PLEASE LIKE THIS ANSWER, IT HELPS ME A LOT. THANK YOU
Network Diagram:
Legend:
Gantt chart:
Activity ID | Duration | Early Start | Early Finish | Late Start | Late Finish | Slack or Total Float | Total Planned Value | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
A | 1 | 0 | 1 | 0 | 1 | 0 | 30 | 30 | ||||||||
B | 2 | 1 | 3 | 2 | 4 | 1 | 20 | 10 | 10 | |||||||
C | 3 | 1 | 4 | 1 | 4 | 0 | 30 | 10 | 10 | 10 | ||||||
D | 1 | 4 | 5 | 4 | 5 | 0 | 40 | 40 | ||||||||
E | 2 | 5 | 7 | 5 | 7 | 0 | 40 | 20 | 20 | |||||||
F | 2 | 5 | 7 | 6 | 8 | 1 | 30 | 15 | 15 | |||||||
G | 1 | 7 | 8 | 7 | 8 | 0 | 40 | 40 | ||||||||
H | 1 | 8 | 9 | 8 | 9 | 0 | 30 | 30 | ||||||||
Total PV by period | 30 | 20 | 20 | 10 | 40 | 35 | 35 | 40 | 30 | |||||||
Cumulative PV by period | 30 | 50 | 70 | 80 | 120 | 155 | 190 | 230 | 260 |
Total Planned value at the end of period 7 =190
Earned Value=PV*Percent complete
CV=EV-AC
SV=EV-PV
SPI=EV/PV
CPI=EV/AC
PCIB=EV/BAC
Activity ID | Percent complete | Earned Value=PV*Percent complete | Actual Cost | PV | CV=EV-AC | SV=EV-PV | SPI=EV/PV | CPI=EV/AC | PCIB=EV/BAC |
A | 100% | 30 | 30 | 30 | 0 | 0 | 1 | 1 | 11.54% |
B | 100% | 20 | 20 | 20 | 0 | 0 | 1 | 1 | 7.69% |
C | 100% | 30 | 35 | 30 | -5 | 0 | 1 | 0.86 | 11.54% |
D | 100% | 40 | 40 | 40 | 0 | 0 | 1 | 1 | 15.38% |
E | 80% | 32 | 40 | 40 | -8 | -8 | 0.8 | 0.8 | 12.31% |
F | 70% | 21 | 30 | 30 | -9 | -9 | 0.7 | 0.7 | 8.08% |
G | 0% | 0 | 0 | 40 | 0.00% | ||||
H | 0% | 0 | 0 | 30 | 0.00% | ||||
Total for EV,AC,PV,CV and SV | 173 | 195 | 260 | -22 | -17 | 0.91(average) | 0.89(Average) |
Current status at the end of period 7
SPI is 0.91 we are progressing at 91% of the rate that we have planned for the project
CPI=0.89 we are getting 89 worth of work out of every 100 spent in that project.
BAC=260
EAC=AC+(BAC-EV)
EAC=195+(260-173)=282
VAC=BAC-EAC=260-282=-22
3) You are in charge of the Aurora Project. Given the following project network, baseline, and...
Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...
Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...
You are a software project manager for a software firm budgeted at 650,000$. As of today, the project should be 42% complete, but after reviewing the status of the scheduled tasks involved in the project, it is clear that only 30% of the work has been completed. The team has spent 425,000$ thus far. What is the current status of the project? 1)calculate PV, AC, EV, SPI, CPI, CV, CV%, SV, SV%, EAC, ETC. 2)write a short description of what...
Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....
Canyouhelpme with this questionYou are managing a project to expand a major county road in your area. The project is expected to take 1 year and the expenses are budgeted to be $12,500 per month. Six months after the project started, you find out that the project is 50% complete, and that you have spent $70,000. Fill in the information in the table below: Item Value BAC PV EV AC CV = EV-AC SV = EV – PV CPI =...
Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8 LEGEND ES | ID | EF SL LS DUR LF SL 8 D 12 0 8412 0 0 0 2 6 8 12 F15 0 12 315 0 0 0 7 E 10 2 93 12 2 4 5 9 Time Period Task LF DUR ES SL Budget (PV)...
PLEASE SHOW ALL CALCULATIONS. PLEASE DRAW A NETWORK DIAGRAM AS WELL. The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods. Activity Predecessor Duration (wks) Budget ($) Actual Cost ($) %Complete a - 2 600 400 100 b - 3 150 180...
Using the below information answer only part e bolded. Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a.What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? (CV) is -$5,000 (SV)...
You have a project to plant corn in 4 fields each having an area of 20 ha (200000 m2). Each field is to take one day to plant, and $1,000 has been budgeted per field. The fields were planned to be planted one after the other. Today is the end of day 3. Using the following project status chart, calculate PV, EV, etc., in the spaces provided. Activity Day1 Day 2 Day3 Day 4 Status at the end of day...
Below is the time-phased baseline budget for a project and a table showing the progress as of End of Period 7. Baseline PV Task Total PV Time Period 0 1 2 3 4 5 6 7 8 9 10 11 A 30 15 15 B 40 20 20 C 80 10 10 10 10 20 20 D 30 5 5 5 5 10 E 20 5 5 5 5 F 40 10 20 5 5 G 10 5 5 PV...