Question

Supose Bowman is the first week, it is paid Si50 for crashing it the second week, it is paid $125: for crashing it the third
1 9:03 LTE 星期二 下午9:59 编辑 12-24 Bowman Builders manufactures steel storage sneas for commercial use. Joe Bowman, president of
the project. For crashing it i Suppose Bowman is paid additional money for crashing the first week, it is paid S150; for cras
Supose Bowman is the first week, it is paid Si50 for crashing it the second week, it is paid $125: for crashing it the third week, it is paid S100, for crashing it any additional weelks, it is 575 per week. What is the minimum cost schedule and what is the cost of the project based on this schedule
1 9:03 LTE 星期二 下午9:59 编辑 12-24 Bowman Builders manufactures steel storage sneas for commercial use. Joe Bowman, president of Bowman Builders, is contemplating producing sheds for home use. The activities necessary to build an experimental model and related data accompanying table are given in the to NORMAL CRASH NORMAL CRASH COST COST IMMEDIATE ACTIVITY TIME TIME 1,000 1,600 2,000 2.700 300 300 3 1,300 1,600 850 1,000 14,000 5,000 2 1.500 2.,000 D. E
the project. For crashing it i Suppose Bowman is paid additional money for crashing the first week, it is paid S150; for crashing it the second week, it is paid S125; for crashing it the third week, it is paid S100, for crashing it any additional weeks, it is $75 per week. What is the minimum cost schedule and what is the cost of the project based on this schedule.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution :

Minimum cost schedule is 12 weeks with cost of 10,825

Predeces Normal ras Norma Crash Crashing Iteration Iteration Iteration Activity sor cost/day ES 600.0 700.0 Time Cost Cost EF

Add a comment
Know the answer?
Add Answer to:
Supose Bowman is the first week, it is paid Si50 for crashing it the second week, it is paid $125...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Expert Q&A 4, page 149, Problems, #24- weeks c) Suppose the first Rowman is paid addirional money...

    Expert Q&A 4, page 149, Problems, #24- weeks c) Suppose the first Rowman is paid addirional money for crasking the p week, it is paid $150: for crashing i the second we t it the third week, it is paid $100 for crasking it ay week. What is the minimum cost schedkadwhish: 12-24 Bowman Builders manufactures steel storage sneas for commercial use. Joe Bowman, president of Bowman Builders, is contemplating producing sheds for home use. The activities necessary to build...

  • Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,000...

    Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,0003,300B...648,0009,000CA114,0004,000      DA543,5004,000EB434,7505,500FC222,0002,000      GD114,0004,000HD,F323,5003,750IE,G323,0004,250JE215,0007,000Since no indirect cost nor penalty cost information is offered, please consider the schedule and crash cost issues only.1. Using Table of Crashing Decision, what is the earliest completion time of this project if normal times are used for all activities?A. fewer than 13 weeks; B. 13 weeks; C. 14 weeks; D. more than 14 weeks2. Using Table of Crashing Decision, what is the minimum time schedule for this project?A. fewer than 8 weeks; B. 8...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT