Question

Instructions: You are preparing a status report for your project sponsor and stakeholders and it's important...

Instructions: You are preparing a status report for your project sponsor and stakeholders and it's important to share the project progress using the Earned Value technique. You are preparing your status report for the period ending October 28th. Your project started February 27th. Assume that the project is executed 5 days per week and 8 hours per day with some additional hours that amount to 8 hours every Saturday and Sunday. The project manager's table of activities are noted below.

ID

Activity

Original Duration (days)

Actual Duration

(days)

Actual Start Date

Actual Finish Date

%

Complete

Original

Budget

Actual

Budget

10

Site Prep

8

9

2/27

4/26

100

$500,000

$600,000

20

Substructure

12

11

5/1

7/18

100

$1,500,000

$1,350,000

30

Super Substructure

18

-

7/20

-

75

$2,000,000

$1,450,000

40

Exterior

6

-

-

-

0

$400,000

-

50

Interior

14

-

8/31

-

50

$1,800,000

$1,000,000

60

Services

10

-

-

-

0

$1,000,000

-

70

Cleanup

4

-

-

-

0

$200,000

Question 2: Calculate the Planned Value (BCWS) based on the original budget, the original duration, and the number of weeks between the planned early start date and the status date (October 28th for the activities that are in progress. This calculation will provide the amount of money the project has spent up to October 28th?

Activity 30 - Super substructure

Original Budget = $2,000,000

Original Duration = 18 Weeks

Number of Weeks between Planned Start Date and Status State = ______ #Weeks to status date (From Question 1.

BCWS = #Weeks to status date / Original Duration * Original Budget

BCWS = ______________________________

Activity 50 - Interior

Original Budget = $1,800,000

Original Duration = 14 Weeks

Number of Weeks between Planned Start Date and Status State =_______ #Weeks to status date (From Question 1).

BCWS = #Weeks to status date / Original Duration * Original Budget

BCWS = ______________________________

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Activity 30 - Super substructure

Original Budget = $2,000,000

Original duration = 18 weeks

Number of weeks between planned start date and status state = 13.5

BCWS = Weeks to status date / Original Duration * Original Budget

BCWS = (13.5/18) X $2,000,000

= $1,500,000

Activity 50 - Interior

Original Budget = $1,800,000

Original Duration = 14 Weeks

Number of weeks between planned start date and status state = 8

BCWS = Weeks to status date / Original Duration * Original Budget

BCWS = (8/14) X $1,800,000

= $1,028,571.43

*If you like the answer, please give it a thumbs-up. It will be highly appreciated*

Add a comment
Know the answer?
Add Answer to:
Instructions: You are preparing a status report for your project sponsor and stakeholders and it's important...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT