Question

Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,000...

Table of Crashing Decision

ACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASH
A...323,0003,300
B...648,0009,000
CA114,0004,000
      
DA543,5004,000
EB434,7505,500
FC222,0002,000
      
GD114,0004,000
HD,F323,5003,750
IE,G323,0004,250
JE215,0007,000

Since no indirect cost nor penalty cost information is offered, please consider the schedule and crash cost issues only.

1. Using Table of Crashing Decision, what is the earliest completion time of this project if normal times are used for all activities?

A. fewer than 13 weeks; B. 13 weeks; C. 14 weeks; D. more than 14 weeks

2. Using Table of Crashing Decision, what is the minimum time schedule for this project?

A. fewer than 8 weeks; B. 8 weeks; C. 9 weeks; D. more than 9 weeks

3. Using Table of Crashing Decision, if the project completion time has to be reduced by one week, which of the following activities should be crashed to minimize the extra cost of earlier completion?

A. Activity E; B. Activity J; C.Activity B; D. Activity H

4. Using Table of Crashing Decision, what is the difference in dollars, between the minimum-time schedule and the schedule created by crashing all activities to their limits? Assume that there are no indirect or penalty costs.

A. less than or equal to $1,000; B. greater than $1,000 but less than or equal to $2,000; C. greater than $2,000 but less than or equal to $3,000; D. greater than $3,000

5. Using Table of Crashing Decision, if the project's normal earliest completion time is to be reduced by two weeks, what is the minimum additional cost that will be incurred in achieving this two-week reduction?

A. less than or equal to $1,000; B. greater than $1,000 but less than or equal to $1,500; C. greater than $1,500 but less than or equal to $2,000; D. greater than $2,000


0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

S ES Tosk/EF LS Time LF * Activity. on-nude diagamia ES: Early starti Efs Early finish Is-hate start: IF - Late Finish slack(T) (NO (T-NO (G-n/ each * Adividy, schedule Activity ceashing Total Normal weach each cost possible achiutty free week A B cContacto completion time of project (normai] * washing the project, 2 C3 3 FS AQ 3lilu u 216 122 206 2416 61319 A Stan তি। 6

Add a comment
Know the answer?
Add Answer to:
Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,000...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Help Please

    Table of Crashing DecisionSince no indirect cost nor penaly cost information is offered, please consider the schedule and crash cost issues only,Using Table of Crashing Decision, what is the minimum time schedule for this project?fewer than 8 weeks8 weeks9 weeksmore than 9 weeksSince no indirect cost nor penaly cost information is offered, please consider the schedule and crash cost issues only,Using Table of Crashing Decision, what is the difference, in dollars, between the minimum-time schedule and the schedule created by...

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • Software Installation: You are the project manager of the software installation project (see figure & table)...

    Software Installation: You are the project manager of the software installation project (see figure & table) below. You would like to find the minimum-cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,500 per week. Oo un D FINISH START START I Normal Normal Crash Crash Max reduction $ per Week Activity Time Cost Time Cost AI 5...

  • Supose Bowman is the first week, it is paid Si50 for crashing it the second week, it is paid $125...

    Supose Bowman is the first week, it is paid Si50 for crashing it the second week, it is paid $125: for crashing it the third week, it is paid S100, for crashing it any additional weelks, it is 575 per week. What is the minimum cost schedule and what is the cost of the project based on this schedule 1 9:03 LTE 星期二 下午9:59 编辑 12-24 Bowman Builders manufactures steel storage sneas for commercial use. Joe Bowman, president of Bowman...

  • Solve the following project crashing problem adopted from Heizer et al. (2016). Attempt the question before looking up the solution on Page 855 of Heizer et. al. 2016 3.32Kimpel Products makes pi...

    Solve the following project crashing problem adopted from Heizer et al. (2016). Attempt the question before looking up the solution on Page 855 of Heizer et. al. 2016 3.32Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are given in the following table: NORMAL CRASH TIME TIME NORMALI CRASH! IMMEDIATE ACTIVITY (WEEKS) (WEEKS) COST...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 narl Case Study A Table 1 below contains activities associated with a...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 nar Case Study A Table 1 below contains activities associated with a...

  • You are the manager of a project to improve a billing process at your firm. The...

    You are the manager of a project to improve a billing process at your firm. The table below contains the data you will need to conduct a cost analysis of the project Indirect costs are $1,600 per week, and penalty costs are $600 per week after week 12 Immediate Normal Cost Crash Cost Predecessor(s) Normal Time (weeks) Crash Time (weeks) ($) ($) Activity A 4 5,500 7,500 В 5 3 8,000 9,500 A 1 1 3,500 3,500 В 6 3...

  • Given below is the crashing data for a project along with other data. The project completion...

    Given below is the crashing data for a project along with other data. The project completion time is 20 davs. Determine: (a) the crash slope (i.e crash cost/day) for all activities, (b) the normal total project cost, (c) prioritized the list of activities for crashing from best to worst, (d) the best activity to crash if the project has to be completed in 19 days and alternative critical paths, if any, (e) the earliest time the project can be completed,...

  • Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens...

    Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table: Activity A Normal Time (weeks) 3 Crash Time (weeks) 2 B 2 1 1 Normal Cost $1,200 $2,000 $400 $1,500 $950 $4,500 $1,600 Total Cost with Immediate Crashing Predecessor(s) $1,800 $2,800 $400 $1,820 A $1,250 B $5,500 с $2,300...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT