part e bolded. Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a.What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? (CV) is -$5,000 (SV)...
Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...
Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....
to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...
2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...
You are a software project manager for a software firm budgeted at 650,000$. As of today, the project should be 42% complete, but after reviewing the status of the scheduled tasks involved in the project, it is clear that only 30% of the work has been completed. The team has spent 425,000$ thus far. What is the current status of the project? 1)calculate PV, AC, EV, SPI, CPI, CV, CV%, SV, SV%, EAC, ETC. 2)write a short description of what...
You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Answer each of the questions below to complete your assignment. Use the same numbers as the assignment when you give your answer, I only grade answers that correspond the assignment questions. 1. For this one-year project calculate: a. cost variance, b. schedule variance, C. cost performance index (CPI),...
You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. 2. Explain your assessment on how the project is doing: Is it ahead or behind schedule? Is it under or over budget? Use calculated variances and indexes to support your argument. [50- 100-word response. 3. Use the CPI to calculate the estimate at completion (EAC) for this project....
A project has just completed its 87th task of a total of 150 tasks in its project plan. The project has a total budget of $1,500,000. It was scheduled to have spent $500,000 at this point in the plan, but has actually spent only $400,000. The project manager estimates that the value of the work actually finished is $300,000. What are the spending and schedule variances for the project? What are the SPI and CPI? What is the EAC, assuming...