Question

The following table shows the current status data for a project at the end of month...

The following table shows the current status data for a project at the end of month 3.

PV

(Planned Value)

EV

(Earned Value)

AC

(Actual Cost)

SV

CV

SPI

CPI

$18,461.54

$35,673.08

$20,673.08

If you were the project manager for this project, should you have any concerns about this data?

If yes, then

  • what are your concerns?
  • what might be some underlying causes?
  • how might you combat these in the future?

If no, then explain why not.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Earned Value (EV) = 35,673.08

Planned Value (PV) = 18,461.54

Actual Cost (AC) = 20,673.08

a) Schedule Variance = Earned Value to date - Planned Value to date

If SV > 0, the week's activity is ahead of the schedule

If SV < 0, the week's activity is behind the schedule

If SV = 0, the week's activity is on the schedule

Here, Schedule Variance = EV - PV = 35,673.08 - 18,461.54

Schedule Variance = $17211.54

Hence, the project is ahead of the schedule.

b) Cost Variance = Earned Value to date - Actual Cost to date

If CV > 0, the week's activity is under budget

If CV < 0, the week's activity is over budget

If CV = 1, the week's activity is on budget

Here, Cost Variance = EV - AV = 35,673.08 - 20,673.08

Cost Variance = $15000

Hence, the project is under budget.

c) Schedule Performance Index = Earned Value to date / Planned Value to date

If SPI > 1, the week's activity is ahead of the schedule

If SPI < 1, the week's activity is behind the schedule

If SPI = 1, the week's activity is on the schedule

Here, Schedule Performance Index = EV / PV = 35,673.08 / 18,461.54

Schedule Performance Index = 1.932

Hence, the project is ahead of the schedule.

d) Cost Performance Index = Earned Value to date / Actual Cost to date

If CPI > 1, the week's activity is under budget

If CPI < 1, the week's activity is over budget

If CPI = 1, the week's activity is on budget

Here, Cost Performance Index = EV / AC = 35,673.08 / 20,673.08

Cost Performance Index = 1.726

Hence, the project is under budget.

Because the project is well ahead of the schedule and project is under budget, the project manager should be relieved given the project is over-achieving the target.

Here, the assumption is that the Planned Value, Earned Value and Actual Cost are captured accurately,

The only thing that should concern the manager is that maybe the project budgeting was not appropriate as the earned value is almost double the planned value and hence, they might have to revise the budget otherwise the variance values will be too large at the end of the project.

Kindly up-vote this answer if it was helpful to you. This will help me in maintaining the quality of my answers. Do reach out to me in case of any queries. Thank you.

Happy Learning!

Add a comment
Know the answer?
Add Answer to:
The following table shows the current status data for a project at the end of month...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question...

    Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....

  • Using the below information answer only part e bolded. Given the following information for a one-year...

    Using the below information answer only part e bolded. Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a.What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? (CV) is -$5,000 (SV)...

  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

  • Earned value calculation Based on the following Project data, answer the questions a and b. Activity...

    Earned value calculation Based on the following Project data, answer the questions a and b. Activity Duration Predecessors Task Budget A 7 days -- $16,850 B 10 days -- $22,500 C 8 days B $16,000 D 10 days A $12,790 E 7 days B $8,500 F 4 days D $10,550 At the end of Day 10, the status of the project is as follows. Activity % Complete Actual Cost A 100% $18,000 B 100% $23,000 C 0% $0 D 10%...

  • You are a software project manager for a software firm budgeted at 650,000$. As of today,...

    You are a software project manager for a software firm budgeted at 650,000$. As of today, the project should be 42% complete, but after reviewing the status of the scheduled tasks involved in the project, it is clear that only 30% of the work has been completed. The team has spent 425,000$ thus far. What is the current status of the project? 1)calculate PV, AC, EV, SPI, CPI, CV, CV%, SV, SV%, EAC, ETC. 2)write a short description of what...

  • Please a clear and understandable answer , i posted this question before and no one answered yet !!!

    please a clear and understandable answer , i posted this question before and no one answered yet !!! Suppose a project X is half completed by the end of first month. Upto this duration the rate of performance is 50 percent. Complete the below table by using given values and explain about the budget and schedule on the basis of calculations. Earned value calculations for project X after 1 month are as follows: PV-8000 SR AC-20000 SR RP=50% Project X...

  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • to chapter 1. Given the following information for a one-year project, answer the following questions. Recall...

    to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...

  • Canyouhelpme with this questionYou are managing a project to expand a major county road in your...

    Canyouhelpme with this questionYou are managing a project to expand a major county road in your area. The project is expected to take 1 year and the expenses are budgeted to be $12,500 per month. Six months after the project started, you find out that the project is 50% complete, and that you have spent $70,000. Fill in the information in the table below: Item Value BAC PV EV AC CV = EV-AC SV = EV – PV CPI =...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT