a)
Project completion date =14 weeks
----------------------------
b)
To reduce the duration of the project to 10 weeks,
The first activity to crash is D by 2 weeks at a per week crashing cost of 80 dollars
Next, one should cash activity D and activity E by 2 weeks (each) for an additional total per week crashing cost of 80+100 = 180 dollars
----------------------------
c)
To reduce the duration of the project to 7 weeks,
Next activity to crash in order is G by 2 weeks at a per week crashing cost of 350 dollars
Next, one should cash activity A and activity E by 1 week (each) for an additional total per week crashing cost of 600+100 = 700 dollars
Total cost of crashing the project to 7 weeks = 1920 dollars
After crashing the project to 7 weeks, total project cost, including normal time = 12150+1920 = 14070 dollars
Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens...
Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table: Activity Normal Time(weeks) Crash Time(weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 3 2 $ 1,200 $1,800 — B 2 1 $2,100 $2,900 __ C 1 1 $400 $400 — D 7 3 $1,300...
Kampel Products makes a vento comerciales C related data are in the following table o ng r eso de Nom e Act Crash Time Normal wek) Court $1.000 $2300 SD 51.000 5900 $4500 $1,300 Cost with dia Casing Predeces) 100 $100 $100 5700 51125 $5500 52 300 thing the activities a) Based on the given information regarding the activities for the project the project completion date wooks b) To reduce the duration of the project 10 weeks at the least...
Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...
Solve the following project crashing problem adopted from Heizer et al. (2016). Attempt the question before looking up the solution on Page 855 of Heizer et. al. 2016 3.32Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are given in the following table: NORMAL CRASH TIME TIME NORMALI CRASH! IMMEDIATE ACTIVITY (WEEKS) (WEEKS) COST...
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: To Cost Normal Time (weeks) Crash Time Normal with Activity (weeks) Cost Crashing Immediate Predecessor(s) $2.700 A $2,000 7 $2,300 S3,100 3 $500 $500 S2,300 $2,580 A E 5900 $1.275 F F $3.400 2 S4,800 C G $1,500 $2.100 D, E a) Based on...
Development of a new deluxe version of a particular toy is being considered by T-O-Y Inc. The activities necessary for the completion of this project along with the relevant information for each activity are listed in the following table. The Total Crash Time represents the time for that activity after it has been crashed the maximum crash time allowed for that activity. For example, we can reduce the time for Activity A by one week to 3 weeks after crashing...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Duration (weeks) Activity A (start) Precedes B, C Crash Cost/Week $400 $100 $200 $300 $400 F F (end) 2 Suppose that Rafay is only given 5 weeks (instead of 7) to complete the project. By how many weeks should each activity be crashed in order to...
1) Based on the given information regarding the activities for the project, the project length= ___ weeks. 2) The total cost required for completing this project on normal time= $____ 3) For reducing the duration of the project by one week, the activity that should be crashed first is activity ___. 4) The cost of the project based on the first activity selected for crashing will increase by $___. 5) The maximum weeks by which the project can be reduced...
Suppose that Rafay is only given 7 weeks (instead of 10) to complete the project . By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Activity Each Activity Should be Reduced BY (weeks) A (weeks)- ? B (weeks)- ? C (weeks)- ? D (weeks)- ? E (weeks)- ? F (weeks)- ? What is the total crashing cost ? The following is a...
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity A Normal Time Crash Time Normal (weeks) (weeks) Cost 4 3 $2,000 2 $2,100 $750 Total Cost with Immediate Crashing Predecessor(s) $2,650 - $2,800 - $750 B 2 3 $2.400 $2,680 Ā $900 3 § $1,200 3 $900 $3,200 § $4,600 $9,500 $2,000...