Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below (Time in weeks). Activit...

Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below (Time in weeks).

Activity

Immediate

Predecessor

a

m

b

A

--

2

5

8

B

A

3

6

9

C

A

4

7

10

D

B

2

5

14

E

D

3

3

3

F

C

6

8

10

G

E, F

1

1

1

H

C

6

10

14

I

G, H

3

4

5

(a) If you wish to reduce the time required to complete this project by two weeks, which activity(ies) should be crashed and why?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

We will select activities = A, C, H, I

EXPLANATION:

In order to find the expected time, we will use the following formula

T = (a + 4m + b) / 6

A. (2 + (4 * 5 ) + 8) / 6 = 5

B. (3 + (4 * 6 ) + 9) / 6 = 6

C. (4 + (4 * 7 ) + 10) / 6 = 7

D. (2 + (4 * 5 ) + 14) / 6 = 6

E. (3 + (4 * 3 ) + 3) / 6 = 3

F. (6 + (4 * 8 ) + 10) / 6 = 8

G. (1 + (4 * 1 ) + 1) / 6 = 1

H. (6 + (4 * 10 ) + 14) / 6 = 10

I. (3 + (4 * 4 ) + 5) / 6 = 4

USING THE EXPECTED TIME, WE CAN FIND THE CRITICAL PATH:



ACTIVITY

DURATION

PRE 1

PRE 2

ES

EF

LS

LF

SLACK

A

5

0

5

0

5

0

B

6

A

5

11

6

12

1

C

7

A

5

12

5

12

0

D

6

B

11

17

12

18

1

E

3

D

17

20

18

21

1

F

8

C

12

20

13

21

1

G

1

E

F

20

21

21

22

1

H

10

C

12

22

12

22

0

I

4

G

H

22

26

22

26

0


The ES, EF values are calculated using a forward pass where the ES of the next activity is the maximum EF of all the predecessor activities.

The LS, LF values are calculated using a backward pass where the LS of the next activity is the minimum LF of all the predecessor activities.

The critical path represents all the activities in a particular chain which have the largest duration and 0 slack for all activities, and due to this fact, any delay in the critical activities can cause a delay for the entire project.


A - C - H - I = 26

If we have to crash an activity to reduce the project time, the critical activities would be selected in order to bring about a decrease in the project time and therefore, for crashing, we will select activities = A, C, H, I

Add a comment
Know the answer?
Add Answer to:
Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below (Time in weeks). Activit...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's...

    Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: To Cost Normal Time (weeks) Crash Time Normal with Activity (weeks) Cost Crashing Immediate Predecessor(s) $2.700 A $2,000 7 $2,300 S3,100 3 $500 $500 S2,300 $2,580 A E 5900 $1.275 F F $3.400 2 S4,800 C G $1,500 $2.100 D, E a) Based on...

  • Development of a new deluxe version of a particular toy is being considered by T-O-Y Inc....

    Development of a new deluxe version of a particular toy is being considered by T-O-Y Inc. The activities necessary for the completion of this project along with the relevant information for each activity are listed in the following table. The Total Crash Time represents the time for that activity after it has been crashed the maximum crash time allowed for that activity. For example, we can reduce the time for Activity A by one week to 3 weeks after crashing...

  • Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's...

    Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity A Normal Time Crash Time Normal (weeks) (weeks) Cost 4 3 $2,000 2 $2,100 $750 Total Cost with Immediate Crashing Predecessor(s) $2,650 - $2,800 - $750 B 2 3 $2.400 $2,680 Ā $900 3 § $1,200 3 $900 $3,200 § $4,600 $9,500 $2,000...

  • Development of Version 20 of a particular accounting software product is being considered by Jose Noguera's...

    Development of Version 20 of a particular accounting software product is being considered by Jose Noguera's technology form in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Immediate Predecessor(s) Activity Normal Time Crash Time Normal (weeks) (weeks) Cost $2,200 $2,200 5750 $2,300 $900 $3.000 $1,600 Total Cost with Crashing $2,850 $3.000 5750 $2.580 $1,200 $4.500 52.200 D.E d) The maximum weeks by which the project can be reduced by crashing =...

  • A small software development project has eight major activities. The times are estimated and prov...

    A small software development project has eight major activities. The times are estimated and provided in the table below: Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 5 -- B 5 7 9 -- C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 C, D G 7 8 9 D, E H 2 6 10 F Answer the following questions based on above table 1-2...

  • QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are s...

    QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are shown follow. Time Immediate Activity (weeks) Predecessor 2 5 В 4 C 5 В 6 В.С D,E F What are the slack times of Activities D and E? 0 and 0, respectively 1 and 1, respectively 2 and 0, respectively 0 and 1, respectively 1 and 0, respectively shown follow. A firm is planning a project for the...

  • Using Table 2.13 below, if the expected time for activity E is changed to nine weeks,...

    Using Table 2.13 below, if the expected time for activity E is changed to nine weeks, by how many weeks will the project's expected completion time increase? Table 2.13 (All activity times for the project are in weeks.) Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessors(s) A 3 4 5 --- B 5 7 9 --- C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 CD G 7...

  • oblem S.ST evelopmient of Version 2 0 of a particular accounting software product is being considered...

    oblem S.ST evelopmient of Version 2 0 of a particular accounting software product is being considered by Jose Noguera's ompletion of this projedt are listed in the following table: technology firm in Baton Rouge. The activities necessary to Total Cost Normal Time Crash Time Normal with (weeks) Cost Crashing Immediate Predecessors) S2,000 $2.600 S2,300 $3,100 S750 $750 S2,500 $2.780 $1,000 $1,375 $3.000 S4,200 $1400 $2.000 D E a) Based on the given information regarding the activities for the project,the project...

  • A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8...

    A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?

  • 2. what is the project variance value of completion? !!! Que A small software development project...

    2. what is the project variance value of completion? !!! Que A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below: Activity Immediate Predecessor a 2 الما COO m 5 6 7 5 3 b 8 9 10 14 3 4 2 3 a) The expected completion time for this project is (enter your response as a whole number),

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT