Question

1- Consider the table shown below: Task Predecessor Time (weeks) Expected time Variance of time Optimistic...

1- Consider the table shown below:

Task

Predecessor

Time (weeks)

Expected time

Variance of time

Optimistic

Most likely

Pessimistic

A

-

1

3

5

B

A

2

6

10

C

B

4

7

10

D

B, C

1

2

9

E

D

2

4

6

F

D,E

4

7

10

G

F

1

3

5

a) Calculate expected time and variance for each task.  

b) Find the critical path and expected project competition time?

c) What is the probability of completing the project on or before 32 weeks?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answers :

a) Expected time and variance are calculated and tabulated

b) critical path : A-B-C-D-E-F-G

  project completion time = 33 weeks

c) probability of completion in 32 weeks= 64.80%

Explanation :

Task Predecessor Expected Variance time Time (weeks) Optimishi | Palost / Pessimistic likely १ § 2 6 io A - R A 3 6 ng 0.14 13841 369 DIAS 01313 Esl Act EE LSI Durif TICI6 197116 Die 120 3199 16 1921 22 3 E30 3014180 kol.3333 237130 1801 Critical pat

Add a comment
Know the answer?
Add Answer to:
1- Consider the table shown below: Task Predecessor Time (weeks) Expected time Variance of time Optimistic...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT