tki 4. What is the estimated slack time for activity A? a. O days b. 20...
Time Estimates (days) Start A, B, C 38 108 115 85 19 91 62 100 25 100 65 End 115 68 End What is the estimated slack time for activity A? O 0 days O 20 days O 40 days 60 days O 100 days Time Estimates (days) Start A, B, C 38 108 115 85 19 91 62 100 25 100 65 End 115 68 End What is the estimated slack time for activity A? O 0 days O...
Consider the following table of activities. What is the estimated time of the completion of the project? Activity Immediate Optimistic Most Likely Predecessor Estimate Estimate A 44 50 B 45 60 A 42 45 D 31 40 E 27 36 F D. E 58 70 (time in days) Pessimistic Estimate 36 75 48 49 39 82 A, B Select one: a. 200 days b. 170 days c. 210 days d. 160 days
Activity Activity Predecessor Time (days) A -- 4 B -- 12 C A, B 15 D A, B 8 E A, B 6 F C, D, E 14 G C, D, E 3 H F, G 6 The expected completion time for the project above is? 27 days 68 days 47 days 30 days The critical path for the project is? B, C, F, H B, C, F, G, H A, C, F, G A, C, E, H How much...
Please use the table to answer questions, SHOW WORK Consider the following work breakdown structure for questions 46-50: Duration (Days) Most Start Finish Activity Node Node Optimistic Likely Pessimistic 50 31 70 41 35 59 34 82 41 58 32 30 5 46 What is the estimated expected (mean) time tor activity D? A 32 days B. 41 days C 44 days D. 42 days E 40 dayts 46 What is the estimated standard deviation for the critical path? A...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME days) MOST LIKELY TIME (days) 10 10 10 B.C DE The total slack for activity D is O 2 O O O
(15 points) Activity Immediate Predecessor Optimistic Time Most likely Time Pessimistic Time A NONE 4 7 9 B A 2 4 6 C A 6 9 9 D B, C 5 5 5 E C 2 5 9 F D, E 3 3 6 Use both the longest path method and ES/EF; LS/LF method for the following questions (e) What are the slack values for non-critical activities? (4 points) (f) What is the probability that the project will be...
the estimated mean time for an activity with a most likely time (m) equal to 14 days, the optimistic time (a) equal to 9 days, and the pessimistic time (b) equal to 21 days is?
Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...
5. A project has critical path activities A, B, and C. A is the predecessor of B. B is the predecessor of C. The duration estimate for activity A, B and C is shown in the following table. Fill the table with mean duration, standard deviation, and variance for activities and the whole project (critical path). Determine what is the probability of completing this project within 80 days? (10 points) Activity Optimistic Pessimistic Most likely Mean Standard Variance deviation duration...
activity immediate processor activity time (days) A - 6 B - 8 C A,B 5 D B 4 E C 7 F C,D 3 G D 6 H E,F,G 5 Given the following information for a project. SHOW ALL WORK. a) Draw the AON(Activity-On-Node) project network b) Write the estimated slack times for activities A-H c) Identify the critical path d) Determine the total completion time of the project.