Question

Activity Predecessor Duration (weeks) a none 12 b none 5 c a, b 7 d c,...

Activity Predecessor Duration (weeks)
a none 12
b none 5
c a, b 7
d c, e 2
e b 8
f e 9
g d 5
h f,g 8

Your firm is implementing a balanced scorecard. As the project manager, you need to make sure the project is completed on time and on-budget. The table below lists the steps that need to be complete. The data analysis team members are going to be late delivering some key data points that are needed to complete the project (activity B). How many weeks can this activity be delayed without delaying the completion of the project?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Activity Duration, D Early start, ES=Max of early finish of preceding activities Early finish, EF = ES + D Late finish, LF= Min of LS of successor activities Late start, LS= LF - D Total slack= LF-EF
A 12 0 12 12 0 0
B 5 0 5 9 4 4
C 7 12 19 19 12 0
D 2 19 21 21 19 0
E 8 5 13 17 9 4
F 9 13 22 26 17 4
G 5 21 26 26 21 0
H 8 26 34 34 26 0

Slack for B is 4

Hence, activity B be delayed without delaying the completion of the project by 4 weeks.

Add a comment
Know the answer?
Add Answer to:
Activity Predecessor Duration (weeks) a none 12 b none 5 c a, b 7 d c,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT