Question

Assume the following: You are a contractor and have just been awarded a Greenfield Project. A...

Assume the following: You are a contractor and have just been awarded a Greenfield Project. A budget has been established to install 20,000ft of pipe at an estimated 15,000 man hours and an estimated billable cost of $700,000. The original schedule planned for 4,000ft of pipe to be installed per day by a 300-man crew working a 10-hour shift (anticipated). The job was scheduled to start in Monday and finish on Friday. On Monday 2,000ft of pipe was installed. On Tuesday 3,500 ft of pipe was installed and on Wednesday 1,000ft of pipe was installed. Actual cumulative man hours incurred to-date is 9,500 hrs. In addition, your crew has installed 1,200ft of pipe and has incurred 2,040 of man hours to-date working on Change Orders. Note: Assume that $200,000 has been billed to the client to-date.

e. What is the current schedule variance?

f. What is the current cost variance? How many man hours are left to be earned?

g. How many actual man hours will be incurred in order to earn the remaining man hours?

h. What is the current projected EAC (Estimate at Completion) in terms of man hours?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Please remember above question based on Project accounting + Standard costing basis . I have created step by step analysis to derive each and every number .

schedule Variance = Negative $ 45755 ( Negative mean Project is behind schedule -which is not sounds good )

Schedule variance is showing project is behind schedule and costs are over run , which is damaging Project Profitability

What is the current Schedule variance ( SV)
The job was scheduled to start Monday and finished on Friday
Ft
Monday         2,000
Tuesday         3,500
Wed         1,000
Total         6,500
Addition - Crew has installed         1,200
Total completion till date         7,700
Contract to completed
$ 20,000+ $1200 ( Additional Installation)      21,200
% completion 36%
formula $( 7700/21200)
Schedule Variance ( SV) Earned $ value - Planned $ value ( as per Formula - Standard costing)
Schedule Variance ( SV) 2,54,245 - 3,00,000     -45,755
Earned $ Value % completion * Estimated Billable cost
Estimated Billable cost 7,00,000
% completion 36%
Earned $ Value 2,54,245
Planned $ Value
Estimated Billable cost 7,00,000
Number of days worked                 3 ( Mon- Wed)
Planned $ Value 3,00,000
('700000/7* No of Hrs worked)

Cost variance - Negative mean Projects are running by Excess cost

Cost variance
Actual Cumulative man Hrs incurred till date (Hr)                        9,500
Additional Man hr                        2,040
Total Man Hr                     11,540
Estimated Man hr                     15,000
Estimated Billable cost                  7,00,000
Rate / HR                              47
Actual cost                  5,38,533
( Actual man hr -11540* rate / hr ( 47)
Cost variance Earned $ value - Actual labour cost ( as per Formula - Standard costing)
Earned $ Value (a)                  2,54,245
Actual cost(b)                  5,38,533
Cost variance (a-b)                -2,84,288

g) answer G is basically based on above 2 answer . Eventhough I have explained all sources again below for easy reference

g) How many actual man hrs
Contract to complete                     21,200
$ 20,000+ $1200 ( Additional Installation)
Estimated Man hr                     15,000
Current rate per work(a)                          1.41 ('21200/15000)
Hours left to earned(b)                        9,555 ('15000-5445)
Remaining Hrs( a*b)-c                     13,504
How many actual man hrs( a)*( c)                     19,086
Estimated Man hr                     15,000
Earned man Hrs                        5,445 ('15000*36.3%)
% completion 36.30%
Estimated Man hr                     15,000

EAC calculation based on CPI ( Index ) so used CPI formula to derive below number.

Earned Value and Actual Cost already calculated as above .  

h) EAC ( Estimated of Completion)
To calculated EAC , we need to calculated Index
CPI ( Index) Earned $ Value         2,54,245
Actual cost(b)         5,38,533           0.47
Estimated Billable cost-$                  7,00,000
EAC ( Estimated of Completion)-$               14,82,715 700000/0.47
Add a comment
Know the answer?
Add Answer to:
Assume the following: You are a contractor and have just been awarded a Greenfield Project. A...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Assume the following: You are a contractor and have just been awarded a Greenfield Project. A...

    Assume the following: You are a contractor and have just been awarded a Greenfield Project. A budget has been established to install 20,000ft of pipe at an estimated 15,000 man hours and an estimated billable cost of $700,000. The original schedule planned for 4,000ft of pipe to be installed per day by a 300-man crew working a 10-hour shift (anticipated). The job was scheduled to start in Monday and finish on Friday. On Monday 2,000 ft of pipe was installed....

  • engineering economics A contractor has been awarded the contract to construct a 6-mile-long tunnel in the...

    engineering economics A contractor has been awarded the contract to construct a 6-mile-long tunnel in the mountains. During the 5-year construction period, the contractor will need water from nearby stream. She will construct a pipeline to carry the water to the main construction yard, an analysis of costs for various pipe sizes is as follows 3. Pipe Sizes (in) 24,000 28,000 30,000 Installed cost of pipeline and pump 20,000 Cost per hour for 1.5 0.75 0.55 0.35 Salvage value of...

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • You have started working as a cost accountant for a firm that has only been in...

    You have started working as a cost accountant for a firm that has only been in business for one month. The firm is able to buy a new type of biodegradable plastic at a fixed price of $100 per roll. The plastic is then cut and sealed to make garbage bags. Fixed factory overhead is estimated to be $125,000 per month. During this past month, 8,000 cartons of garbage bags were produced, which represents 80% of the activity volume. You...

  • You have started working as a cost accountant for a firm that has only been in...

    You have started working as a cost accountant for a firm that has only been in business for one month. The firm is able to buy a new type of biodegradable plastic at a fixed price of $100 per roll. The plastic is then cut and sealed to make garbage bags. Fixed factory overhead is estimated to be $125,000 per month. During this past month, 8,000 cartons of garbage bags were produced, which represents 80% of the activity volume. You...

  • You have recently been employed as a junior accountant at Thrones Ltd, a manufacturer of a...

    You have recently been employed as a junior accountant at Thrones Ltd, a manufacturer of a miniature statue based on a popular TV show character. Unfortunately, your supervisor, the main company accountant, has been injured in a recent horse riding accident and is away from work for some time. The company CEO, after hearing you have recently graduated from a prestigious university with great results in management d you to prepare a variance report for a management meeting later in...

  • only part b, thanks Question 5 (24 marks) You have recently been employed as a junior...

    only part b, thanks Question 5 (24 marks) You have recently been employed as a junior accountant at Thrones Ltd, a manufacturer of a miniature statue based on a popular TV show character. Unfortunately, your supervisor, the main company accountant, has been injured in a recent horse riding accident and is away from work for some time. The company CEO, after hearing you have recently graduated from a prestigious university with great results in management accounting, has asked you to...

  • Question 5 (24 marks) You have recently been employed as a junior accountant at Thrones Ltd,...

    Question 5 (24 marks) You have recently been employed as a junior accountant at Thrones Ltd, a manufacturer of a miniature statue based on a popular TV show character. Unfortunately, your supervisor, the main company accountant, has been injured in a recent horse riding accident and is away from work for some time. The company CEO, after hearing you have recently graduated from a prestigious university with great results in management accounting, has asked you to prepare a variance report...

  • QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an...

    QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...

  • You have just been hired as a new management trainee by Earrings Unlimited, a distributor of...

    You have just been hired as a new management trainee by Earrings Unlimited, a distributor of earrings to various retail outlets located in shopping malls across the country. In the past, the company has done very little in the way of budgeting and at certain times of the year has experienced a shortage of cash. Since you are well trained in budgeting, you have decided to prepare a master budget for the upcoming second quarter. To this end, you have...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT