Question

Using Table 2.13 below, if the expected time for activity E is changed to nine weeks,...

Using Table 2.13 below, if the expected time for activity E is changed to nine weeks, by how many weeks will the project's expected completion time increase?
Table 2.13
(All activity times for the project are in weeks.)

Activity

Optimistic Time

Most Likely Time

Pessimistic Time

Immediate Predecessors(s)

A

3

4

5

---

B

5

7

9

---

C

2

3

10

A

D

2

5

8

B

E

1

7

7

B

F

3

5

7

CD

G

7

8

9

DE

H

2

6

10

F

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Critical path = Longest path duration of project = BDFH = 23 weeks

Activity ACTIVITY before Optimistic (a) Most likely (M) Pessimistic (b) PERT Estimate = (a+4*M+b)/6
A --- 3 4 5 4.00
B --- 5 7 9 7.00
C A 2 3 10 4.00
D B 2 5 8 5.00
E B 1 7 7 6.00
F CD 3 5 7 5.00
G DE 7 8 9 8.00
H F 2 6 10 6.00

New Expected time for E = 9 weeks. The critical path shifts to BEG. New project duration = 7 + 9+ 8 = 24 weeks

Add a comment
Know the answer?
Add Answer to:
Using Table 2.13 below, if the expected time for activity E is changed to nine weeks,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT