Question

Development of Version 2.0 of a particular accounting software product is being considered by Jose Noqueras technology firm

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a)

Based on the given info, the project length is 16 weeks

Activity Normal Crash Normal C Crash C IP Max Crash Crash slope Crash time Final time Start Finish Original CP
A 4 3 2000 3700 - 1 1700 0 4 0 4 Y
B 2 1 2300 3100 - 1 800 0 2 0 2
C 3 3 500 500 - 0 N/A 0 3 0 3
D 8 4 2300 2580 A 4 70 0 8 4 12 Y
E 6 3 900 1275 B 3 125 0 6 2 8
F 3 2 3400 4800 C 1 1400 0 3 3 6
G 4 2 1500 2100 D,E 2 300 0 4 12 16 Y
Normal cost 12900
Crash cost 0

b)

The total cost based on normal time (add up all the normal cost) = 12900

c)

For reducing the project duration by 1 week, we must reduce the critical activity that is the cheapest (smallest crash slope). That is Activity D.

The critical path is A-D-G.

Activity Normal Crash Normal C Crash C IP Max Crash Crash slope Crash time Final time Start Finish Original CP
A 4 3 2000 3700 - 1 1700 0 4 0 4 Y
B 2 1 2300 3100 - 1 800 0 2 0 2
C 3 3 500 500 - 0 N/A 0 3 0 3
D 8 4 2300 2580 A 4 70 1 7 4 11 Y
E 6 3 900 1275 B 3 125 0 6 2 8
F 3 2 3400 4800 C 1 1400 0 3 3 6
G 4 2 1500 2100 D,E 2 300 0 4 11 15 Y
Normal cost 12900
Crash cost 70

d)

Maximum weeks that project can be reduced by crashing is 9 weeks

We can crash A, D, and G to the maximum. This will reduce the path duration to 9 weeks. In addition we need to crash E as well. This will make two critical paths. ADG and BEG

The total cost will be 1290 + 2705 = 3995

Activity Normal Crash Normal C Crash C IP Max Crash Crash slope Crash time Final time Start Finish Original CP
A 4 3 2000 3700 - 1 1700 1 3 0 3 Y
B 2 1 2300 3100 - 1 800 0 2 0 2
C 3 3 500 500 - 0 N/A 0 3 0 3
D 8 4 2300 2580 A 4 70 4 4 3 7 Y
E 6 3 900 1275 B 3 125 1 5 2 7
F 3 2 3400 4800 C 1 1400 0 3 3 6
G 4 2 1500 2100 D,E 2 300 2 2 7 9 Y
Normal cost 12900
Crash cost 2705
Add a comment
Know the answer?
Add Answer to:
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT