Question

The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in Table 1 below. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each

The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in Table 1 below. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each day the project lasts beyond day 14. (a) What is the shortest time duration for this project regardless of cost? 

 (b) What is the total cost and time of the minimum-cost schedule?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER (a)

Project duration is 23 days i.e. shortest time duration for this project regardless of cost

Project

Activity
time

Predessor

ES

EF

LS

LF

Slack
(LS-ES)

A

6

-

0

6

0

6

0

B

4

-

0

4

2

6

2

C

3

A,B

6

9

6

9

0

D

2

B

4

6

7

9

3

E

6

C,D

9

15

9

15

0

F

2

E

15

17

21

23

6

G

4

E

15

19

15

19

0

H

4

G

19

23

19

23

0



Project

23





فه 0 D Q

Critical Path is A-C-E-G-H = 6+3+6+4+4 = 23

ANSWER (b)

Project

Normal time

Crash time

Normal cost

crash cost

Crash cost/pd

Crash by

Crashing cost

A

6

5

1000

1200

200

1

200

B

4

2

800

2000

600

0

0

C

3

2

600

900

300

1

300

D

2

1

1500

2000

500

0

0

E

6

4

900

1200

150

2

300

F

2

1

1300

1400

100

0

0

G

4

4

900

900

0

0

0

H

4

2

500

900

200

2

400

Totals



7500




1200

We can crash only Critical path activities to shorten project duration.

So Max crash time is 6 days for $1200.

So Minimum Project duration = 23-6 = 17 days

So Penalty is payable for 17-14 = 3 days

So minimum cost = Project cost + Crash cost + Indirect cost + penalty

= 7500 + 1200 + 300*17 + 3*150

= 14,250

Critical path has Not changed & remains A-C-E-G-H

Critical path length is now 5+2+4+4+2 = 17

N 2 F 5 2 А E H 4 2 B D G

Activity A A, B ש ס ס ח ו ם 1 Normal Time ( days) Normal cost ($) Crash time ( days) Crash cost ($) Immediate Predecessor (s)


answered by: ANURANJAN SARSAM
Add a comment
Know the answer?
Add Answer to:
The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in Table 1 below. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the pr...

    The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given $150 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 15. the following table. Indirect project costs amount to Normal Time Crash Time Crash Cost Immediate Normal Cost (S) Activity Predecessor(s) (S) (days) (days) 1.200 A 6 800 4 6 1,000 2 2,200 600 900 C...

  • The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the pr...

    The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to S150 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 15. Normal Time Crash Time Crash Cost Immediate Normal Cost ($) Activity (S) (days) (days) Predecessor(s) 6 800 1,200 A 4 6 1,000 2,200 C 600 1...

  • Project Cycle

    The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in Table 1 below. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each day the project lasts beyond day 14.(a) What is the shortest time duration for this project regardless of cost?(30 marks) (b) What is the total cost and time of the minimum-cost schedule?(10 marks)Table 1:...

  • The following information about a project was provided: • Indirect costs per day: $341 • Late...

    The following information about a project was provided: • Indirect costs per day: $341 • Late completion penalty of $145 per day beyond day 19 • The current Critical Path duration is 24 Acitvity Immed Pred(s) Normal Time Normal (days) Cost ($) Crash Time Crash Cost (days) ($) 3 1 A B с D E F G 4 2 A B C DE E 7,000 3,000 12,000 12.000 8.000 5,000 9,000 2 1 2 1 1 2 10,000 3,000 40,000...

  • The table below contains data for the installation of new equipment in a manufacturing process at...

    The table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation, Your company is responsible for the installation project. Indirect costs are $10,000 per week, and a penaity cost of $9,000 per week will be incurred by your company for every week the project is delayed beyond week12. Normal Time Crash Time Normal Cost Crash Cost Activity Immediate Predecessor(s) (weoks) (weeks)(5) long dash- long dash- 7,000 3,000 14,000 3,000 12,00040,000 12,000 22,000 8,000...

  • Question 15 The following information about a project was provided: • Indirect costs per day: $233...

    Question 15 The following information about a project was provided: • Indirect costs per day: $233 • Late completion penalty of $84 per day beyond day 19 • The current Critical Path duration is 26 Acitvity А B с D E F G Immed Normal Normal Pred(s) Time (days) Cost ($) 3 7,000 1 3,000 A 4 12,000 B 2 12,000 1 8,000 DE 4 5,000 E 2 9,000 Crash Time Crash Cost (days) 2 10,000 1 3,000 2 40,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT