Question

(15 points) Activity Immediate Predecessor Optimistic Time Most likely Time Pessimistic Time A NONE 4 7...

  1. (15 points)

Activity

Immediate

Predecessor

Optimistic Time

Most likely Time

Pessimistic Time

A

NONE

4

7

9

B

A

2

4

6

C

A

6

9

9

D

B, C

5

5

5

E

C

2

5

9

F

D, E

3

3

6

Use both the longest path method and ES/EF; LS/LF method for the following questions

(e) What are the slack values for non-critical activities? (4 points)

      (f) What is the probability that the project will be completed in 26 weeks? (2 points)

(g) What is the probability that the project will be completed in 23 weeks? (2 points)

0 0
Add a comment Improve this question Transcribed image text
Answer #1


gewen that Optime the Most Pessimenti Activity Predecessor time Am To Teruete) likely time 14 79 A2 46 A 6919 Bics 55 NONE DIProject Network diagram Bimeste mon-critical activity [123216.59 OF 8:33 A - [{8-a 3 5 = 2. 4 10 91.421-99 CX 5.16 tut tu. shfor Es ar 1932)=(29=136 for F =) -(6-3)=(3) = 0.25 & Standard Normal deviation (2) Be Due time-time required to Complete thea similarly, le 723-25.49 JO:69 +0.25 +1:36 10:25 Z- 105592 from Normal de tribution tables, > Doobability for project to com

Add a comment
Know the answer?
Add Answer to:
(15 points) Activity Immediate Predecessor Optimistic Time Most likely Time Pessimistic Time A NONE 4 7...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B -...

    Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B - 4 6 10 C A,B 2 5 8 D B 3 5 9 E A,C 3 6 9 F C,E 1 3 5 G C,D 3 4 9 H D 4 6 10 I F,G 3 4 9 J H 2 4 6 A).Draw the project network b).what is the expected completion time of the project. c) after your calculation, if you find one...

  • 123) Given (Time in weeks): Activity Optimistic Most Likely Pessimistic A 3 4 5 B 6...

    123) Given (Time in weeks): Activity Optimistic Most Likely Pessimistic A 3 4 5 B 6 7 14 C 2 3 10 D 6 9 12 E 4 5 12 F 1 3 11 G 1 2 9 H 2 5 8 I 1 4 7 Determine: (a) the critical path. ( HOW DO I DO THIS WITH OUT A PREDECESSOR?) (b) the probability that the project will be completed in 22 weeks.

  • PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A -...

    PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....

  • 2. Consider the network described in the table below. Immediate Activity Predecessor(s)Pessimistic Probable Optimistic 15 10...

    2. Consider the network described in the table below. Immediate Activity Predecessor(s)Pessimistic Probable Optimistic 15 10 8 K 9 8 7 L 10 6 5 M 3 3 3 N KM 9 5 1 O KM 10 7 4 P LN 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path. (c) Calculate the probability that the project will...

  • Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity...

    Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity on Node (AON) diagram to reflect the flow of these activities. Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity. Calculate the slack for each activity. Identify all activities on the Critical Path. Use the data to calculate the probability the project will finish in 20 weeks (Hint: z-score). Activity A 8 с D E...

  • Activity Predecessor Optimistic Time (a) Most Probable Time (m) Pessimistic Time (b) A None 2 6...

    Activity Predecessor Optimistic Time (a) Most Probable Time (m) Pessimistic Time (b) A None 2 6 10 B None 2 4 6 C A 2 4 6 D A 4 6 8 E B 6 8 22 F B 6 8 10 G C,D 2 8 12 H E,F 2 7 12 I G,H 4 8 16 Question for Blank 1: What is the Critical Path? Question for Blank 2: What is the Expected Duration of the Project? round to...

  • Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...

    Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K, M 9 5 1 O K, M 10 7 4 P L, N 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path....

  • Consider the following project where times are in weeks. Activity Duration Immediate Predecessors A B с...

    Consider the following project where times are in weeks. Activity Duration Immediate Predecessors A B с D E F G H A.B B A с E,F 8 12 7 4 2 3 7 3 DF a) Determine the activity schedule (ES, EF, LS, and LF) as well as slack using the information from the table above (11 marks) b) Determine all the possible paths of this project and determine the shortest possible time this project can be completed? (4 marks)...

  • Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A...

    Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...

  • Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic...

    Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic                         Time                Time                Time A                     7                      10                    12 B                     6                      8                      14 C                     5                      9                      12 D                     12                    14                    21 E                      10                    12                    15 F                      4                      5                      8 G                     1                      3                      8 H                     12                    15                    17 NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”. Calculate the schedule duration of the critical path in days. What is the probability of the project being completed...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT