Question

Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B -...

Activity

Predecessor

Optimistic time

Most likely time

Pessimistic time

A

-

3

5

8

B

-

4

6

10

C

A,B

2

5

8

D

B

3

5

9

E

A,C

3

6

9

F

C,E

1

3

5

G

C,D

3

4

9

H

D

4

6

10

I

F,G

3

4

9

J

H

2

4

6

A).Draw the project network b).what is the expected completion time of the project. c) after your calculation, if you find one path that has the longest completion time, why it is not necessarily critical path? d.) what are the variances for each activity. e) assuming that the path completion times are independent, what is the probability of completing the project in 25 weeks? f.) given the assumption in part(e), what is the probabilitu of completing the project in 20 weeks?

0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B -...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT