Instructions: You are preparing a status report for your project sponsor and stakeholders and it's important to share the project progress using the Earned Value technique. You are preparing your status report for the period ending October 28th. Your project started February 27th. Assume that the project is executed 5 days per week and 8 hours per day with some additional hours that amount to 8 hours every Saturday and Sunday. The project manager's table of activities are noted below.
ID |
Activity |
Original Duration (days) |
Actual Duration (days) |
Actual Start Date |
Actual Finish Date |
% Complete |
Original Budget |
Actual Budget |
10 |
Site Prep |
8 |
9 |
2/27 |
4/26 |
100 |
$500,000 |
$600,000 |
20 |
Substructure |
12 |
11 |
5/1 |
7/18 |
100 |
$1,500,000 |
$1,350,000 |
30 |
Super Substructure |
18 |
- |
7/20 |
- |
75 |
$2,000,000 |
$1,450,000 |
40 |
Exterior |
6 |
- |
- |
- |
0 |
$400,000 |
- |
50 |
Interior |
14 |
- |
8/31 |
- |
50 |
$1,800,000 |
$1,000,000 |
60 |
Services |
10 |
- |
- |
- |
0 |
$1,000,000 |
- |
70 |
Cleanup |
4 |
- |
- |
- |
0 |
$200,000 |
Question 2: Calculate the Planned Value (BCWS) based on the original budget, the original duration, and the number of weeks between the planned early start date and the status date (October 28th for the activities that are in progress. This calculation will provide the amount of money the project has spent up to October 28th?
Activity 30 - Super substructure
Original Budget = $2,000,000
Original Duration = 18 Weeks
Number of Weeks between Planned Start Date and Status State = ______ #Weeks to status date (From Question 1.
BCWS = #Weeks to status date / Original Duration * Original Budget
BCWS = ______________________________
Activity 50 - Interior
Original Budget = $1,800,000
Original Duration = 14 Weeks
Number of Weeks between Planned Start Date and Status State =_______ #Weeks to status date (From Question 1).
BCWS = #Weeks to status date / Original Duration * Original Budget
BCWS = ______________________________
Activity 30 - Super substructure
Original Budget = $2,000,000
Original duration = 18 weeks
Number of weeks between planned start date and status state = 13.5
BCWS = Weeks to status date / Original Duration * Original Budget
BCWS = (13.5/18) X $2,000,000
= $1,500,000
Activity 50 - Interior
Original Budget = $1,800,000
Original Duration = 14 Weeks
Number of weeks between planned start date and status state = 8
BCWS = Weeks to status date / Original Duration * Original Budget
BCWS = (8/14) X $1,800,000
= $1,028,571.43
*If you like the answer, please give it a thumbs-up. It will be highly appreciated*
Instructions: You are preparing a status report for your project sponsor and stakeholders and it's important...
Question 1: The following data and table illustrate a small project: Activity A was completed on schedule • Activity B started as planned but it is expected to take four weeks more Activity C started as planned but finished one week later • %age of completion of activity D is 60% ACWP at the end of week 10 = SR 90400 Activity Original Planned Start Time Original Planned Finish Time Wage Complete Amount Completed BCWP Amount Scheduled BCWS Amount Spent...
Earned value calculation Based on the following Project data, answer the questions a and b. Activity Duration Predecessors Task Budget A 7 days -- $16,850 B 10 days -- $22,500 C 8 days B $16,000 D 10 days A $12,790 E 7 days B $8,500 F 4 days D $10,550 At the end of Day 10, the status of the project is as follows. Activity % Complete Actual Cost A 100% $18,000 B 100% $23,000 C 0% $0 D 10%...
Your company was hired as a subcontractor for a client's "Destiny project and awarded two main work packages within that project. Your company refers to this project internally using the cost code "P2 2019". You're given the table below that lists the work packages, their cost code, their budget, and their scheduled start day and end day (as agreed upon with the main contractor). The start and end days are measured in working days after the main project's start. So,...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
Assume the following: You are a contractor and have just been awarded a Greenfield Project. A budget has been established to install 20,000ft of pipe at an estimated 15,000 man hours and an estimated billable cost of $700,000. The original schedule planned for 4,000ft of pipe to be installed per day by a 300-man crew working a 10-hour shift (anticipated). The job was scheduled to start in Monday and finish on Friday. On Monday 2,000ft of pipe was installed. On...
Assume the following: You are a contractor and have just been awarded a Greenfield Project. A budget has been established to install 20,000ft of pipe at an estimated 15,000 man hours and an estimated billable cost of $700,000. The original schedule planned for 4,000ft of pipe to be installed per day by a 300-man crew working a 10-hour shift (anticipated). The job was scheduled to start in Monday and finish on Friday. On Monday 2,000 ft of pipe was installed....
You are appointed as a site engineer representing a consulting firm to supervise a construction project. The project will start on the 1 January and is expected to be completed in 10 month. The cost break down for the project is as shown in Table 1 below. Table 1. Cost Breakdown of the Project Work Cost Rd Seart Finish 100 000 Jan 31 Jan piling 300 000 Feb 1 March Sub-structure 300 000 15 Feb 15 May Beams Stab-deck 80...
Step 1: Design and create the tables You must create additional tables to hold Project and Activity Data. A project represents the construction of a facility with a limited scope of work and financial funding. A Project can be composed of many activities which indicate the different phases in the construction cycle. Example Project Name: Bobba Fett’s Bounty Chase Ride An activity represents the work that must be done to complete the project. Example Activity Name: For Example activity name...
QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...
Consider the proposal. Should SCF accept or reject ACL’s request? If you were the project manager, which option would you select? What risks are involved with your choice and with ACL’s request? Shell Case Fabricators BACKGROUND Shell Case Fabricators (SCF) designs and builds shell casings that enclose electronic products such as calculators, cell phones, modems. Typically the cases are plastic or plastic compounds. SCF has six different production lines that cover different types of product. For example, the largest high...