Question

Please use the table to answer questions, SHOW WORK

Consider the following work breakdown structure for questions 46-50: Duration (Days) Most Start Finish Activity Node Node OptWhat is the estimated expected (mean) time tor activity D? A 32 days B. 41 days C 44 days D. 42 days E 40 dayts 46 What is th

Consider the following work breakdown structure for questions 46-50: Duration (Days) Most Start Finish Activity Node Node Optimistic Likely Pessimistic 50 31 70 41 35 59 34 82 41 58 32 30 5 46
What is the estimated expected (mean) time tor activity D? A 32 days B. 41 days C 44 days D. 42 days E 40 dayts 46 What is the estimated standard deviation for the critical path? A 6 days B. 5 days C. 49 days D. 3 days E. 2 days 47 48 What is the estimated expected (mean) time for project completion? A 70 days B 100 days C 106 days D 120 days E. 226 days What is the estimated slack time for activity D? A 0 days B. 10days C. 14 days D. 20 days E. 80 days 49 What is the probability that this project will be completed within 130 days? A 08413 В 09 C 09544 D 0.9772 50
0 0
Add a comment Improve this question Transcribed image text
Answer #1

A 50 2 5 (90 2 6 D (46 了

50 30 70 40 1 Activity Optimistic Most Likely Pessimistic Expected (Mean) time Variance 59 34 82 50 31 70 41 35 41 16 58 32 3

Expected mean time = (Optimistic + pessimistic + 4*most likely)/6

Variance = ((Pessimistic - Optimistic)/6)^2

46.

Correct answer is E.40 days

47.

Path available: A-C duration => 120 days

B-D-E duration => 106 days

Critical path is A-C
Variance of critical path = 9+16 = 25 days
Standard deviation of Critical path A-C is sqrt(25) = 5 days
So correct answer is B. 5 days

48.

Estimated time for project completion = Duration of critical path A-C =120 days

Correct answer is D. 120 days

49.

Earliest Start time of B = 0 days
Earliest Finish time of B = Earliest Start time of B + Duration of B = 0+30 = 30 days

Earliest start time of D = Earliest Finish time of B = 30 days
Earliest Finish time of D = Earliest Start time of D + Duration of D = 30+40 = 70 days

Late Finish of E = 120 days
Late Start of E = Late Finish of E - Duration of E = 120 - 36 = 84 days

Late Finish of D = Late Start of E = 84 days

Slack of D = Late Finish - Early Finish = 84 - 70 = 14 days

Correct answer is C. 14 days

50.

When x = 130

z = (130 - 120)/5 = 2

Probability of project completing within 130 days = P(Z<2) = 0.9772

So correct answer is D) 0.9772

Add a comment
Know the answer?
Add Answer to:
Please use the table to answer questions, SHOW WORK Consider the following work breakdown structure for questions 46-50: Duration (Days) Most Start Finish Activity Node Node Optimistic Likely Pessimi...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • TIMES (days) Activity Start Node Finish Node OPTIMISTIC to MOST LIKELY tm PESSIMISTIC tp A 1...

    TIMES (days) Activity Start Node Finish Node OPTIMISTIC to MOST LIKELY tm PESSIMISTIC tp A 1 2 24 30 42 B 1 3 20 23 32 C 2 5 15 27 39 D 3 4 25 43 61 E 4 5 15 42 69 Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity A………te = 31 Standard Deviation = 3 Activity B………te = Standard Deviation = Activity C………te...

  • Activity D on a PERT network has an optimistic duration of 3 days, a most likely...

    Activity D on a PERT network has an optimistic duration of 3 days, a most likely duration of 5 days and a pessimistic duration of 13 days. What is the expected duration of activity D? Formula: Expected Activity time: t = (a + 4m + b)/6 a. 5 days b. 6 days c. 7 days d. 10 days e. 12 days

  • Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME days) MOST LIKELY...

    Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME days) MOST LIKELY TIME (days) 10 10 10 B.C DE The total slack for activity D is O 2 O O O

  • Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic...

    Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic                         Time                Time                Time A                     7                      10                    12 B                     6                      8                      14 C                     5                      9                      12 D                     12                    14                    21 E                      10                    12                    15 F                      4                      5                      8 G                     1                      3                      8 H                     12                    15                    17 NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”. Calculate the schedule duration of the critical path in days. What is the probability of the project being completed...

  • Use the network activity diagram and table below to answer questions 45-53. Activity Optimistic Most Probable...

    Use the network activity diagram and table below to answer questions 45-53. Activity Optimistic Most Probable Pessimistic A 5 7 B 3 5 7 C 1 2 9 5 E 3 4 2 3 10 G 6 7 14 H 4 12 B G E H. C A. Finish Start F D Using the three time estimate approach, what is the value of uC? O 6 O4 None of the above are correct Use the network activity diagram and table...

  • Consider the following work breakdown structure: Start Finish Time Estimates(wks) Activity Node Node to tm tp...

    Consider the following work breakdown structure: Start Finish Time Estimates(wks) Activity Node Node to tm tp A 1 2 11 20 29 B 2 3 2 5 8 C 2 4 18 30 42 D 3 4 7 10 13 E 1 4 31 40 43 What is the estimated standard deviation in the time for activity E?

  • Consider the following table of activities. What is the estimated time of the completion of the...

    Consider the following table of activities. What is the estimated time of the completion of the project? Activity Immediate Optimistic Most Likely Predecessor Estimate Estimate A 44 50 B 45 60 A 42 45 D 31 40 E 27 36 F D. E 58 70 (time in days) Pessimistic Estimate 36 75 48 49 39 82 A, B Select one: a. 200 days b. 170 days c. 210 days d. 160 days

  • tki 4. What is the estimated slack time for activity A? a. O days b. 20...

    tki 4. What is the estimated slack time for activity A? a. O days b. 20 days c. 40 days d. 60 days 5. What is the distribution of assumed project completio a. Normalb. Beta c. Uniform di Binomia shqi - k activity in Belar 6. Write down the critical path: A) START A NE SU Activity Immediate Predecessor Most Likely Estimate Optimistic Estimate 38 90 85 - 가 Pessimistic. Estimate 62 0 50 108 lat 99 100 25 100...

  • Estimated activity times and precedences are given below: Activity Optimistic Most Likely Pessimistic Required Precedence A...

    Estimated activity times and precedences are given below: Activity Optimistic Most Likely Pessimistic Required Precedence A 6 7 14 B 8 10 12 C 2 3 4 D 6 7 8 A E 5 5.5 9 B, C F 5 7 9 B, C G 4 6 8 D, E H 2.7 3 3.5 F What is the probability that the project will be completed within: A. 21 Days B. 22 Days C. 25 Days

  • QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questio...

    QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT