Question

Choose the closest answer a, b, c ord for the following questions Q4 (40) Choos A project manager performs Earned Value Analy

0 0
Add a comment Improve this question Transcribed image text
Answer #1

2. Project costs are over budgeted when CPI is less than 1.

Hence the correct answer is option A.

3.te - Expected teme = ?? tm = Most likely time = 280 days to = optimistic teme = Eortiest time = tp = Longest time = 330 days

4. Dummy activities are used to represent the dependencies between different events and activities.

Hence the correct answer is option B.

Add a comment
Know the answer?
Add Answer to:
Choose the closest answer a, b, c ord for the following questions Q4 (40) Choos A...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A project has just completed its 87th task of a total of 150 tasks in its...

    A project has just completed its 87th task of a total of 150 tasks in its project plan. The project has a total budget of $1,500,000. It was scheduled to have spent $500,000 at this point in the plan, but has actually spent only $400,000. The project manager estimates that the value of the work actually finished is $300,000. What are the spending and schedule variances for the project? What are the SPI and CPI? What is the EAC, assuming...

  • Earned value calculation Based on the following Project data, answer the questions a and b. Activity...

    Earned value calculation Based on the following Project data, answer the questions a and b. Activity Duration Predecessors Task Budget A 7 days -- $16,850 B 10 days -- $22,500 C 8 days B $16,000 D 10 days A $12,790 E 7 days B $8,500 F 4 days D $10,550 At the end of Day 10, the status of the project is as follows. Activity % Complete Actual Cost A 100% $18,000 B 100% $23,000 C 0% $0 D 10%...

  • to chapter 1. Given the following information for a one-year project, answer the following questions. Recall...

    to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...

  • 1 What should not be covered by a risk management plan? a Roles and responsibilities for...

    1 What should not be covered by a risk management plan? a Roles and responsibilities for handling project risks b Timing of project risk management activities c The methodological approach used for risk management d Individual risks and potential responses to them 2 You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile been finished. You perform earned value analysis and get the following...

  • 1 In regard to Project Work, which activity refers to “reviewing the progress and capturing project...

    1 In regard to Project Work, which activity refers to “reviewing the progress and capturing project performance data with reference to the project plan, developing performance measures, and communicating performance information?” a. controlling b. monitoring c. executing d. managing 3 Which of the following formulas represents the schedule performance index (SPI)? a. EV/PV b. EV PV c. EV AC d. EV/AC 4 If your sponsor asks for an estimate as to how much more money your team needs to complete...

  • Activity Predecessor Duration (weeks) a none 12 b none 5 c a, b 7 d c,...

    Activity Predecessor Duration (weeks) a none 12 b none 5 c a, b 7 d c, e 2 e b 8 f e 9 g d 5 h f,g 8 Your firm is implementing a balanced scorecard. As the project manager, you need to make sure the project is completed on time and on-budget. The table below lists the steps that need to be complete. The data analysis team members are going to be late delivering some key data points...

  • Please solve these questions by choosing the correct answer 25 B) Work Breakciown Siructure is: A)...

    Please solve these questions by choosing the correct answer 25 B) Work Breakciown Siructure is: A) A hierarchically-organized depiction of the project organization ) A hierarchical representation of project risks 5 C D) A hierarchical structure of resource categories A deliverables-oriented decomposition of the project work Based on your experience with three similar past projects, you estimate an 8-10 month implementation time frame for a new project. What is this type of estimation technique called? A) Three-Point Estimating B) Bottom-Up...

  • You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Answer each of the questions below to complete your assignment. Use the same numbers as the assignment when you give your answer, I only grade answers that correspond the assignment questions. 1. For this one-year project calculate: a. cost variance, b. schedule variance, C. cost performance index (CPI),...

  • 33) Span of control refers to: A) The number of departments involved in a project. B) The number of days that the pr...

    33) Span of control refers to: A) The number of departments involved in a project. B) The number of days that the project manager is allowed to complete the project. C) The number of levels from top to bottom in an organization D) The number of employees one person supervises. 34) A writer estimates it will take three months to generate spiffy documents to accompany a seminal work in operations management. He grossly underestimates the time required and misses his...

  • 5. Chapter 2 Summary Read the following scenario and then answer the questions about team and...

    5. Chapter 2 Summary Read the following scenario and then answer the questions about team and intercultural communication in the workplace. Noreen is a creative manager overseeing a project with a team of six members. Noreen’s team is located in Tokyo, and most of the members have worked together before; however, they have a new addition to the team for this project. The new team member is from the company’s Atlanta offices. What is the first step that Noreen should...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT