Planned value PV at the end of week 7 = 205
Earned value = 100% of A+100%of B+40% of C +60% of D+50% of E +30% of F
=30+40+32+18+10+12 = 142
Actual cost = 160
1. SV = EV-PV = 142-205=-63
2. CV = EV-AC = 142-160=-18
3. Percentage completion in terms of budget = EV / BAC = 142/250 = 0.568 = 56.8%
4.EAC = AC + (BAC – EV) = 160+250-142 = 268
TCPI = (BAC – EV) / (BAC – AC) = 250-142 /250-160 = 108/90 =1.2
VAC = BAC - EAC = 250-268 =-18
Question 9 Below is the time phased baseline budget for a project and a table showing...
Below is the time-phased baseline budget for a project and a table showing the progress as of End of Period 7. Baseline PV Task Total PV Time Period 0 1 2 3 4 5 6 7 8 9 10 11 A 30 15 15 B 40 20 20 C 80 10 10 10 10 20 20 D 30 5 5 5 5 10 E 20 5 5 5 5 F 40 10 20 5 5 G 10 5 5 PV...
Given the network diagram and time-phased work packages shown below, complete a baseline budget for the project. Use that information to answer the problems below. Legeno Mack Ourion Cost by Period Week Activity 1. 12 10 15 17 20 E 15 15 10 30 ene hadeer Week Aty gt otd Note that week 1 refers to the period0-1, week 2 refers to period 1-2, and so on, Ouestion 1 (1 point) SAMSUNG Baseline adet Wrek 13 10 1 1 lget...
Given the time-phased work packages and network, complete the baseline budget form for the project. Market Survey Project WBS Work Package Cost by Week WP Design - 52 WP Survey 2 2 4 4 - 5 WP Report 332 Project Network Design Survey Report Task Budget Time-Phased Budget Week 3 4 5 6 7 8 9 10 11 Design Survey Report 80 Total Cumulative
Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8 LEGEND ES | ID | EF SL LS DUR LF SL 8 D 12 0 8412 0 0 0 2 6 8 12 F15 0 12 315 0 0 0 7 E 10 2 93 12 2 4 5 9 Time Period Task LF DUR ES SL Budget (PV)...
3) You are in charge of the Aurora Project. Given the following project network, baseline, and status information, (40 Points) B DI OA E • Develop status reports for periods 7 and complete the performance indices table. . Calculate the EAC, and VAC. Based on your data, what is the current status of the project? At completion? Rule 1 0% complete 2-50/50 3 - 0/100 ID LF SL Schedule information Total 0 1 2 PV 3 4 30 5 6...
Question 1: The following data and table illustrate a small project: Activity A was completed on schedule • Activity B started as planned but it is expected to take four weeks more Activity C started as planned but finished one week later • %age of completion of activity D is 60% ACWP at the end of week 10 = SR 90400 Activity Original Planned Start Time Original Planned Finish Time Wage Complete Amount Completed BCWP Amount Scheduled BCWS Amount Spent...
At week 10 of a project below to improve distance learning platform, assume that the planned values (PV) are based on time proportionality but the “% Complete” values for earned values (EV) are from the workers actually doing the tasks. ACTIVITY PRE- DECESSORS DURATION (WEEKS) BUDGET ($) ACTUAL COST ($) % COMPLETE A - 5 500 640 100 B A 3 300 400 100 C B 4 320 310 80 D B 6 600 250 60 E C,D 3 300...
Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....
Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...
The scenario is this. You have a budget for this web page project of $707k. The budget was decided when this project was conceived two years ago. Now as the time approaches to execute the project, a detailed budget analysis is done. It is discovered that the features associated with the project exceed the budget. Some features will have to be eliminated (scrubbed). The question is, which ones...to eliminate. Use the attached spreadsheet to decide. The cost associated with one...