Code | Budget | Start Date | End Date | Report Date | Actual Cost | % of Completion | BCWP $ | BCWS $ |
ACWP $ |
CPI $ | SPI $ |
1 | 43500 | 14 | 18 | 17 | 52200 | 100 | 43500 | 43500 | 52200 | 0.83 | 1.00 |
2 | 77500 | 16 | 19 | 17 | 30500 | 75 | 58125 | 25831 | 30500 | 1.91 | 2.25 |
101625 | 69331 | 82700 |
BCWP = Budget Cost x % of Completed
BCWS= Budget Cost x % of Schedule Time
1 = 43500* (17-14)/ (18-14)
2 = 77500 * (17-16)/ (19-16)
CPI = BCWP / ACWP
SPI = BCWP/ BCWS
B) Based on Schedule
CV = BCWP - BCWS
1 st work order = 43500 -43500 = 10875 Ans is 0
2 nd work order = 58125 -25831 = 32294 Ans is 1
Total work order = 101625 -69331 = 32294 Ans is 1
B) Based on Schedule
CV = BCWP - BCWS
1 st work order = 43500 -43500 = 10875 Ans is 0 TRACK
2 nd work order = 58125 -25831 = 32294 Ans is 1 AHEAD
Total work order = 101625 -69331 = 32294 Ans is 1 AHEAD
B) Based on Schedule
CV = BCWP - BCWS
1 st work order = 43500 -43500 = 10875 Ans is 0
2 nd work order = 58125 -25831 = 32294 Ans is 1
Total work order = 101625 -69331 = 32294 Ans is 1
C) Based on Budjet
CV = BCWP - ACWP
1 st work order = 43500 - 52200 = - 8700 Ans is -1 BEHIND
2 nd work order = 58125 - 30500 = 27625 Ans is 1 AHEAD
Total work order = 101625 -82700 = 18925 Ans is 1 AHEAD
Your company was hired as a subcontractor for a client's "Destiny project and awarded two main work packages within that project. Your company refers to this project internally using the cost...
You are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value and actual value. That means the project is _____ schedule and _____ budget. Select an answer: behind; under ahead of; under ahead of: over behind; over
Aflooring subcontractor has to install 2,600sq ft of carpet for an existing building for unit cost of $2.30 per sq ft. The subcontractor was given 10 days to finish all the work. Four days after the start of the work, he found out 1,500sqft of the carpet is installed and its actual cost was $3,150 to that date. Perform EV (earned value) analysis on the task above and answer Questions 1-11 Next → Question 1 5 pts What is the...
16. Jane is a project manager for a company that produces two special widgets each year for suppliers around the world. Jane receives a project schedule of 10 months and a budget with estimates of what it will cost to produce both widgets (shown below). The project requires 200 widgets to be produced per month for Widget A, and 100 widgets to be produced per month for Widget B. Activity Widget A Widget B Total Start Jan 1 Mar 1...
You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Answer each of the questions below to complete your assignment. Use the same numbers as the assignment when you give your answer, I only grade answers that correspond the assignment questions. 1. For this one-year project calculate: a. cost variance, b. schedule variance, C. cost performance index (CPI),...
Here is a practical example of EVM (Earned Value Management). Three values, BCWS, BCWP, and AC, are all cumulative. Acronyms: BCWS (Budgeted Cost of Work Scheduled) is equal to PV (Planned Value). BCWP (Budgeted Cost of Work Performed) is equal to EV (Earned Value). AC (Actual Cost) is the actual costs that we pay for the works. Variances: Schedule variance: when BCWP - BCWS is negative, the project is behind schedule, when the value is 0, it is on schedule,...
QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...
#1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI? What is your assessment of the project from a cost and schedule perspective? #2. A project has just completed the 87th item in its plan. It was scheduled to have spent $168,000 at...
2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...
Analyze the cost data received for the given project activities (provided in table) using earn value management technique and find the values of below questions; 1. Are we ahead or behind schedule? Find the value of variance in Rupees (Rs.) & in percentage If there is any deviation from work planned. 2. How efficiently are we using time? 3. Are we over or under budget? Express the variance in Rupees (Rs.) & in percentage. 4. How efficiently are we using...
Spot Construction builds roads, bridges, and other infrastructure. The following is the budget for a road project along with the actual results (in thousands of dollars) for the last fifteen months. Month 1 m in Actual Cost Complete $ 0 0.0% $ 700 5.5% $ 1,160 11.2% $ 1,820 13.4% $ 2,270 21.6% $ 2,810 27.5% $ 3,190 34.0% $ 3,870 36.5% $ 4,200 45.0% $ 4,710 48.8% $ 5,400 53.4% $ 5,920 56.7% $ 6,300 62.3% $ 7,190 70.0%...