1 | B | C | D | E | F | G | H |
2 | End of Period 4 | ||||||
3 | Task | Actual % Complete | EV | AC | PV | CV | SV |
4 | A | Finished | 400 | 300 | 400 | 100 | 0 |
5 | B | 50 | 1150 | 900 | 700 | 250 | 450 |
6 | C | 30 | 453 | 500 | 600 | -47 | -147 |
7 | D | 0 | 0 | 0 | 0 | 0 | 0 |
8 | E | 0 | 0 | 0 | 0 | 0 | 0 |
9 | Cumulative Totals | 2003 | 1700 | 1700 | 303 | 303 | |
10 | |||||||
11 | End of Period 8 | ||||||
12 | Task | Actual % Complete | EV | AC | PV | CV | SV |
13 | A | Finished | 400 | 300 | 400 | 100 | 0 |
14 | B | Finished | 2300 | 2100 | 2300 | 200 | 0 |
15 | C | Finished | 1510 | 1600 | 1510 | -90 | 0 |
16 | D | 25 | 390 | 400 | 0 | -10 | 390 |
17 | E | 30 | 270 | 500 | 300 | -230 | -30 |
18 | F | 0 | 0 | 0 | 0 | 0 | 0 |
19 | Cumulative Totals | 4870 | 4900 | 4510 | -30 | 360 |
Formula
1 | B | C | D | E | F | G | H |
2 | End of Period 4 | ||||||
3 | Task | Actual % Complete | EV | AC | PV | CV | SV |
4 | A | Finished | 400 | 300 | 400 | =D4-E4 | =D4-F4 |
5 | B | 50 | =(200+500+200+600+200+600)*C5/100 | 900 | 700 | =D5-E5 | =D5-F5 |
6 | C | 30 | =(200+400+500+110+300)*C6/100 | 500 | 600 | =D6-E6 | =D6-F6 |
7 | D | 0 | =F7*C7/100 | 0 | 0 | =D7-E7 | =D7-F7 |
8 | E | 0 | =F8*C8/100 | 0 | 0 | =D8-E8 | =D8-F8 |
9 | Cumulative Totals | =SUM(D4:D8) | =SUM(E4:E8) | =SUM(F4:F8) | =D9-E9 | =D9-F9 | |
10 | |||||||
11 | End of Period 8 | ||||||
12 | Task | Actual % Complete | EV | AC | PV | CV | SV |
13 | A | Finished | 400 | 300 | 400 | =D13-E13 | =D13-F13 |
14 | B | Finished | 2300 | 2100 | =(200+500+200+600+200+600) | =D14-E14 | =D14-F14 |
15 | C | Finished | 1510 | 1600 | =(200+400+500+110+300) | =D15-E15 | =D15-F15 |
16 | D | 25 | =(360+400+400+400)*25/100 | 400 | 0 | =D16-E16 | =D16-F16 |
17 | E | 30 | =(300+400+200)*30/100 | 500 | 300 | =D17-E17 | =D17-F17 |
18 | F | 0 | 0 | 0 | 0 | =D18-E18 | =D18-F18 |
19 | Cumulative Totals | =SUM(D13:D18) | =SUM(E13:E18) | =SUM(F13:F18) | =D19-E19 | =D19-F19 |
Given the project network and baseline information below, complete the form to develop a status r...
3) You are in charge of the Aurora Project. Given the following project network, baseline, and status information, (40 Points) B DI OA E • Develop status reports for periods 7 and complete the performance indices table. . Calculate the EAC, and VAC. Based on your data, what is the current status of the project? At completion? Rule 1 0% complete 2-50/50 3 - 0/100 ID LF SL Schedule information Total 0 1 2 PV 3 4 30 5 6...
Your organization is preparing a new marketing campaign. The test marketing project plan and the information reported at the end of week 6 are presented in the table below: Duration (weeks) Activity Predecessors Budget, $ Actual Cost, $ % Complete 400 200 a: Build items b: Supply stores c: Create ad program d: Schedule ads e: Check sale results 180 300 Solo bc 200 Ignore the last column "% complete" and use the rule 50-50 percent completion rule for the...
Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...
Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...
Below is the network diagram for a construction project. Given ONLY THREE (3) workers are available at all times, develop a resource schedule using the parallel heuristics for resource-constrained projects. 0 A 1 1 2 1 1 1 2 4 E 7 0 0 4 3 7 IN نا 7 G 2 c 4 3 0 2 24 1 ON 0 7 00 000 7 1 4 1 F 1 0 B 2 02 o 0 2 2 N ON...
Below is the time-phased baseline budget for a project and a table showing the progress as of End of Period 7. Baseline PV Task Total PV Time Period 0 1 2 3 4 5 6 7 8 9 10 11 A 30 15 15 B 40 20 20 C 80 10 10 10 10 20 20 D 30 5 5 5 5 10 E 20 5 5 5 5 F 40 10 20 5 5 G 10 5 5 PV...
PLEASE SHOW ALL CALCULATIONS. PLEASE DRAW A NETWORK DIAGRAM AS WELL. The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods. Activity Predecessor Duration (wks) Budget ($) Actual Cost ($) %Complete a - 2 600 400 100 b - 3 150 180...
At week 10 of a project below to improve distance learning platform, assume that the planned values (PV) are based on time proportionality but the “% Complete” values for earned values (EV) are from the workers actually doing the tasks. ACTIVITY PRE- DECESSORS DURATION (WEEKS) BUDGET ($) ACTUAL COST ($) % COMPLETE A - 5 500 640 100 B A 3 300 400 100 C B 4 320 310 80 D B 6 600 250 60 E C,D 3 300...
Question 9 Below is the time phased baseline budget for a project and a table showing the progress as of End of Period 7. 2 Baseline PV Total Task Time Period PV 0 1 3 5 6 7 8 10 11 A 30 15 15 40 20 20 с 80 10 10 10 10 20 20 D 30 5 5 5 5 10 E 20 5 5 5 5 F 40 10 20 5 5 10 5 5 PV by...
Studern Date: 08/12/2018 #1, #2and #3 are based onthe below given information: Task z Corporation's Balance Sheet is made from: Date 31/12/17 31/12/16 1) Equipment 2) Bank Loans (Long Term) 74 000 21 000 1 200 6 300 14 200 2 000 3 400 4 200 26 100 7600 13 000 23 400 300 45 000 4 300 23 700 8 000 12 000 11 900 29 500 13 500 3 100 23 000 200 23 000 6 500 6...