Question

Development of Version 20 of a particular accounting software product is being considered by Jose Nogueras technology form i
d) The maximum weeks by which the project can be reduced by crashing = 7 weeks. Total cost of crashing the project to minimum
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: d) 7 weeks, $1330

Initial duration of project = 16 weeks

After maximum possible crashing, Project duration = 9 weeks.

The maximum weeks by which the project can be reduced = 16 -9 =7 weeks

Crashing Cost:

Crashing Cost of Activity D by 4 weeks = $280

Crashing Cost of Activity G by 2 weeks = $300

Crashing cost of Activity A & E by 1 week = $650 + $100 =$750

Total Crashing Cost = 280 + 300 + 750 = $1330

Activity Normal Time Crash time Normal Cost Total Cost with Max. Crashing Crashing possible Crash Cost per week 4 3 $ 2,200.0

Network Diagram:

Cl, 12) CO, 4 ) C12, 162 End St B CO ) (0,3) Criticul path after coughing -E-G2 Critical puth - step i Gush Step 2 Cough Step

After mea. possible crushing 3,7 End 02,72 BS Scarined wqu32 hak cam Seanner

Add a comment
Know the answer?
Add Answer to:
Development of Version 20 of a particular accounting software product is being considered by Jose Noguera's...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT