Solution :
Minimum cost schedule is 12 weeks with cost of 10,825
Supose Bowman is the first week, it is paid Si50 for crashing it the second week, it is paid $125...
Expert Q&A 4, page 149, Problems, #24- weeks c) Suppose the first Rowman is paid addirional money for crasking the p week, it is paid $150: for crashing i the second we t it the third week, it is paid $100 for crasking it ay week. What is the minimum cost schedkadwhish: 12-24 Bowman Builders manufactures steel storage sneas for commercial use. Joe Bowman, president of Bowman Builders, is contemplating producing sheds for home use. The activities necessary to build...
Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,0003,300B...648,0009,000CA114,0004,000 DA543,5004,000EB434,7505,500FC222,0002,000 GD114,0004,000HD,F323,5003,750IE,G323,0004,250JE215,0007,000Since no indirect cost nor penalty cost information is offered, please consider the schedule and crash cost issues only.1. Using Table of Crashing Decision, what is the earliest completion time of this project if normal times are used for all activities?A. fewer than 13 weeks; B. 13 weeks; C. 14 weeks; D. more than 14 weeks2. Using Table of Crashing Decision, what is the minimum time schedule for this project?A. fewer than 8 weeks; B. 8...