You are a software project manager for a software firm budgeted at
650,000$. As of today, the project should be 42% complete, but
after reviewing the status of the scheduled tasks involved in the
project, it is clear that only 30% of the work has been completed.
The team has spent 425,000$ thus far. What is the current status of
the project?
1)calculate PV, AC, EV, SPI, CPI, CV, CV%, SV, SV%, EAC, ETC.
2)write a short description of what the outcome means for the
project.
1 | ||||
Particulars | Working | Answer | Remark | |
Planned % Complete | 42% | |||
BAC/ Budget at Completion | 6,50,000 | |||
PV | Planned Value = (Planned % Complete) X (BAC) | 2,73,000 | Planned Value (PV) is the authorized budget assigned to work to be accomplished for an activity or WBS component | |
AC | Actual Cost | 4,25,000 | Actual Cost is the amount of money that you have spent so far. | |
% of completed work | 30% | |||
BAC (Budget at Completion). | 6,50,000 | |||
EV | Earned Value (EV) | 195000 | Earned Value is the work actually completed to date. It shows you the value that the project has produced if it were terminated today. | |
Earned Value | 1,95,000 | |||
Planned Value | 2,73,000 | |||
SPI | SPI = EV / PV | 0.71 | The schedule performance index (SPI) is a measure of how close the project is to being completed compared to the schedule. | |
CPI | Earned Value | 1,95,000 | ||
Actual Cost | 4,25,000 | 0.46 | The Cost Performance Index helps you to analyze the cost efficiency of the project. It measures the value of the work completed compared to the actual cost spent | |
Earned Value | 1,95,000 | |||
Actual Cost | 4,25,000 | |||
CV | Cost Variance = Earned Value – Actual Cost | -2,30,000 | the project’s Cost Variance is –2,30,000 $, and you are over budget since it is negative. | |
CV% | Earned Value | 195000 | ||
Actual Cost | 425000 | |||
Cost Variance in %= Earned Value / Actual Cost | 45.88% | |||
Earned Value | 1,95,000 | |||
Planned Value | 2,73,000 | |||
SV | Schedule Variance = Earned Value – Planned Value | -78,000 | The project’s Schedule Variance is -78,000 $. You are behind schedule since it is negative. | |
Earned Value | 195000 | |||
Planned Value | 273000 | |||
SV% | Schedule Variance in % = Earned Value /Planned Value | 71.43% | ||
EAC | Estimate at completion (Based on Various Method) | EAC is the expected total cost of completing all work for the project | ||
Future performance will be based on the budgeted cost | ||||
EAC = AC + (BAC – EV) | 880000 | |||
AC | 425000 | |||
BAC | 6,50,000 | |||
EV | -1,95,000 | |||
Future cost performance will be based on past cost performance | ||||
EAC = AC + [(BAC – EV) / CPI] | 2266666.667 | |||
AC | 425000 | |||
BAC | 650000 | |||
EV | -195000 | |||
CPI | 0.46 | |||
Future cost performance will be influenced by past schedule performance | ||||
EAC = AC + [(BAC -EV) / (CPI x SPI)] | 3003333.333 | |||
AC | 425000 | |||
BAC | 650000 | |||
EV | -195000 | |||
CPI | 0.46 | |||
SPI | 0.71 | |||
A new estimate is produced | ||||
EAC = AC + ETC | 701932.77 | |||
AC | 425000 | |||
ETC | 276932.77 | |||
ETC | Estimate to complete | 276932.77 | ETC is the expected cost to finish the remaining work of the project | |
ETC = (BAC – EV) / Performance factor | ||||
BAC | 650000 | |||
EV | -195000 | |||
Performance Factor(CPI*SPI) | 0.33 | |||
2 | outcome means for the project. | |||
Company’s forcats not aligned with actual i.e project should be completed 42% but actually its just 30% and company SV and CV also negative so its not give more focus on resource scheduling and ETC also $ 276932.77 |
You are a software project manager for a software firm budgeted at 650,000$. As of today,...
Canyouhelpme with this questionYou are managing a project to expand a major county road in your area. The project is expected to take 1 year and the expenses are budgeted to be $12,500 per month. Six months after the project started, you find out that the project is 50% complete, and that you have spent $70,000. Fill in the information in the table below: Item Value BAC PV EV AC CV = EV-AC SV = EV – PV CPI =...
Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....
Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...
A project has just completed its 87th task of a total of 150 tasks in its project plan. The project has a total budget of $1,500,000. It was scheduled to have spent $500,000 at this point in the plan, but has actually spent only $400,000. The project manager estimates that the value of the work actually finished is $300,000. What are the spending and schedule variances for the project? What are the SPI and CPI? What is the EAC, assuming...
You have a project to plant corn in 4 fields each having an area of 20 ha (200000 m2). Each field is to take one day to plant, and $1,000 has been budgeted per field. The fields were planned to be planted one after the other. Today is the end of day 3. Using the following project status chart, calculate PV, EV, etc., in the spaces provided. Activity Day1 Day 2 Day3 Day 4 Status at the end of day...
2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...
Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...
3) You are in charge of the Aurora Project. Given the following project network, baseline, and status information, (40 Points) B DI OA E • Develop status reports for periods 7 and complete the performance indices table. . Calculate the EAC, and VAC. Based on your data, what is the current status of the project? At completion? Rule 1 0% complete 2-50/50 3 - 0/100 ID LF SL Schedule information Total 0 1 2 PV 3 4 30 5 6...
Using the below information answer only part e bolded. Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a.What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? (CV) is -$5,000 (SV)...
The following table shows the current status data for a project at the end of month 3. PV (Planned Value) EV (Earned Value) AC (Actual Cost) SV CV SPI CPI $18,461.54 $35,673.08 $20,673.08 If you were the project manager for this project, should you have any concerns about this data? If yes, then what are your concerns? what might be some underlying causes? how might you combat these in the future? If no, then explain why not.