Question

-files from the merret Lulu Instructor: Philip Zopp! Problem #1 BCWS, BCWP, and ACWP represent CUMULATIVE TOTALS on a week by
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Problem #1

Week

BCWS

BCWP

ACWP

SV = BCWP - BCWS

CV = BCWP - ACWP

CPI = BCWP / ACWP

SPI = BCWP / BCWS

EAC = [ACWP + (BAC - BCWP) / CPI]

1

50

50

25

0

25

2

1

230

2

70

60

40

-10

20

1.5

0.86

306.67

3

90

80

67

-10

13

1.19

0.89

385.25

4

120

105

90

-15

15

1.17

0.88

394.29

5

130

120

115

-10

5

1.04

0.92

440.83

6

140

135

130

-5

5

1.04

0.96

442.96

7

165

150

155

-15

-5

0.97

0.91

475.33

8

200

175

190

-25

-15

0.92

0.88

499.43

9

250

220

230

-30

-10

0.96

0.88

480.91

10

270

260

270

-10

-10

0.96

0.96

477.69

11

300

295

305

-5

-10

0.97

0.98

475.59

12

350

340

340

-10

0

1

0.97

460

13

380

360

370

-20

-10

0.97

0.95

472.78

14

420

395

400

-25

-5

0.99

0.94

465.82

15

460

460

450

0

10

1.02

1

450

Graph-1:

Plot of CPI over Time CPI 1 2 3 4 5 6 7 9 10 11 12 13 14 15 8 Week

Graph-2:

Plot of SPI over Time 1 2 3 4 5 6 7 9 10 11 12 13 14 15 8 Week

Add a comment
Know the answer?
Add Answer to:
-files from the merret Lulu Instructor: Philip Zopp! Problem #1 BCWS, BCWP, and ACWP represent CUMULATIVE...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 1: The following data and table illustrate a small project: Activity A was completed on...

    Question 1: The following data and table illustrate a small project: Activity A was completed on schedule • Activity B started as planned but it is expected to take four weeks more Activity C started as planned but finished one week later • %age of completion of activity D is 60% ACWP at the end of week 10 = SR 90400 Activity Original Planned Start Time Original Planned Finish Time Wage Complete Amount Completed BCWP Amount Scheduled BCWS Amount Spent...

  • Earned Value 1. Complete the calculations Case BCWS or PV ACWP or AC BCWP or EV...

    Earned Value 1. Complete the calculations Case BCWS or PV ACWP or AC BCWP or EV CV SV CPI SPI 1 800 800 800 2 800 600 400 3 800 400 600 4 800 600 600 5 800 800 600 6 800 800 1000

  • Earned value calculation Based on the following Project data, answer the questions a and b. Activity...

    Earned value calculation Based on the following Project data, answer the questions a and b. Activity Duration Predecessors Task Budget A 7 days -- $16,850 B 10 days -- $22,500 C 8 days B $16,000 D 10 days A $12,790 E 7 days B $8,500 F 4 days D $10,550 At the end of Day 10, the status of the project is as follows. Activity % Complete Actual Cost A 100% $18,000 B 100% $23,000 C 0% $0 D 10%...

  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

  • I need help with the attached assignment. I attached the question and completed assigment. I just...

    I need help with the attached assignment. I attached the question and completed assigment. I just need help with answering one more question which is which is: Discuss a strategy that you would use to communicate the status of the project to stakeholders? Project Monitoring and Control Assignment Complete the following items for this assignment: 1. Read through the Case 13.1 Tree Trimming Project Case in Larson and Gray. Respond to Questions 1 and 2 of the case. Use Microsoft...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT