Question

25 B) Work Breakciown Siructure is: A) A hierarchically-organized depiction of the project organization ) A hierarchical repr

Please solve these questions by choosing the correct answer

0 0
Add a comment Improve this question Transcribed image text
Answer #1

OLUN Question I: work break down structene is to [ A deliverables -oriented decomposition of the O project work]. Work GreakdOM Question 3% (PI 20.96 cost performance index Measures the cost effectiveness of the project a cost performance index of 1.

Add a comment
Know the answer?
Add Answer to:
Please solve these questions by choosing the correct answer 25 B) Work Breakciown Siructure is: A)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • to chapter 1. Given the following information for a one-year project, answer the following questions. Recall...

    to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...

  • You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Answer each of the questions below to complete your assignment. Use the same numbers as the assignment when you give your answer, I only grade answers that correspond the assignment questions. 1. For this one-year project calculate: a. cost variance, b. schedule variance, C. cost performance index (CPI),...

  • 1 In regard to Project Work, which activity refers to “reviewing the progress and capturing project...

    1 In regard to Project Work, which activity refers to “reviewing the progress and capturing project performance data with reference to the project plan, developing performance measures, and communicating performance information?” a. controlling b. monitoring c. executing d. managing 3 Which of the following formulas represents the schedule performance index (SPI)? a. EV/PV b. EV PV c. EV AC d. EV/AC 4 If your sponsor asks for an estimate as to how much more money your team needs to complete...

  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

  • At week 10 of a project below to improve distance learning platform, assume that the planned...

    At week 10 of a project below to improve distance learning platform, assume that the planned values (PV) are based on time proportionality but the “% Complete” values for earned values (EV) are from the workers actually doing the tasks. ACTIVITY PRE- DECESSORS DURATION (WEEKS) BUDGET ($) ACTUAL COST ($) % COMPLETE A - 5 500 640 100 B A 3 300 400 100 C B 4 320 310 80 D B 6 600 250 60 E C,D 3 300...

  • 1 What should not be covered by a risk management plan? a Roles and responsibilities for...

    1 What should not be covered by a risk management plan? a Roles and responsibilities for handling project risks b Timing of project risk management activities c The methodological approach used for risk management d Individual risks and potential responses to them 2 You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile been finished. You perform earned value analysis and get the following...

  • Earned value calculation Based on the following Project data, answer the questions a and b. Activity...

    Earned value calculation Based on the following Project data, answer the questions a and b. Activity Duration Predecessors Task Budget A 7 days -- $16,850 B 10 days -- $22,500 C 8 days B $16,000 D 10 days A $12,790 E 7 days B $8,500 F 4 days D $10,550 At the end of Day 10, the status of the project is as follows. Activity % Complete Actual Cost A 100% $18,000 B 100% $23,000 C 0% $0 D 10%...

  • solv rroject Manager You are required to estimate the time to paint a large wall. You...

    solv rroject Manager You are required to estimate the time to paint a large wall. You know it takes two hour one square foot of wall. The wall has an area of 30 square foot. So you estimate that hours to paint the wall. Which estimation model are you using? A) Bottom-up J S , J UB Parametric C) Analogous v ie j oy - D) Expert judgment Cost baseline is usually represented using which curve or line? A) S...

  • Choose the closest answer a, b, c ord for the following questions Q4 (40) Choos A...

    Choose the closest answer a, b, c ord for the following questions Q4 (40) Choos A project manager performs Earned Value Analysis and finds the foll results: EV: 250,000; PV: 200,000; AC 275,000; BAC is 500,000. What AC is 500,000. What is right A. EAC-400,000 75,000 B. EAC - 550,000 C. BTC - 400,000 D. ETC - • Project costs are over budget when A CPI <1. B. CPI > 1. C. CPI <0. D. SPI-1. You are calculating PERT...

  • Please answer a describe questions 10-14. I know its blurry so here are the numbers. Activity...

    Please answer a describe questions 10-14. I know its blurry so here are the numbers. Activity Exp Cost Exp % complete Actual % complete Actual cost to date Sales price $2.5M 100 100 $1.7M Pour communication $12.3M 90 85 $10.5 communication $8.5M 80 65 $7.5M 10. The scheduled Variance is? A. $2.6M B. -$2.6M C. $1.89M D. -$1.89M E. $0 11. The schedule performance index is? A. 1.11 B. 1.00 C. 0.90 D. 1.75 E. 0.76 12. The cost performance...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT