Question

You are the manager of a project to improve a billing process at your firm. The table below contains the data you will need t

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Step 1: - Drawing Network Diagram

E 716) - Dummy 6/ 3 ESTILST) Critical Path NT(CT)

Step 2. Statement Showing activity cost slope

Activity Normal Cost ($) Crash Cost ($) Difference in cost Normal Time (weeks) Crash Time (Weeks) Difference in Time Cost Slope =
Difference in cost/ Difference in Time
A (1-2) 5500 7500 2000 4 1 3 666.67
B (1-3) 8000 9500 1500 5 3 2 750.00
C (2-4) 3500 3500 0 1 1 0 0.00
D (3-5) 6000 11500 5500 6 3 3 1833.33
E (4-6) 4000 7500 3500 7 6 1 3500.00
F (5-6) 3500 6500 3000 7 6 1 3000.00
Sub Total $30,500

.

Step 3:-

Critical path of the project is 1 - 3 - 5 - 6 having normal duration of completion of 18 Weeks.

Normal Cost of Project is $30500 (i.e. 5500+8000+3500+6000+4000+3500)

.

Step 4:- Various Paths and their progress

Various Paths Crash Time Normal Time Crashing Progress
1 - 2 - 4 - 6 1+1+6 = 8 4+1+7 = 12 12
1 - 3 - 4 - 6 3+0+6 = 9 5+0+7 = 12 12/11/10
1 - 3 - 5 - 6 3+3+6 = 12 5+6+7 = 18 18/17/16/15/14/13/12


We crash least cost activities on the critical paths Crashing Activity

Therefore,

First we crash Activity B (1 - 3) by 2 Weeks,

Second we crash Activity D (3-5) by 3 Weeks,

Finally, We crash Activity F(5-6) By 1 Weeks.

Step 5 :- Statement showing Associated cost of Project on each week.

Project Length (Weeks) Activity Crashed (each Week) Crashing Cost (Each Week) Cumulative Crashing Cost Normal Cost Indirect Cost Penalty Cost Total Cost of Project
Sum of Normal Cost ($1600 x No. Of Weeks) [($600 x No. of Weeks - 12 Weeks)]
18 - 0 0 30500 28800 3600 62900
17 B (1-3) 750 750 30500 27200 3000 61450
16 B (1-3) 750 1500 30500 25600 2400 60000
15 D (3-5) 1833.33 3333.33 30500 24000 1800 59633.33
14 D (3-5) 1833.33 5166.66 30500 22400 1200 59266.66
13 D (3-5) 1833.33 6999.99 30500 20800 600 58899.99
12 F (5-6) 3000 9999.99 30500 19200 0 59699.99

Step 6 : - Final Answer

a) The Minimum-Cost Schedule for the Project is 13 Weeks.
b) The Minimum cost Schedule cost is $ 4000 (i.e. 62900 - 58900) Less than Cost using Normal Times
Add a comment
Know the answer?
Add Answer to:
You are the manager of a project to improve a billing process at your firm. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You are the manager of a project to improve a billing process at your firm. Table 7.7 contains the data you will need to conduct a cost analysis of the project.

    You are the manager of a project to improve a billing process at your firm. Table 7.7 contains the data you will need to conduct a cost analysis of the project. Indirect costs are $1,600 per week, and penalty costs are $1,200 per week after week 12.a. What is the minimum-cost schedule for this project?b. What is the difference in total project costs between the earliest completion time of the project using "normal"times and the minimum-cost schedule you derived in...

  • Software Installation: You are the project manager of the software installation project (see figure & table)...

    Software Installation: You are the project manager of the software installation project (see figure & table) below. You would like to find the minimum-cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,500 per week. Oo un D FINISH START START I Normal Normal Crash Crash Max reduction $ per Week Activity Time Cost Time Cost AI 5...

  • The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the pr...

    The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to S150 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 15. Normal Time Crash Time Crash Cost Immediate Normal Cost ($) Activity (S) (days) (days) Predecessor(s) 6 800 1,200 A 4 6 1,000 2,200 C 600 1...

  • The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the pr...

    The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given $150 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 15. the following table. Indirect project costs amount to Normal Time Crash Time Crash Cost Immediate Normal Cost (S) Activity Predecessor(s) (S) (days) (days) 1.200 A 6 800 4 6 1,000 2 2,200 600 900 C...

  • The table below contains data for the installation of new equipment in a manufacturing process at...

    The table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation, Your company is responsible for the installation project. Indirect costs are $10,000 per week, and a penaity cost of $9,000 per week will be incurred by your company for every week the project is delayed beyond week12. Normal Time Crash Time Normal Cost Crash Cost Activity Immediate Predecessor(s) (weoks) (weeks)(5) long dash- long dash- 7,000 3,000 14,000 3,000 12,00040,000 12,000 22,000 8,000...

  • Also solve for the minimum total cost associated with finishing the project in 13 weeks and...

    Also solve for the minimum total cost associated with finishing the project in 13 weeks and the total project's duration (and of each activity according to the minimum cost schedule) The table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $10,000 per week, and a penalty cost of $8,000 per week will be incurred by your company for every week the...

  • Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,000...

    Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,0003,300B...648,0009,000CA114,0004,000      DA543,5004,000EB434,7505,500FC222,0002,000      GD114,0004,000HD,F323,5003,750IE,G323,0004,250JE215,0007,000Since no indirect cost nor penalty cost information is offered, please consider the schedule and crash cost issues only.1. Using Table of Crashing Decision, what is the earliest completion time of this project if normal times are used for all activities?A. fewer than 13 weeks; B. 13 weeks; C. 14 weeks; D. more than 14 weeks2. Using Table of Crashing Decision, what is the minimum time schedule for this project?A. fewer than 8 weeks; B. 8...

  • Table 2 contains information about an environmental cleanup project in the township of Hiles. Shorten the...

    Table 2 contains information about an environmental cleanup project in the township of Hiles. Shorten the project 3 weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. What is the project’s duration if only normal times are used? What is the minimum-cost schedule? What is the critical path for the minimum-cost schedule? TABLE 2 Activity Normal Time (wks) Crash Time (wks) Cost to...

  • Problem 3 A project for improving a billing process has the following precedence relationships and activity...

    Problem 3 A project for improving a billing process has the following precedence relationships and activity times: Activity Time (weeks) Activity Immediate Predecessor(s) A В 7 C 7 A В, С D 14 Е 10 5 D E Н F, G a. Choose the correct network diagram below. O A. O B. в O C. O D. S в Problem 3 Question Help O D. O C b. Calculate the slack for each activity. Which activities are on the critical...

  • Help Please

    Table of Crashing DecisionSince no indirect cost nor penaly cost information is offered, please consider the schedule and crash cost issues only,Using Table of Crashing Decision, what is the minimum time schedule for this project?fewer than 8 weeks8 weeks9 weeksmore than 9 weeksSince no indirect cost nor penaly cost information is offered, please consider the schedule and crash cost issues only,Using Table of Crashing Decision, what is the difference, in dollars, between the minimum-time schedule and the schedule created by...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT