Question

Question 1: The following data and table illustrate a small project: Activity A was completed on schedule • Activity B starte
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

% age of completion of activity “A” = 100%

Projected duration of activity “B” = 8 + 4 = 12 weeks

% age of completion of activity “B” = 5/12 = 41.6666%

% age of completion of activity “C” = 100%

  1. BCWS10 = A + C + 5/8*B + 5/6*D = 50000 + 16000 + 5/8*12000 + 5/6*24000 = SR 93500

[Note: 5/8 & 5/6 represent ratio off completion of activities B&D with respect to scheduled duration]

BCWP10 = A + C + 0.4167*12000 + 0.60*24000 = SR 85400

[Note: 0.4167 & 0.6 represent ratio of completion of activities B&D with respect to actual completion duration]

  1. CV = BCWP – ACWP = 85400 – 90400 = SR -5000 (Over Budget)

SV = BCWP – BCWS = 85400 – 93500 = SR -8100 (Behind Schedule)

BAC = 50000 + 12000 + 16000 + 24000 + 12000 + 21000 + 20000 = SR 155000

EAC = [ACWP/BCWP] * BAC = [90400/85400] * 155000 = SR 164075

ETC = EAC – ACWP = 164075 – 90400 = SR 73675

SPI = BCWP/BCWS = 85400/93500 = 0.9134

CPI = BCWP/ACWP = 85400/90400 = 0.9447

Variance from original budget = EAC – BAC = 164075 – 155000 = SR 9,075

  1. As CV > 0, the cost performance is over budget.
    As SV < 0, the schedule (time) performance is behind schedule:
  2. Please find below the Gantt Chart:

Gantt Chart Time to complete (in weeks) 15 5 10 | 15 20 25 == Activity

Add a comment
Know the answer?
Add Answer to:
Question 1: The following data and table illustrate a small project: Activity A was completed on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • -files from the merret Lulu Instructor: Philip Zopp! Problem #1 BCWS, BCWP, and ACWP represent CUMULATIVE...

    -files from the merret Lulu Instructor: Philip Zopp! Problem #1 BCWS, BCWP, and ACWP represent CUMULATIVE TOTALS on a week by week basis. Complete SV, CV, CPI, SPI and EAC for each week. Also, plot plot CPI and SPI over time. BAC - 460 SPIEAC Week BCWS BCWP CV ACWP sv 70 Problem #2 Complete this table using the information below for the project AT THE END OF WEEK #4.

  • Earned value calculation Based on the following Project data, answer the questions a and b. Activity...

    Earned value calculation Based on the following Project data, answer the questions a and b. Activity Duration Predecessors Task Budget A 7 days -- $16,850 B 10 days -- $22,500 C 8 days B $16,000 D 10 days A $12,790 E 7 days B $8,500 F 4 days D $10,550 At the end of Day 10, the status of the project is as follows. Activity % Complete Actual Cost A 100% $18,000 B 100% $23,000 C 0% $0 D 10%...

  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • 1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 20...

    1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...

  • At week 10 of a project below to improve distance learning platform, assume that the planned...

    At week 10 of a project below to improve distance learning platform, assume that the planned values (PV) are based on time proportionality but the “% Complete” values for earned values (EV) are from the workers actually doing the tasks. ACTIVITY PRE- DECESSORS DURATION (WEEKS) BUDGET ($) ACTUAL COST ($) % COMPLETE A - 5 500 640 100 B A 3 300 400 100 C B 4 320 310 80 D B 6 600 250 60 E C,D 3 300...

  • You have a project to plant corn in 4 fields each having an area of 20...

    You have a project to plant corn in 4 fields each having an area of 20 ha (200000 m2). Each field is to take one day to plant, and $1,000 has been budgeted per field. The fields were planned to be planted one after the other. Today is the end of day 3. Using the following project status chart, calculate PV, EV, etc., in the spaces provided. Activity Day1 Day 2 Day3 Day 4 Status at the end of day...

  • Instructions: You are preparing a status report for your project sponsor and stakeholders and it's important...

    Instructions: You are preparing a status report for your project sponsor and stakeholders and it's important to share the project progress using the Earned Value technique. You are preparing your status report for the period ending October 28th. Your project started February 27th. Assume that the project is executed 5 days per week and 8 hours per day with some additional hours that amount to 8 hours every Saturday and Sunday. The project manager's table of activities are noted below....

  • I need help with the attached assignment. I attached the question and completed assigment. I just...

    I need help with the attached assignment. I attached the question and completed assigment. I just need help with answering one more question which is which is: Discuss a strategy that you would use to communicate the status of the project to stakeholders? Project Monitoring and Control Assignment Complete the following items for this assignment: 1. Read through the Case 13.1 Tree Trimming Project Case in Larson and Gray. Respond to Questions 1 and 2 of the case. Use Microsoft...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT