Question

You are a software project manager for a software firm budgeted at 650,000$. As of today,...


You are a software project manager for a software firm budgeted at 650,000$. As of today, the project should be 42% complete, but after reviewing the status of the scheduled tasks involved in the project, it is clear that only 30% of the work has been completed. The team has spent 425,000$ thus far. What is the current status of the project?

1)calculate PV, AC, EV, SPI, CPI, CV, CV%, SV, SV%, EAC, ETC.
2)write a short description of what the outcome means for the project.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1
Particulars Working Answer Remark
Planned % Complete 42%
BAC/ Budget at Completion 6,50,000
PV Planned Value = (Planned % Complete) X (BAC) 2,73,000 Planned Value (PV) is the authorized budget assigned to work to be accomplished for an activity or WBS component
AC Actual Cost 4,25,000 Actual Cost is the amount of money that you have spent so far.
% of completed work 30%
BAC (Budget at Completion). 6,50,000
EV Earned Value (EV) 195000 Earned Value is the work actually completed to date. It shows you the value that the project has produced if it were terminated today.
Earned Value 1,95,000
Planned Value 2,73,000
SPI SPI = EV / PV 0.71 The schedule performance index (SPI) is a measure of how close the project is to being completed compared to the schedule.
CPI Earned Value 1,95,000
Actual Cost 4,25,000 0.46 The Cost Performance Index helps you to analyze the cost efficiency of the project. It measures the value of the work completed compared to the actual cost spent
Earned Value 1,95,000
Actual Cost 4,25,000
CV Cost Variance = Earned Value – Actual Cost -2,30,000 the project’s Cost Variance is –2,30,000 $, and you are over budget since it is negative.
CV% Earned Value 195000
Actual Cost 425000
Cost Variance in %= Earned Value / Actual Cost 45.88%
Earned Value 1,95,000
Planned Value 2,73,000
SV Schedule Variance = Earned Value – Planned Value -78,000 The project’s Schedule Variance is -78,000 $. You are behind schedule since it is negative.
Earned Value 195000
Planned Value 273000
SV% Schedule Variance in % = Earned Value /Planned Value 71.43%
EAC Estimate at completion (Based on Various Method) EAC is the expected total cost of completing all work for the project
Future performance will be based on the budgeted cost
EAC = AC + (BAC – EV) 880000
AC 425000
BAC 6,50,000
EV -1,95,000
Future cost performance will be based on past cost performance
EAC = AC + [(BAC – EV) / CPI] 2266666.667
AC 425000
BAC 650000
EV -195000
CPI 0.46
Future cost performance will be influenced by past schedule performance
EAC = AC + [(BAC -EV) / (CPI x SPI)] 3003333.333
AC 425000
BAC 650000
EV -195000
CPI 0.46
SPI 0.71
A new estimate is produced
EAC = AC + ETC 701932.77
AC 425000
ETC 276932.77
ETC Estimate to complete 276932.77 ETC is the expected cost to finish the remaining work of the project
ETC = (BAC – EV) / Performance factor
BAC 650000
EV -195000
Performance Factor(CPI*SPI) 0.33
2 outcome means for the project.
Company’s forcats not aligned with actual i.e project should be completed 42% but actually its just 30% and company SV and CV also negative so its not give more focus on resource scheduling and ETC also $ 276932.77
Add a comment
Know the answer?
Add Answer to:
You are a software project manager for a software firm budgeted at 650,000$. As of today,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Canyouhelpme with this questionYou are managing a project to expand a major county road in your...

    Canyouhelpme with this questionYou are managing a project to expand a major county road in your area. The project is expected to take 1 year and the expenses are budgeted to be $12,500 per month. Six months after the project started, you find out that the project is 50% complete, and that you have spent $70,000. Fill in the information in the table below: Item Value BAC PV EV AC CV = EV-AC SV = EV – PV CPI =...

  • Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question...

    Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....

  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

  • A project has just completed its 87th task of a total of 150 tasks in its...

    A project has just completed its 87th task of a total of 150 tasks in its project plan. The project has a total budget of $1,500,000. It was scheduled to have spent $500,000 at this point in the plan, but has actually spent only $400,000. The project manager estimates that the value of the work actually finished is $300,000. What are the spending and schedule variances for the project? What are the SPI and CPI? What is the EAC, assuming...

  • You have a project to plant corn in 4 fields each having an area of 20...

    You have a project to plant corn in 4 fields each having an area of 20 ha (200000 m2). Each field is to take one day to plant, and $1,000 has been budgeted per field. The fields were planned to be planted one after the other. Today is the end of day 3. Using the following project status chart, calculate PV, EV, etc., in the spaces provided. Activity Day1 Day 2 Day3 Day 4 Status at the end of day...

  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • 3) You are in charge of the Aurora Project. Given the following project network, baseline, and...

    3) You are in charge of the Aurora Project. Given the following project network, baseline, and status information, (40 Points) B DI OA E • Develop status reports for periods 7 and complete the performance indices table. . Calculate the EAC, and VAC. Based on your data, what is the current status of the project? At completion? Rule 1 0% complete 2-50/50 3 - 0/100 ID LF SL Schedule information Total 0 1 2 PV 3 4 30 5 6...

  • Using the below information answer only part e bolded. Given the following information for a one-year...

    Using the below information answer only part e bolded. Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a.What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? (CV) is -$5,000 (SV)...

  • The following table shows the current status data for a project at the end of month...

    The following table shows the current status data for a project at the end of month 3. PV (Planned Value) EV (Earned Value) AC (Actual Cost) SV CV SPI CPI $18,461.54 $35,673.08 $20,673.08 If you were the project manager for this project, should you have any concerns about this data? If yes, then what are your concerns? what might be some underlying causes? how might you combat these in the future? If no, then explain why not.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT