Question

16. Jane is a project manager for a company that produces two special widgets each year for suppliers around the world. Jane
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Let us first understand the basic terms used in the calculations:

PV-Planned Value:- It is cost of the work that is planned to be expensed as per budget.

EV-Earned Value:- It is cost of the work that is performed as per budget.

AC-Actual Cost:- It is cost of the budget that is completed till the time.

SV-Schedule Variance:- EV – PV

CV-Cost Variance:- EV – AC

SPI(scheduled performance index) = EV / PV

CPI (cost performance index) = EV /AC

Now we calculates the initial basic terms PV,EV and AC for Widget A and B:

Widget A

PV = Per Widget $50 spent x 200 Widget per month x 6 months = $60,000

EV = Per Widget $50 spent x 800 Widget Produced = $40,000

AC = $45,000

Widget B

PV = Per Widget $100 spent x 100 Widget per month x 4 months = $40,000

EV = Per Widget $100 spent x 400 Widget Produced = $40,000

AC = $35,000

Widget A

Widget B

SV = EV-PV

$40,000-$60,000

SV = EV-PV

$40,000-$40,000

-$20,000

$0

CV = EV - AC

$40,000-$45,000

CV = EV - AC

$40,000-$35,000

-$5,000

$5,000

SPI = EV/PV

$40,000/$60,000

SPI = EV/PV

$40,000/$40,000

0.67

1

CPI = EV/AC

$40,000/$45,000

CPI = EV/AC

$40,000/$35,000

0.89

1.14

Interpretation:

SPI = 1, All work has been completed as scheduled

SPI <1, Work has not been completed as scheduled

SPI >1, Work is completed fast as scheduled before time.

CPI = 1, Team is spending as originally planned

CPI < 1, Project is over Budget

CPI > 1, Project is under Budget

Here Widget A SPI is just 0.67, i.e. it is behind schedule and CPI is 0.89, I.e. Project is over budget by $5,000 ($40,000-$45,000)

Widget B SPI is 1, i.e. its is on schedule and CPI is 1.14, i.e. Project is under budget by $5,000 ($40,000-$35,000)

Add a comment
Know the answer?
Add Answer to:
16. Jane is a project manager for a company that produces two special widgets each year...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Q4 Maria is a project manager for a company that produces two types of appliances each...

    Q4 Maria is a project manager for a company that produces two types of appliances each year for local suppliers. The project requires 200 appliances to be produced per month for Appliance A with a cost of RM 50 each, and 100 appliances to be produced per month for Appliance B with a cost of RM 100 each. Maria receives a project budget of RM 200,000 for 10 months to produce both appliances. After Maria's project team into six months...

  • Project UMUC is to produce 200 widgets and is scheduled to take five weeks. Each unit...

    Project UMUC is to produce 200 widgets and is scheduled to take five weeks. Each unit is planned to cost $90. The project is severely cost constrained. Performance data for the project at the end of week three is presented below: 120 total units were planned to be produced 130 units have actually been produced The financial manager reported that the business had actually spent $13,000 on the project by the end of week three. Answer the following questions; show...

  • Sweet Ayla Company currently has the capacity to manufacture 150,000 widgets a year. The widgets normally...

    Sweet Ayla Company currently has the capacity to manufacture 150,000 widgets a year. The widgets normally sell for $23.00 each. Sweet Ayla Company has the following costs related to manufacturing and selling 120,000 widgets: Direct materials $300,000 Direct labor $540,000 Variable manufacturing overhead $180,000 Depreciation on equipment only used for the widgets $40,000 Depreciation on factory $100,000 Salary of widget production manager $70,000 Variable selling costs (commissions) $60,000 Fixed selling costs $80,000 Total $1,370,000 Now assume that at the end...

  • Monrose Park had the following transactions during the month of November 2018. Nov 2                        Purchased 1,000 widgets...

    Monrose Park had the following transactions during the month of November 2018. Nov 2                        Purchased 1,000 widgets for $20 per unit on credit Nov 5                        Sold 900 widgets for $55 each for cash Nov 10                     Purchased 500 widgets for $25 per unit on credit Nov 18                     Sold 100 widgets for $60 each on credit Nov 29                     Sold 300 widgets for $50 each for cash Monrose Park uses a perpetual inventory system and the FIFO inventory valuation method. There were no widgets in the company’s opening...

  • Calculate the fully loaded cost of labor for your project team members. (20 points) Write only th...

    Calculate the fully loaded cost of labor for your project team members. (20 points) Write only the total fully loaded labor cost for each member. Don't wTite the cost for each activity in the table below Project Team Hours Needed forOverhead NameEach ActvityCharge RateHourly RateLabor Cest Total) C-10 E-10 Tommy 1.70 $20 Kellie 1.35 $15 B-10 Drew D-10 F-20 1.70 $15 Blake E-10 1.50 $25 esse 1.70 $25 Schedule for each task is as follows: Calculate the cost for each...

  • Software Installation: You are the project manager of the software installation project (see figure & table)...

    Software Installation: You are the project manager of the software installation project (see figure & table) below. You would like to find the minimum-cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,500 per week. Oo un D FINISH START START I Normal Normal Crash Crash Max reduction $ per Week Activity Time Cost Time Cost AI 5...

  • You are the manager of a project to improve a billing process at your firm. The...

    You are the manager of a project to improve a billing process at your firm. The table below contains the data you will need to conduct a cost analysis of the project Indirect costs are $1,600 per week, and penalty costs are $600 per week after week 12 Immediate Normal Cost Crash Cost Predecessor(s) Normal Time (weeks) Crash Time (weeks) ($) ($) Activity A 4 5,500 7,500 В 5 3 8,000 9,500 A 1 1 3,500 3,500 В 6 3...

  • Variance Project The Special Widget division manufactures a product called SW for Global Corporation. The plant...

    Variance Project The Special Widget division manufactures a product called SW for Global Corporation. The plant is a completely autonomous subsidiary that sells SWs to other subsidiaries of Global Corporation, as well as outside companies. At the beginning of the year the controller for Special Widget estimates sales and unit costs based on projections from past quarters’ data. Projected sales for the quarter are 11,000 units and budgeted unit costs are as follows: Direct costs Unit Costs Raw materials (10...

  • It is December 15 and Jane Jones, the plant manager at Acme Electric Fan Co., faces a difficult decision. The operation has been running steadily over the last 11 months. During that time, Jane worked with the production engineers to tweak the production

    It is December 15 and Jane Jones, the plant manager at Acme Electric Fan Co., faces a difficult decision. The operation has been running steadily over the last 11 months. During that time, Jane worked with the production engineers to tweak the production machinery just enough to allow for a small increase in available capacity. The plant produced 18,000 fans between January and the end of November and is scheduled to produce 2,000 fans in the month of December. The...

  • 2. The Hercules Machine Company purchases 38,000 units of a component each year at a price...

    2. The Hercules Machine Company purchases 38,000 units of a component each year at a price of $4.00 per unit. The ordering cost is $9.00 per order, and the annual holding cost is estimated at 25% of the unit value. (a) What is the economic order quantity for the component? (b) What is the total annual inventory cost for the component if it is ordered in economic quantities? (c) What is the maximum number of components in inventory at one...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT