As per the expert guidelines we have to answer only the first question.
1) The correct answer is option c) It is based on project cost estimates and is separate from the project management plan.
As the cost management process is not separate from the project management plan therefore this option is not the characteristic of project management process.
QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an...
Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....
Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...
4. You are the project finance manager on a project that is coming in over budget and requires a cost change through the cost change control system. You know all of the following statements are true regarding the Control Costs process except A description of how cost changes should be managed and controlled is found in the cost management plan. Approved cost changes are reflected in the cost baseline. The equation, (BAC-AC)/(BAC-EV) is used to determine the cost performance that...
Here is a practical example of EVM (Earned Value Management). Three values, BCWS, BCWP, and AC, are all cumulative. Acronyms: BCWS (Budgeted Cost of Work Scheduled) is equal to PV (Planned Value). BCWP (Budgeted Cost of Work Performed) is equal to EV (Earned Value). AC (Actual Cost) is the actual costs that we pay for the works. Variances: Schedule variance: when BCWP - BCWS is negative, the project is behind schedule, when the value is 0, it is on schedule,...
I need help with the attached assignment. I attached the question and completed assigment. I just need help with answering one more question which is which is: Discuss a strategy that you would use to communicate the status of the project to stakeholders? Project Monitoring and Control Assignment Complete the following items for this assignment: 1. Read through the Case 13.1 Tree Trimming Project Case in Larson and Gray. Respond to Questions 1 and 2 of the case. Use Microsoft...
Choose the closest answer a, b, c ord for the following questions Q4 (40) Choos A project manager performs Earned Value Analysis and finds the foll results: EV: 250,000; PV: 200,000; AC 275,000; BAC is 500,000. What AC is 500,000. What is right A. EAC-400,000 75,000 B. EAC - 550,000 C. BTC - 400,000 D. ETC - • Project costs are over budget when A CPI <1. B. CPI > 1. C. CPI <0. D. SPI-1. You are calculating PERT...
QUESTION 23 Current challenges in operations Management include all of the following EXCEPT: lean operations increased communication cost. rapid product development. sustainability mass customization how many hours would the plant have to work to produce 1000 parts? QUESTION 24 A small metal shop operates 10 hours each day, producing 100 parts/hour. If productivity were increased 20 between 9 and 10 hours between 2 and 6 hours less than 2 hours between 6 and 8 hours between 8 and 9 hours...
Complete the following items for this assignment: 1. Read through the Case 13.1 Tree Trimming Project Case in Larson and Gray. Respond to Questions 1 and 2 of the case. Use Microsoft Excel to complete this item and include all calculations in your Excel file. Note that showing all calculations in Excel is required. 2. Complete Appendix Exercise 2 at end of Chapter 13 in Larson and Gray. Specifically, complete the table on pp. 509-510 in the textbook (note th...
Question 9 Below is the time phased baseline budget for a project and a table showing the progress as of End of Period 7. 2 Baseline PV Total Task Time Period PV 0 1 3 5 6 7 8 10 11 A 30 15 15 40 20 20 с 80 10 10 10 10 20 20 D 30 5 5 5 5 10 E 20 5 5 5 5 F 40 10 20 5 5 10 5 5 PV by...
a. Find the FV of $1,000 invested to earn 10% annually 5 years from now. Answer this question by using a math formula and also by using the Excel function wizard. Inputs: PV = 1000 I/YR = 10% N = 5 Formula: FV = PV(1+I)^N = Wizard (FV): $1,610.51 Note: When you use the wizard and fill in the menu items, the result is the formula you see on the formula line if you click on cell E12. Put the...