Question

Development of a new deluxe version of a particular toy is being considered by T-O-Y Inc....

Development of a new deluxe version of a particular toy is being considered by T-O-Y Inc. The activities necessary for the completion of this project along with the relevant information for each activity are listed in the following table. The Total Crash Time represents the time for that activity after it has been crashed the maximum crash time allowed for that activity. For example, we can reduce the time for Activity A by one week to 3 weeks after crashing it.

Activity

Time to complete using Normal Time (Weeks)

Time activity is completed using Crash Time (Weeks)

Total Normal Cost

Crash Cost per period

Immediate Predecessors

A

4

3

$2,000

$600

--

B

2

1

2,200

$800

--

C

3

3

500

$0

--

D

8

4

2,300

$750

A

E

6

3

900

$100

B

F

3

2

3,000

$1,200

C

G

4

2

1,400

$300

D,E

a) Using the normal time, what is the critical path, the project completion time, the total time required to complete all of the activities, and the slack time for each path and each activity? (The slack time for each path should be relative to the time to complete the critical path.)

b) If you wish to reduce the time required to complete this project by one week, which activity should be crashed, and how much will this increase the total cost?

c) Now, we want to crash the project to the minimum possible time crashing any and all activities necessary to do this using the crash cost per period rule we have studied. What is the project completion time now? How much would the total cost increase?

d) Let’s return to the results found in a). Suppose the company believes that reducing the project completion time from the time reported in part a), will help the company realize an additional $700 per week in revenue for the first two weeks the project time is reduced, $650 per week in revenue for the next two weeks the project is reduced and $500 per week in revenue after that for every week the project is reduced. How many weeks should the company reduce the project completion time and what is the resulting cost of the project considering the additional revenue as an offset to the cost associated with crashing the project? The company is interested in selecting the project duration and reduced activity times that minimize the cost of the project.

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Development of a new deluxe version of a particular toy is being considered by T-O-Y Inc....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's...

    Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: To Cost Normal Time (weeks) Crash Time Normal with Activity (weeks) Cost Crashing Immediate Predecessor(s) $2.700 A $2,000 7 $2,300 S3,100 3 $500 $500 S2,300 $2,580 A E 5900 $1.275 F F $3.400 2 S4,800 C G $1,500 $2.100 D, E a) Based on...

  • Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's...

    Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity A Normal Time Crash Time Normal (weeks) (weeks) Cost 4 3 $2,000 2 $2,100 $750 Total Cost with Immediate Crashing Predecessor(s) $2,650 - $2,800 - $750 B 2 3 $2.400 $2,680 Ā $900 3 § $1,200 3 $900 $3,200 § $4,600 $9,500 $2,000...

  • Development of Version 20 of a particular accounting software product is being considered by Jose Noguera's...

    Development of Version 20 of a particular accounting software product is being considered by Jose Noguera's technology form in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Immediate Predecessor(s) Activity Normal Time Crash Time Normal (weeks) (weeks) Cost $2,200 $2,200 5750 $2,300 $900 $3.000 $1,600 Total Cost with Crashing $2,850 $3.000 5750 $2.580 $1,200 $4.500 52.200 D.E d) The maximum weeks by which the project can be reduced by crashing =...

  • oblem S.ST evelopmient of Version 2 0 of a particular accounting software product is being considered...

    oblem S.ST evelopmient of Version 2 0 of a particular accounting software product is being considered by Jose Noguera's ompletion of this projedt are listed in the following table: technology firm in Baton Rouge. The activities necessary to Total Cost Normal Time Crash Time Normal with (weeks) Cost Crashing Immediate Predecessors) S2,000 $2.600 S2,300 $3,100 S750 $750 S2,500 $2.780 $1,000 $1,375 $3.000 S4,200 $1400 $2.000 D E a) Based on the given information regarding the activities for the project,the project...

  • QUESTION 9 Consider the following project; for which activities is it possible that the slack can...

    QUESTION 9 Consider the following project; for which activities is it possible that the slack can be greater than zero? Activity Immediate Predecessors B, E a. Only activities B or E could have slack, but they could not both have slack. Ob. Only activities B or C could have slack, but they could not both have slack. Oc. It is possible for any or all activities in this project to have slack. Od. It is possible for either all three...

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • Kampel Products makes a vento comerciales C related data are in the following table o ng...

    Kampel Products makes a vento comerciales C related data are in the following table o ng r eso de Nom e Act Crash Time Normal wek) Court $1.000 $2300 SD 51.000 5900 $4500 $1,300 Cost with dia Casing Predeces) 100 $100 $100 5700 51125 $5500 52 300 thing the activities a) Based on the given information regarding the activities for the project the project completion date wooks b) To reduce the duration of the project 10 weeks at the least...

  • Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens...

    Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table: Activity A Normal Time (weeks) 3 Crash Time (weeks) 2 B 2 1 1 Normal Cost $1,200 $2,000 $400 $1,500 $950 $4,500 $1,600 Total Cost with Immediate Crashing Predecessor(s) $1,800 $2,800 $400 $1,820 A $1,250 B $5,500 с $2,300...

  • Kimpel Products makes pizza ovens for commercial use. James​ Kimpel, CEO, is contemplating producing smaller ovens...

    Kimpel Products makes pizza ovens for commercial use. James​ Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following​ table:                                                                                                                                   Activity Normal Time​(weeks) Crash Time​(weeks) Normal Cost Total Cost with Crashing    Immediate​ Predecessor(s) A 3 2 $ 1,200 $1,800 — B 2 1 $2,100 $2,900    __ C 1 1 $400 $400 — D 7 3 $1,300...

  • 1) Based on the given information regarding the activities for the project, the project length= ___...

    1) Based on the given information regarding the activities for the project, the project length= ___ weeks. 2) The total cost required for completing this project on normal time= $____ 3) For reducing the duration of the project by one week, the activity that should be crashed first is activity ___. 4) The cost of the project based on the first activity selected for crashing will increase by $___. 5) The maximum weeks by which the project can be reduced...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT