Normal completion time = 14 weeks
b)
The first activity to crash is D by 2 weeks at a per week crashing cost of 75 dollas
Next, one should crash activity D and activity E by 2 weeks each for an additional total per week crashing of 150 dollars (this is total per week cost for both activities D and E)
c)
Next activity to crash in order is G by 2 weeks at a per week crashing cost of 250 dollars
Next, one should crash activity A and activity E by 1 week each at a total per week crashing cost of 775 dollars
Total cost of crashing the project to 7 weeks = 1725 dollars
Kampel Products makes a vento comerciales C related data are in the following table o ng...
Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table: Activity A Normal Time (weeks) 3 Crash Time (weeks) 2 B 2 1 1 Normal Cost $1,200 $2,000 $400 $1,500 $950 $4,500 $1,600 Total Cost with Immediate Crashing Predecessor(s) $1,800 $2,800 $400 $1,820 A $1,250 B $5,500 с $2,300...
Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table: Activity Normal Time(weeks) Crash Time(weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 3 2 $ 1,200 $1,800 — B 2 1 $2,100 $2,900 __ C 1 1 $400 $400 — D 7 3 $1,300...
Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Duration (weeks) Activity A (start) Precedes B, C Crash Cost/Week $400 $100 $200 $300 $400 F F (end) 2 Suppose that Rafay is only given 5 weeks (instead of 7) to complete the project. By how many weeks should each activity be crashed in order to...
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: To Cost Normal Time (weeks) Crash Time Normal with Activity (weeks) Cost Crashing Immediate Predecessor(s) $2.700 A $2,000 7 $2,300 S3,100 3 $500 $500 S2,300 $2,580 A E 5900 $1.275 F F $3.400 2 S4,800 C G $1,500 $2.100 D, E a) Based on...
Development of a new deluxe version of a particular toy is being considered by T-O-Y Inc. The activities necessary for the completion of this project along with the relevant information for each activity are listed in the following table. The Total Crash Time represents the time for that activity after it has been crashed the maximum crash time allowed for that activity. For example, we can reduce the time for Activity A by one week to 3 weeks after crashing...
Suppose that Rafay is only given 7 weeks (instead of 10) to
complete the project . By how many weeks should each activity be
crashed in order to meet the deadline? Assume that you can crash an
activity down to 0 weeks duration.
Activity
Each Activity Should be Reduced BY (weeks)
A
(weeks)- ?
B
(weeks)- ?
C
(weeks)- ?
D
(weeks)- ?
E
(weeks)- ?
F
(weeks)- ?
What is the total crashing cost ?
The following is a...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Activity Duration (weeks) Precedes Crash Cost/Week A (start) 2 B, C $ 370 B 2 E $ 130 C 4 F $ 200 E 1 F $ 150 F (end) 2 — $ 420 Suppose that Rafay is only given 5 weeks (instead of 8) to...
1) Based on the given information regarding the activities for
the project, the project length= ___ weeks.
2) The total cost required for completing this project on normal
time= $____
3) For reducing the duration of the project by one week, the
activity that should be crashed first is activity ___.
4) The cost of the project based on the first activity selected
for crashing will increase by $___.
5) The maximum weeks by which the project can be reduced...
I just need the last two parts of the question answered.
PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) $1,050 $2,000 $2,560 $2,600 $1,300 $2,600 $2,200 $1,800 $2,400 4 $4,200 $5,540 $2,050 4...