Question

Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic...

Given the following activity list and times in days: (15 points)

Activity           Optimistic       Most Likely     Pessimistic

                        Time                Time                Time

A                     7                      10                    12

B                     6                      8                      14

C                     5                      9                      12

D                     12                    14                    21

E                      10                    12                    15

F                      4                      5                      8

G                     1                      3                      8

H                     12                    15                    17

NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”.

  1. Calculate the schedule duration of the critical path in days.
  1. What is the probability of the project being completed in 39 days?

  1. If you want a probability that the project will finish with no less that 85% certainty what is the project duration for that certainty? (5 points)

Note no interpolation is necessary from the table of Z values attached.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer to question a :

Refer below table for activities on critical path :

Activity

Optimistic

Most likely

Pessimistic

Mean

Variance

B

6

8

14

8.67

1.78

E

10

12

15

12.17

0.69

H

12

15

17

14.83

0.69

Mean = ( Optimistic + 4 x Most likely + Pessimistic) / 6

Variance = ( Pessimistic – Optimistic)^2/36

Schedule duration of the critical path

= Sum of means

= 8.67 + 12.17 + 14.83

= 35.67 days

Answer to question b :

Variance of the critical path

= Sum of variances of activities on critical path

= 1.78 + 0.69 + 0.69

= 3.16 days

Standard deviation of the critical path

= Square root ( Variance of critical path )

= 1.78

Let Z value for the probability of the project being completed in 39 days

= Z1

Therefore ,

Schedule duration of critical path + Z1 x Standard deviation of critical path = 39

Or, 35.67 + Z1x 1.78 = 39

Or, 1.78.Z1 = 3.33

Or, Z1 = 1.87

Corresponding probability for Z = 1.87 as derived from Z table =0 .9693

Answer to question C :

Required probability = 0.85

Corresponding Z value = NORMSINV ( 0.85) = 1.036

Project duration for this certainty

= Schedule duration + Z value x Standard deviation of duration of critical path

= 35.67 + 1.036 x 1.78

= 35.67 + 1.844

= 37.514 days

Add a comment
Know the answer?
Add Answer to:
Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT