Problem #1
Week |
BCWS |
BCWP |
ACWP |
SV = BCWP - BCWS |
CV = BCWP - ACWP |
CPI = BCWP / ACWP |
SPI = BCWP / BCWS |
EAC = [ACWP + (BAC - BCWP) / CPI] |
1 |
50 |
50 |
25 |
0 |
25 |
2 |
1 |
230 |
2 |
70 |
60 |
40 |
-10 |
20 |
1.5 |
0.86 |
306.67 |
3 |
90 |
80 |
67 |
-10 |
13 |
1.19 |
0.89 |
385.25 |
4 |
120 |
105 |
90 |
-15 |
15 |
1.17 |
0.88 |
394.29 |
5 |
130 |
120 |
115 |
-10 |
5 |
1.04 |
0.92 |
440.83 |
6 |
140 |
135 |
130 |
-5 |
5 |
1.04 |
0.96 |
442.96 |
7 |
165 |
150 |
155 |
-15 |
-5 |
0.97 |
0.91 |
475.33 |
8 |
200 |
175 |
190 |
-25 |
-15 |
0.92 |
0.88 |
499.43 |
9 |
250 |
220 |
230 |
-30 |
-10 |
0.96 |
0.88 |
480.91 |
10 |
270 |
260 |
270 |
-10 |
-10 |
0.96 |
0.96 |
477.69 |
11 |
300 |
295 |
305 |
-5 |
-10 |
0.97 |
0.98 |
475.59 |
12 |
350 |
340 |
340 |
-10 |
0 |
1 |
0.97 |
460 |
13 |
380 |
360 |
370 |
-20 |
-10 |
0.97 |
0.95 |
472.78 |
14 |
420 |
395 |
400 |
-25 |
-5 |
0.99 |
0.94 |
465.82 |
15 |
460 |
460 |
450 |
0 |
10 |
1.02 |
1 |
450 |
Graph-1:
Graph-2:
-files from the merret Lulu Instructor: Philip Zopp! Problem #1 BCWS, BCWP, and ACWP represent CUMULATIVE...
Question 1: The following data and table illustrate a small project: Activity A was completed on schedule • Activity B started as planned but it is expected to take four weeks more Activity C started as planned but finished one week later • %age of completion of activity D is 60% ACWP at the end of week 10 = SR 90400 Activity Original Planned Start Time Original Planned Finish Time Wage Complete Amount Completed BCWP Amount Scheduled BCWS Amount Spent...
Earned Value 1. Complete the calculations Case BCWS or PV ACWP or AC BCWP or EV CV SV CPI SPI 1 800 800 800 2 800 600 400 3 800 400 600 4 800 600 600 5 800 800 600 6 800 800 1000
Earned value calculation Based on the following Project data, answer the questions a and b. Activity Duration Predecessors Task Budget A 7 days -- $16,850 B 10 days -- $22,500 C 8 days B $16,000 D 10 days A $12,790 E 7 days B $8,500 F 4 days D $10,550 At the end of Day 10, the status of the project is as follows. Activity % Complete Actual Cost A 100% $18,000 B 100% $23,000 C 0% $0 D 10%...
2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...
I need help with the attached assignment. I attached the question and completed assigment. I just need help with answering one more question which is which is: Discuss a strategy that you would use to communicate the status of the project to stakeholders? Project Monitoring and Control Assignment Complete the following items for this assignment: 1. Read through the Case 13.1 Tree Trimming Project Case in Larson and Gray. Respond to Questions 1 and 2 of the case. Use Microsoft...