Question

Help Please

Table of Crashing Decision












Since no indirect cost nor penaly cost information is offered, please consider the schedule and crash cost issues only,

Using Table of Crashing Decision, what is the minimum time schedule for this project?





Since no indirect cost nor penaly cost information is offered, please consider the schedule and crash cost issues only,

Using Table of Crashing Decision, what is the difference, in dollars, between the minimum-time schedule and the schedule created by crashing all activities to their limits? Assume that there are no indirect or penalty costs.


less than or equal to $1,000


greater than $1000 but less than or equal to $2,000


greater than $2000 but less than or equal to $3,000


greater than $3,000

Since no indirect cost nor penaly cost information is offered, please consider the schedule and crash cost issues only,

Using Table of Crashing Decision, what is the earliest completion time of this project if normal times are used for all activities?





Since no indirect cost nor penaly cost information is offered, please consider the schedule and crash cost issues only,

Using Table of Crashing Decision, if the project completion time has to be reduced by one week, which of the following activities should be crashed to minimize the extra cost of earlier completion?





Since no indirect cost nor penaly cost information is offered, please consider the schedule and crash cost issues only,

Using Table of Crashing Decision, if the project's normal earliest completion time is to be reduced by two weeks, what is the minimum additional cost that will be incurred in achieving this two-week reduction?







0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 9 more requests to produce the answer.

1 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
Help Please
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,000...

    Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,0003,300B...648,0009,000CA114,0004,000      DA543,5004,000EB434,7505,500FC222,0002,000      GD114,0004,000HD,F323,5003,750IE,G323,0004,250JE215,0007,000Since no indirect cost nor penalty cost information is offered, please consider the schedule and crash cost issues only.1. Using Table of Crashing Decision, what is the earliest completion time of this project if normal times are used for all activities?A. fewer than 13 weeks; B. 13 weeks; C. 14 weeks; D. more than 14 weeks2. Using Table of Crashing Decision, what is the minimum time schedule for this project?A. fewer than 8 weeks; B. 8...

  • Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens...

    Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table: Activity A Normal Time (weeks) 3 Crash Time (weeks) 2 B 2 1 1 Normal Cost $1,200 $2,000 $400 $1,500 $950 $4,500 $1,600 Total Cost with Immediate Crashing Predecessor(s) $1,800 $2,800 $400 $1,820 A $1,250 B $5,500 с $2,300...

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's...

    Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: To Cost Normal Time (weeks) Crash Time Normal with Activity (weeks) Cost Crashing Immediate Predecessor(s) $2.700 A $2,000 7 $2,300 S3,100 3 $500 $500 S2,300 $2,580 A E 5900 $1.275 F F $3.400 2 S4,800 C G $1,500 $2.100 D, E a) Based on...

  • Kimpel Products makes pizza ovens for commercial use. James​ Kimpel, CEO, is contemplating producing smaller ovens...

    Kimpel Products makes pizza ovens for commercial use. James​ Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following​ table:                                                                                                                                   Activity Normal Time​(weeks) Crash Time​(weeks) Normal Cost Total Cost with Crashing    Immediate​ Predecessor(s) A 3 2 $ 1,200 $1,800 — B 2 1 $2,100 $2,900    __ C 1 1 $400 $400 — D 7 3 $1,300...

  • I ONLY need help on letters G and I. According to the answers I've tried for...

    I ONLY need help on letters G and I. According to the answers I've tried for these, it is NOT Activity G for the letter G and not $2,120 for letter I. M5_A5. A computer installation project is being reviewed. Assume the project has to be completed in 16 weeks. Crash the project as necessary (crashing one week at a time). The relevant information is in the table below. CRASH STANDARD STANDARD CRASH IMMEDIATE ACTIVITY TIME TIME COST PREDECESSORS COST...

  • You are the manager of a project to improve a billing process at your firm. The...

    You are the manager of a project to improve a billing process at your firm. The table below contains the data you will need to conduct a cost analysis of the project Indirect costs are $1,600 per week, and penalty costs are $600 per week after week 12 Immediate Normal Cost Crash Cost Predecessor(s) Normal Time (weeks) Crash Time (weeks) ($) ($) Activity A 4 5,500 7,500 В 5 3 8,000 9,500 A 1 1 3,500 3,500 В 6 3...

  • Kampel Products makes a vento comerciales C related data are in the following table o ng...

    Kampel Products makes a vento comerciales C related data are in the following table o ng r eso de Nom e Act Crash Time Normal wek) Court $1.000 $2300 SD 51.000 5900 $4500 $1,300 Cost with dia Casing Predeces) 100 $100 $100 5700 51125 $5500 52 300 thing the activities a) Based on the given information regarding the activities for the project the project completion date wooks b) To reduce the duration of the project 10 weeks at the least...

  • Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's...

    Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity A Normal Time Crash Time Normal (weeks) (weeks) Cost 4 3 $2,000 2 $2,100 $750 Total Cost with Immediate Crashing Predecessor(s) $2,650 - $2,800 - $750 B 2 3 $2.400 $2,680 Ā $900 3 § $1,200 3 $900 $3,200 § $4,600 $9,500 $2,000...

  • Software Installation: You are the project manager of the software installation project (see figure & table)...

    Software Installation: You are the project manager of the software installation project (see figure & table) below. You would like to find the minimum-cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,500 per week. Oo un D FINISH START START I Normal Normal Crash Crash Max reduction $ per Week Activity Time Cost Time Cost AI 5...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT