Question

rroject Manager You are required to estimate the time to paint a large wall. You know it takes two hour one square foot of wa

solv

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Q1) B) Parametric

Explanation: parametric estimation uses the relationship between the variables to estimate duration or cost. A parametric technique is determined by identifying unit cost or duration and the number of units required by project.

Q2) A) S or progress curve

Explanation: We use S curve to show cost baseline. The cost is low in the beginning and end , and high in the middle of the project..

Q3) C) Crashing

Explanation: All the options above can get the project on schedule.But we choose crashing as the correct option because it involves addition of extra resources to reduce duration. This fulfillment is same as what is required in the question. Where as fast tracking involves overlapping of activity to reduce duration.

Q4) D) Transfer

Explanation: We use insurance to transfer the risk from us to the insurance company. In this case by taking insurance , we are tranfering the risk to the insurance company. By taking insurance we are compensated at the time of any damage.

Q5) A) Acceptance

Explanation: By not taking any action against the employees, we are accepting the risk , as the probability of it happening is low.

Q6) D) CPI of greater than 1

Explanation: A CPI greater than 1 means the project is under budget and is a favourable situation.

Other options do not show that the project is doing well.

Add a comment
Know the answer?
Add Answer to:
solv rroject Manager You are required to estimate the time to paint a large wall. You...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • As the project manager of a large project, you have just completed the Estimate Costs process....

    As the project manager of a large project, you have just completed the Estimate Costs process. As you begin the Determine Budget process, which of the following would you require as inputs? A. Activity cost estimates, Basis of estimates B. Activity cost estimates, Activity resource estimates C. Resource breakdown structure, Agreements D. Activity cost estimates, Staff management plan

  • A-if you used a can of spray paint to write "save the ozone layer!" on the wall why would this be...

    a-if you used a can of spray paint to write "save the ozone layer!" on the wall why would this be funny? b-what causes Aurora Borealis and Aurora Australis? c-what causes the polar ozone holes? d-describe the regions of the Earth's atmosphere. e-how do volcanic eruptions affect the climate what is the greenhouse effect? what characteristic makes a gas a greenhouse gas? f-describe three human activities that generate CO2 and list two mechanisms for the uptake of CO2 g-briefly describe...

  • 5. You are taking over a project that is currently in the planning stage. The previous...

    5. You are taking over a project that is currently in the planning stage. The previous project manager worked with the team to finalize the process of defining activities, and you joined the team at the end of this process. The next process requires the determination and documentation of the relationships among project activities. Of the following, which is a tool and technique used in this process? a. Schedule Baseline b. Dependency Determination c. Activity List d. Schedule Compression You...

  • You are the manager of a auto service department at a location at a large multi-brand,...

    You are the manager of a auto service department at a location at a large multi-brand, multi-location car dealership. You have been in discussions with the company’s accounting manager to determine the management reports that are available to you. The accounting manager indicates that they can provide monthly reporting to you on the following four areas: A) efficiency data on your department’s work performance. B) quality data on your department’s work performance. C) profitability data of the whole company. D)...

  • 1 What should not be covered by a risk management plan? a Roles and responsibilities for...

    1 What should not be covered by a risk management plan? a Roles and responsibilities for handling project risks b Timing of project risk management activities c The methodological approach used for risk management d Individual risks and potential responses to them 2 You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile been finished. You perform earned value analysis and get the following...

  • (I) You have just been appointed the product manager of the "FIFO" electric blankets in a large consumer products company. As part of your new job, you want to develop an understanding of the...

    (I) You have just been appointed the product manager of the "FIFO" electric blankets in a large consumer products company. As part of your new job, you want to develop an understanding of the financial situation for your product. Your brand assistant has provided you with the following facts: a. Retail selling price                                                  $40 per unit b. Retailer's margin                                                     25% c. Jobber's margin                                                       12% d. Wholesaler's margin[1]                                              20% e. Direct factory labor                                                $2 per unit f. Raw materials                                                         $1 per...

  • Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the...

    Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the following questions. A. Create the network diagram representing the problem. B. What is the total time expected to be required to complete the project if no delays occur? C. What are the earliest and latest start and finish times for the individual activities required to meet the expected project completion time provided in question B (show your method for determining this)? D. Which are...

  • RE VIE W Vocabulary Review Matching Match the key terms in the right column with the...

    RE VIE W Vocabulary Review Matching Match the key terms in the right column with the definitions in the left column by placing the letter of answer in the space provided. 1. How unemployment taxes are filed by employers -K.-2. Physician assistants and nurse practitioners, for example 3. Defines the hierarchy of an organization a. agenda b. budget c. chain of command d. employee handbook e. Form 1-9 f. FUTA g gnevance process h. incident report i. labor relations j....

  • Hi, I am requesting your help. Some of those that I am not sure if I...

    Hi, I am requesting your help. Some of those that I am not sure if I am right? Thank you, Michelle ________________________________ You work at Ford Motor Company and are responsible for determining weekly production capacity for the Juarez, Mexico assembly plant. There are 21 days left in the production month. Your sales manager just informed you that 4,725 vehicles need to be produced in the upcoming days to meet projected sales demand in the United States 21. Your production...

  • What an Executive Summary Is An executive summary is a specific type of document that does...

    What an Executive Summary Is An executive summary is a specific type of document that does two things: it summarizes a research article, and it offers recommendations as to how information from the article can be used. Some long reports can contain an executive summary section, as indicated in the Pearson handbook. Write a 2 pahe Executive Summary In business contexts, an executive summary is always written for a specific purpose: to explain the information in the article to a...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT