TIMES (days) |
|||||
Activity |
Start Node |
Finish Node |
OPTIMISTIC to |
MOST LIKELY tm |
PESSIMISTIC tp |
A |
1 |
2 |
24 |
30 |
42 |
B |
1 |
3 |
20 |
23 |
32 |
C |
2 |
5 |
15 |
27 |
39 |
D |
3 |
4 |
25 |
43 |
61 |
E |
4 |
5 |
15 |
42 |
69 |
Given the Activity on Arrow Diagram and the data found in the table
above, calculate each of the following values:
Activity A………te = 31
Standard Deviation = 3
Activity B………te =
Standard Deviation =
Activity C………te =
Standard Deviation =
Activity D………te =
Standard Deviation =
Activity E………te =
Standard Deviation = 9
Path 1 – 2 – 5
Mean Time =
Standard Deviation =5
Path 1 – 3 – 4 – 5
Mean Time =
Standard Deviation =
Answer:
Activity | Optimistic time-a | Most likely-m | Pessimistic time-b | Expected time= (a+4*m+ b)/6 | Variance, (sigma)^2= (b-a/6)^2 | Standard deviation= sqrt(variance) |
A | 24 | 30 | 42 | 31 | 9 | 3 |
B | 20 | 23 | 32 | 24 | 4 | 2 |
C | 15 | 27 | 39 | 27 | 16 | 4 |
D | 25 | 43 | 61 | 43 | 36 | 6 |
E | 15 | 42 | 69 | 42 | 81 | 9 |
Paths and standard deviation
Paths | Duration | Variance | standard deviation= sqrt(variance) | |
A-C | 1-2-5 | 58 | 25 | 5 |
B-D-E | 1-3-4-5 | 109 | 121 | 11 |
TIMES (days) Activity Start Node Finish Node OPTIMISTIC to MOST LIKELY tm PESSIMISTIC tp A 1...
Consider the following work breakdown structure: Start Finish Time Estimates(wks) Activity Node Node to tm tp A 1 2 11 20 29 B 2 3 2 5 8 C 2 4 18 30 42 D 3 4 7 10 13 E 1 4 31 40 43 What is the estimated standard deviation in the time for activity E?
Please use the table to answer questions, SHOW WORK Consider the following work breakdown structure for questions 46-50: Duration (Days) Most Start Finish Activity Node Node Optimistic Likely Pessimistic 50 31 70 41 35 59 34 82 41 58 32 30 5 46 What is the estimated expected (mean) time tor activity D? A 32 days B. 41 days C 44 days D. 42 days E 40 dayts 46 What is the estimated standard deviation for the critical path? A...
Given the following activity list and times in days: (15 points) Activity Optimistic Most Likely Pessimistic Time Time Time A 7 10 12 B 6 8 14 C 5 9 12 D 12 14 21 E 10 12 15 F 4 5 8 G 1 3 8 H 12 15 17 NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”. Calculate the schedule duration of the critical path in days. What is the probability of the project being completed...
123) Given (Time in weeks): Activity Optimistic Most Likely Pessimistic A 3 4 5 B 6 7 14 C 2 3 10 D 6 9 12 E 4 5 12 F 1 3 11 G 1 2 9 H 2 5 8 I 1 4 7 Determine: (a) the critical path. ( HOW DO I DO THIS WITH OUT A PREDECESSOR?) (b) the probability that the project will be completed in 22 weeks.
Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B - 4 6 10 C A,B 2 5 8 D B 3 5 9 E A,C 3 6 9 F C,E 1 3 5 G C,D 3 4 9 H D 4 6 10 I F,G 3 4 9 J H 2 4 6 A).Draw the project network b).what is the expected completion time of the project. c) after your calculation, if you find one...
Given an activity's optimistic, most likely, and pessimistic time estimates of 5, 7, and 15 days respectively, compute the PERT expected activity time (t) and variance of activity completion time (Var) for this activity. 1. t = 8, and Var = 2.78 2. t = 7, and Var = 1.78 3. t = 14, and Var = 2.78 4. t = 8, and Var = 1.78
(15 points) Activity Immediate Predecessor Optimistic Time Most likely Time Pessimistic Time A NONE 4 7 9 B A 2 4 6 C A 6 9 9 D B, C 5 5 5 E C 2 5 9 F D, E 3 3 6 Use both the longest path method and ES/EF; LS/LF method for the following questions (e) What are the slack values for non-critical activities? (4 points) (f) What is the probability that the project will be...
Assume all activities A, B, D are on the critical path. Activity Optimistic Time Most Likely Time Pessimistic Time A 1 4 10 B 4 9 10 C 12 17 28 D 4 5 6 The expected time for activity B is? 18.0 4.5 8.33 6.17 What is the standard deviation for the project? 4.43 2.11 1.67 2.80
Estimated activity times and precedences are given below: Activity Optimistic Most Likely Pessimistic Required Precedence A 6 7 14 B 8 10 12 C 2 3 4 D 6 7 8 A E 5 5.5 9 B, C F 5 7 9 B, C G 4 6 8 D, E H 2.7 3 3.5 F What is the probability that the project will be completed within: A. 21 Days B. 22 Days C. 25 Days
Use the network activity diagram and table below to answer questions 45-53. Activity Optimistic Most Probable Pessimistic A 5 7 B 3 5 7 C 1 2 9 5 E 3 4 2 3 10 G 6 7 14 H 4 12 B G E H. C A. Finish Start F D Using the three time estimate approach, what is the value of uC? O 6 O4 None of the above are correct Use the network activity diagram and table...