Using Table 2.13 below, if the expected time for activity E is
changed to nine weeks, by how many weeks will the project's
expected completion time increase?
Table 2.13
(All activity times for the project are in weeks.)
Activity |
Optimistic Time |
Most Likely Time |
Pessimistic Time |
Immediate Predecessors(s) |
A |
3 |
4 |
5 |
--- |
B |
5 |
7 |
9 |
--- |
C |
2 |
3 |
10 |
A |
D |
2 |
5 |
8 |
B |
E |
1 |
7 |
7 |
B |
F |
3 |
5 |
7 |
CD |
G |
7 |
8 |
9 |
DE |
H |
2 |
6 |
10 |
F |
Critical path = Longest path duration of project = BDFH = 23 weeks
Activity | ACTIVITY before | Optimistic (a) | Most likely (M) | Pessimistic (b) | PERT Estimate = (a+4*M+b)/6 |
A | --- | 3 | 4 | 5 | 4.00 |
B | --- | 5 | 7 | 9 | 7.00 |
C | A | 2 | 3 | 10 | 4.00 |
D | B | 2 | 5 | 8 | 5.00 |
E | B | 1 | 7 | 7 | 6.00 |
F | CD | 3 | 5 | 7 | 5.00 |
G | DE | 7 | 8 | 9 | 8.00 |
H | F | 2 | 6 | 10 | 6.00 |
New Expected time for E = 9 weeks. The critical path shifts to BEG. New project duration = 7 + 9+ 8 = 24 weeks
Using Table 2.13 below, if the expected time for activity E is changed to nine weeks,...
The following table shows estimates of activity times (weeks) for a project: Activity Optimistic Time Most Probable Time Pessimistic Time A 3 4.5 9 B 1.5 2 2.5 C 5 6 7 D 4 4.5 8 E 5 6 7 F 1 2.5 7 G 7 9 11 Suppose that the critical path is A-B-D-F-G. Use Appendix A to answer the questions. Do not round intermediate calculations. Round your answers to three decimal places. What is the probability that the...
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...
Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m b Time (t) o 2 3 2 1 B с D NWN mlm A 1 A,B 2 4 1 6 7 9 F 1 с с DE F,G 4 2 5 3 G 4 12 H 2 4 From the table above find the flowing answers. 1. Construct the project Network 2. Find the expected duration and Variance of each activity 3. Find the...
1- Consider the table shown below: Task Predecessor Time (weeks) Expected time Variance of time Optimistic Most likely Pessimistic A - 1 3 5 B A 2 6 10 C B 4 7 10 D B, C 1 2 9 E D 2 4 6 F D,E 4 7 10 G F 1 3 5 a) Calculate expected time and variance for each task. b) Find the critical path and expected project competition time? c) What is the probability of...
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Time Estimates (weeks) Activity a m b Activity Predecessor A 3 5 7 -- B 4 8 10 A C 2 3 5 A D 6 9 12 B, C E 5 9 15 D Table 9.2 Reference: Ref 9-2 Using Table 9.2, the variance for activity E is Select one: A. 2.582. B. 1.667. C. 1.291. D. 2.778.
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Preceding Optimistic Time Probable Time Pessimistic Time Expected Time Variance A -- 7 9 14 1.361 B A 2 2 8 0 C A 8 12 16 0 D A 3 5 10 1.361 E B 4 6 8 0 F B 6 8 10 0 G C, F 2 3 4 0 H D 2 2 8 1.000 I H 6 8...
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Time Estimates (weeks) Activity a m b Activity Predecessor A 3 5 7 -- B 4 8 10 A C 2 3 5 A D 6 9 12 B, C E 5 9 15 D Table 9.2 Reference: Ref 9-2 Using Table 9.2, the earliest start (ES) time for activity D is Select one: A. 21.67 weeks. B. 8.17 weeks. C. 12.67 weeks....
PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....
Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B - 4 6 10 C A,B 2 5 8 D B 3 5 9 E A,C 3 6 9 F C,E 1 3 5 G C,D 3 4 9 H D 4 6 10 I F,G 3 4 9 J H 2 4 6 A).Draw the project network b).what is the expected completion time of the project. c) after your calculation, if you find one...
Activity No. Activity Time (weeks) Immediate Predecessors 1 Collect requirements 6 2 Analyze processes 2 1 3 Analyze data 4 2 4 Design processes 18 2 5 Design data 6 3 6 Design screens 6 3,4 7 Design reports 12 4,5 8 Program 10 6,7 9 Test and Document 14 7 10 Install 4 8,9 Construct a network diagram & calculate the earliest expected completion time/s