Question

The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Step 1: Network diagram is following: A F Start Finish B Step 2: Draw the table listing Max crash time and Crash cost per uni

Step 4: Project Crashing using least cost method 1. Identify and list the various alternative paths through the network and t

a) Using normal times, The project duration is 22 days

b) Minimum-cost schedule:

With the minimum-cost schedule, the project duration is: 17 days

c) The critical path for the minimum-cost schedule is B-D-E-G-H

Add a comment
Know the answer?
Add Answer to:
The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the pr...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the pr...

    The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to S150 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 15. Normal Time Crash Time Crash Cost Immediate Normal Cost ($) Activity (S) (days) (days) Predecessor(s) 6 800 1,200 A 4 6 1,000 2,200 C 600 1...

  • The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in Table 1 below. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each

    The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in Table 1 below. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each day the project lasts beyond day 14. (a) What is the shortest time duration for this project regardless of cost?  (b) What is the total cost and time of the minimum-cost schedule?

  • Project Cycle

    The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in Table 1 below. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each day the project lasts beyond day 14.(a) What is the shortest time duration for this project regardless of cost?(30 marks) (b) What is the total cost and time of the minimum-cost schedule?(10 marks)Table 1:...

  • Software Installation: You are the project manager of the software installation project (see figure & table)...

    Software Installation: You are the project manager of the software installation project (see figure & table) below. You would like to find the minimum-cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,500 per week. Oo un D FINISH START START I Normal Normal Crash Crash Max reduction $ per Week Activity Time Cost Time Cost AI 5...

  • Problem 13 Question Help urasn 'me (days) Activity (days) Normal Cost ($) Immediate Predecessor(s) 1,000 2,200...

    Problem 13 Question Help urasn 'me (days) Activity (days) Normal Cost ($) Immediate Predecessor(s) 1,000 2,200 1,500 1,500 1,500 1,400 1,000 500 1,000 A, B 1,200 1,500 1,300 C, D 300 a. What is the project's duration if only normal times are used? The project duration is 22 day(s). (Enter your response as an integer.) b. What is the minimum-cost schedule? With the minimum-cost schedule, the project duration is day s). (Enter your response as an integer.)

  • Table 2 contains information about an environmental cleanup project in the township of Hiles. Shorten the...

    Table 2 contains information about an environmental cleanup project in the township of Hiles. Shorten the project 3 weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. What is the project’s duration if only normal times are used? What is the minimum-cost schedule? What is the critical path for the minimum-cost schedule? TABLE 2 Activity Normal Time (wks) Crash Time (wks) Cost to...

  • Question 15 The following information about a project was provided: • Indirect costs per day: $233...

    Question 15 The following information about a project was provided: • Indirect costs per day: $233 • Late completion penalty of $84 per day beyond day 19 • The current Critical Path duration is 26 Acitvity А B с D E F G Immed Normal Normal Pred(s) Time (days) Cost ($) 3 7,000 1 3,000 A 4 12,000 B 2 12,000 1 8,000 DE 4 5,000 E 2 9,000 Crash Time Crash Cost (days) 2 10,000 1 3,000 2 40,000...

  • You are the manager of a project to improve a billing process at your firm. The...

    You are the manager of a project to improve a billing process at your firm. The table below contains the data you will need to conduct a cost analysis of the project Indirect costs are $1,600 per week, and penalty costs are $600 per week after week 12 Immediate Normal Cost Crash Cost Predecessor(s) Normal Time (weeks) Crash Time (weeks) ($) ($) Activity A 4 5,500 7,500 В 5 3 8,000 9,500 A 1 1 3,500 3,500 В 6 3...

  • The following information about a project was provided: • Indirect costs per day: $341 • Late...

    The following information about a project was provided: • Indirect costs per day: $341 • Late completion penalty of $145 per day beyond day 19 • The current Critical Path duration is 24 Acitvity Immed Pred(s) Normal Time Normal (days) Cost ($) Crash Time Crash Cost (days) ($) 3 1 A B с D E F G 4 2 A B C DE E 7,000 3,000 12,000 12.000 8.000 5,000 9,000 2 1 2 1 1 2 10,000 3,000 40,000...

  • Question 16 4 points Save Answe The following provides information about a project, including a list...

    Question 16 4 points Save Answe The following provides information about a project, including a list of activities and precedence relationships, activity durations (normal and "crash" times), direct activity costs (normal and "crash"), indirect costs for the project, as well as calculated crash costs/day and the maximum amount that each activity can be shortened (crashed) by. There are no penalty costs for this project. Total project cost (using normal times), a network diagram, and the four paths and durations have...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT