Question

QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify varian
QUESTION 3 If cumulative PV 100, cumulative EV-98 and cumulative AC- 104, the project is likely to be: Item PV 10,000 9,000 A
QUESTION 4 BAC 200 PV= 100 AC 120 EV-80 Assuming that all future work will be performed at the budgeted rate, the estimate to
QUESTION 5 BAC- 200 PV 100 AC 120 EV 80 Assuming that what the project has experienced to date can be expected to continue in
QUESTION 6 BAC 200 PV- 100 AC-120 EV 80 Assuming that future work will be performed at an efficiency rate that considers both
QUESTION 7 During the sixth monthly update on a 10-month. $300,000 project, analysis of the earned value management data s S1
QUESTION 9 Earned value management (EVM) is a commonly used: peen installed in the project as of the status date. Method of m
QUESTION 11 If cumulative Pv-100, cumulative EV- 98 and cumulative AC 104, the project is likely to be PV 10,000 9,000 8000 7
media%2F01d%2F01d8bbb2-aad8-41f0-99a3-4b
0-137045 I&content id 12132653 1&step-n QUESTION 13 3.8 points Save Answer You have been promoted to the position of project
QUESTION 14 ВАС 200 PV 100 AC 120 EV 80 Assuming that all future work will be performed at the budgeted rate, the estimate at
QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the degree to which activity cost estimates, will be rounded up or down 3.8 points Save A QUESTION 2 The cost performance baseline has all of the following characteristics EXCEPT: It is developed as a summation of the approved budgets for the different schedule activities. It is typically displayed in the form of an S-curve. It is the ap used as a basis for comparison with actual results. pproved version of the time-phased project budget, excluding any management reserves, and is O It shows the actual cost expenditures throughout the project life cyele.
QUESTION 3 If cumulative PV 100, cumulative EV-98 and cumulative AC- 104, the project is likely to be: Item PV 10,000 9,000 AC 11,000 8,0007 EV 10,000 7,000 8,000 5,000 2 8,0008,000 7,000 7,000 Which item has the LOWEST SPI? Item 4 Item 2. Item 1. Item 3
QUESTION 4 BAC 200 PV= 100 AC 120 EV-80 Assuming that all future work will be performed at the budgeted rate, the estimate to complete (ETC) is: 120. 200 140 180
QUESTION 5 BAC- 200 PV 100 AC 120 EV 80 Assuming that what the project has experienced to date can be expected to continue in the future, the estimate at completion (EAC) is 325 350 O375 300.
QUESTION 6 BAC 200 PV- 100 AC-120 EV 80 Assuming that future work will be performed at an efficiency rate that considers both the cost and schedule performance indices because project schedule is a factor that impacts future effort, the estimate at completion (EAC) is: 345. Click Save and Submit to save and submit. Click Save All Answers to save all answers. Save All Ans
QUESTION 7 During the sixth monthly update on a 10-month. $300,000 project, analysis of the earned value management data s S150, measures EXCEPT hows that the cumulative PV is $190.000, the cumulative AC is $120,000, and the cumulative EV is 000. In planning its action, the project management team can conclude all of the following from these Continuing performance at the same efficiency with no management intervention, the project will probably be completed ahead of schedule and over budget. Less has been spent than was planned Less has been accomplished than was planned be completed behind schedule and under budget Continuing performance at the same efficiency with no management intervention, the project will probably QUESTION 8 Earned value (EV) involves all of the following EXCEPT: Value of the work performed expressed in ternms of the budget authorized for that work. @Progress measurement criteria, which should be established for each WBS component to measure work in progress. Budget associated with the authorized work that has been completed. O Actual cost for an activity or work breakdown structure WBS) component
QUESTION 9 Earned value management (EVM) is a commonly used: peen installed in the project as of the status date. Method of measuring the amount of money that has been spent on the project to date. Analysis of the sum of the labour costs that have been incurred on the project to date. Method of performance measurement for projects. QUESTION 10 BAC = 200 PV 100 AC 120 EV 80 Assuming that what the project has experienced to date can be expeeted to continue in the future, the variance at completion (VAC) is: +100. 80. e -100 +200
QUESTION 11 If cumulative Pv-100, cumulative EV- 98 and cumulative AC 104, the project is likely to be PV 10,000 9,000 8000 7,000 Item AC 11,000 8,000 8,000 7,000 EV 10,000 7,000 8000 ,000 Which item is MOST over budget? Item 4 Item 3 Item 1 ltem 2

0-137045 I&content id 12132653 1&step-n QUESTION 13 3.8 points Save Answer You have been promoted to the position of project manager for a large project, due to the abrupt transfer of the us project manager. On the first day in your new, exciting position, you find a folder on your desk entitled: Earned Value Management. In that folder, you find only the following chart related to your project with the Data Date of a few days ago: Based on this chart, you conclude that: The performance on this project compared to budget and schedule cannot be determined because this chart does not show any values. The project is below budget but probably behind schedule. The project is below budget and probably ahead of schedule. The project is over budget and probably behind schedule.
QUESTION 14 ВАС 200 PV 100 AC 120 EV 80 Assuming that all future work will be performed at the budgeted rate, the estimate at completion (EAC) is: 240. 200. 260. 220. QUESTION 15 Project Cost Management includes all of the folloving processes EXCEPT Determine budget Level resources. Plan cost management Control costs
0 0
Add a comment Improve this question Transcribed image text
Answer #1

As per the expert guidelines we have to answer only the first question.

1) The correct answer is option c) It is based on project cost estimates and is separate from the project management plan.

As the cost management process is not separate from the project management plan therefore this option is not the characteristic of project management process.

Add a comment
Know the answer?
Add Answer to:
QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question...

    Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • 4. You are the project finance manager on a project that is coming in over budget...

    4. You are the project finance manager on a project that is coming in over budget and requires a cost change through the cost change control system. You know all of the following statements are true regarding the Control Costs process except A description of how cost changes should be managed and controlled is found in the cost management plan. Approved cost changes are reflected in the cost baseline. The equation, (BAC-AC)/(BAC-EV) is used to determine the cost performance that...

  • Here is a practical example of EVM (Earned Value Management). Three values, BCWS, BCWP, and AC,...

    Here is a practical example of EVM (Earned Value Management). Three values, BCWS, BCWP, and AC, are all cumulative. Acronyms: BCWS (Budgeted Cost of Work Scheduled) is equal to PV (Planned Value). BCWP (Budgeted Cost of Work Performed) is equal to EV (Earned Value). AC (Actual Cost) is the actual costs that we pay for the works. Variances: Schedule variance: when BCWP - BCWS is negative, the project is behind schedule, when the value is 0, it is on schedule,...

  • I need help with the attached assignment. I attached the question and completed assigment. I just...

    I need help with the attached assignment. I attached the question and completed assigment. I just need help with answering one more question which is which is: Discuss a strategy that you would use to communicate the status of the project to stakeholders? Project Monitoring and Control Assignment Complete the following items for this assignment: 1. Read through the Case 13.1 Tree Trimming Project Case in Larson and Gray. Respond to Questions 1 and 2 of the case. Use Microsoft...

  • Choose the closest answer a, b, c ord for the following questions Q4 (40) Choos A...

    Choose the closest answer a, b, c ord for the following questions Q4 (40) Choos A project manager performs Earned Value Analysis and finds the foll results: EV: 250,000; PV: 200,000; AC 275,000; BAC is 500,000. What AC is 500,000. What is right A. EAC-400,000 75,000 B. EAC - 550,000 C. BTC - 400,000 D. ETC - • Project costs are over budget when A CPI <1. B. CPI > 1. C. CPI <0. D. SPI-1. You are calculating PERT...

  • QUESTION 23 Current challenges in operations Management include all of the following EXCEPT: lean operations increased...

    QUESTION 23 Current challenges in operations Management include all of the following EXCEPT: lean operations increased communication cost. rapid product development. sustainability mass customization how many hours would the plant have to work to produce 1000 parts? QUESTION 24 A small metal shop operates 10 hours each day, producing 100 parts/hour. If productivity were increased 20 between 9 and 10 hours between 2 and 6 hours less than 2 hours between 6 and 8 hours between 8 and 9 hours...

  • Complete the following items for this assignment: 1. Read through the Case 13.1 Tree Trimming Project...

    Complete the following items for this assignment: 1. Read through the Case 13.1 Tree Trimming Project Case in Larson and Gray. Respond to Questions 1 and 2 of the case. Use Microsoft Excel to complete this item and include all calculations in your Excel file. Note that showing all calculations in Excel is required. 2. Complete Appendix Exercise 2 at end of Chapter 13 in Larson and Gray. Specifically, complete the table on pp. 509-510 in the textbook (note th...

  • Question 9 Below is the time phased baseline budget for a project and a table showing...

    Question 9 Below is the time phased baseline budget for a project and a table showing the progress as of End of Period 7. 2 Baseline PV Total Task Time Period PV 0 1 3 5 6 7 8 10 11 A 30 15 15 40 20 20 с 80 10 10 10 10 20 20 D 30 5 5 5 5 10 E 20 5 5 5 5 F 40 10 20 5 5 10 5 5 PV by...

  • a.   Find the FV of $1,000 invested to earn 10% annually 5 years from now. Answer...

    a.   Find the FV of $1,000 invested to earn 10% annually 5 years from now. Answer this question by using a math formula and also by using the Excel function wizard. Inputs: PV = 1000 I/YR = 10% N = 5 Formula: FV = PV(1+I)^N = Wizard (FV): $1,610.51 Note: When you use the wizard and fill in the menu items, the result is the formula you see on the formula line if you click on cell E12. Put the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT