21) Determine the information missing from Table 7.7; then answer the following questions. How many week(s) of crashing are available for activity D in Table 2.9?
22) How many week(s) of crashing are available for activity B in Table 7.7?
23) How many weeks of crashing are available for activity C in Table 7.7?
24) What is the crashing cost per week for activity A in Table 7.7?
25) What is the crashing cost per week for activity E in Table 7.7?
26) What is the crashing cost per week for activity F in Table 7.7?
27) If a decision is made to crash activity D in Table 7.7 by one week, what is the cost for this one week of crashing?
28) Which activity should be crashed first for the project shown in Table 7.7?
[Note: All the cost has been expressed as ($000 s) such as cost value 54 is considered for cost value 54000]
Activity |
Normal Time |
Crash Time |
Normal cost($000s) |
Crash cost ($000s) |
Slope |
A |
4 |
2 |
8 |
14 |
3 |
B |
3 |
2 |
9 |
11 |
2 |
C |
4 |
4 |
10 |
10 |
0 |
D |
5 |
3 |
10 |
15 |
2.5 |
E |
4 |
1 |
11 |
14 |
1 |
F |
1 |
1 |
6 |
6 |
0 |
54 |
Total Normal cost = $54
Crashing cost per week = Slope of an activity = (Crash cost – normal cost)/(Normal Time – crash time)
So, Slope of A = (14-8)/(4-2) = 3
Likewise, slope for other activities have been calculated.
Let’s see how many paths are available to complete the activities and duration of each paths to find the critical path
Path |
Duration |
A-B-D-F |
4+3+5+1 = 13 |
A-C-D-F |
4+4+5+1 = 14 |
A-C-E-F |
4+4+4+1 = 13 |
Critical path is the path having maximum duration here critical path is A-C-D-F
Normal project completion time = 14 weeks
1st Iteration
Crash limit and Slope
Critical Path |
Critical Activities |
Crash Limit(Normal time - crash time) |
Cost Slope |
A-C-D-F |
A |
2 |
3 |
C |
0 |
0 |
|
D |
2 |
2.5 |
|
F |
0 |
0 |
Least cost slope is of activity D .So, first crash activity D by 1 week as difference between critical path and next path is 1 day .
Critical activities,
Path |
Duration |
A-B-D-F |
4+3+4+1 = 12 |
A-C-D-F |
4+4+4+1 = 13 |
A-C-E-F |
4+4+4+1 = 13 |
Now project completion time is 13 weeks and we have two critical paths A-C-D-F and A-C-E-F
2nd Iteration
Crash limit and Slope
Critical Path |
Critical Activities |
Crash Limit(Normal time - crash time) |
Cost Slope |
A-C-D-F |
A |
2 |
3 |
C |
0 |
0 |
|
D |
1 |
2.5 |
|
F |
0 |
0 |
Critical Path |
Critical Activities |
Crash Limit(Normal time - crash time) |
Cost Slope |
A-C-E-F |
A |
2 |
3 |
C |
0 |
0 |
|
E |
3 |
1 |
|
F |
0 |
0 |
Crash combinations between critical paths as we have to crash in such a way that both the critical paths are reduced
Crash combinations |
Cost slope |
A |
3 |
D,E |
3.5 |
Crash A by 1 day as difference between critical path and next path is 1 day so crash cost = 3 and project duration is now 12 weeks
Critical activities,
Path |
Duration |
A-B-D-F |
3+3+4+1 = 11 |
A-C-D-F |
3+4+4+1 = 12 |
A-C-E-F |
3+4+4+1 = 12 |
3rd iteration
Crash limit and Slope
Critical Path |
Critical Activities |
Crash Limit(Normal time - crash time) |
Cost Slope |
A-C-D-F |
A |
1 |
3 |
C |
0 |
0 |
|
D |
1 |
2.5 |
|
F |
0 |
0 |
Critical Path |
Critical Activities |
Crash Limit(Normal time - crash time) |
Cost Slope |
A-C-E-F |
A |
1 |
3 |
C |
0 |
0 |
|
E |
3 |
1 |
|
F |
0 |
0 |
Crash combinations between critical paths
Crash combinations |
Cost slope |
A |
3 |
D,E |
3.5 |
Crash A by 1 day so crash cost = 3 and project duration is now 11 weeks
Critical activities,
Path |
Duration |
A-B-D-F |
2+3+4+1 = 10 |
A-C-D-F |
2+4+4+1 = 11 |
A-C-E-F |
2+4+4+1 = 11 |
4th iteration
Crash limit and Slope
Critical Path |
Critical Activities |
Crash Limit(Normal time - crash time) |
Cost Slope |
A-C-D-F |
A |
0 |
3 |
C |
0 |
0 |
|
D |
1 |
2.5 |
|
F |
0 |
0 |
Critical Path |
Critical Activities |
Crash Limit(Normal time - crash time) |
Cost Slope |
A-C-E-F |
A |
0 |
3 |
C |
0 |
0 |
|
E |
3 |
1 |
|
F |
0 |
0 |
Crash combinations between critical paths
Crash combinations |
Cost slope |
D,E |
3.5 |
Now we have to crash D and E simultaneously as D has 1 crash limit so let’s Crash D by 1 day and E by 1 day and project duration is now 10 weeks
Critical activities,
Path |
Duration |
A-B-D-F |
2+3+3+1 = 9 |
A-C-D-F |
2+4+3+1 = 10 |
A-C-E-F |
2+4+3+1 = 10 |
Now we can not crash more as crash limit of D = 0
Based on the above table;
Activity |
Normal Time |
Crash Time |
Normal cost($000s) |
Crash cost ($000s) |
Available weeks of crashing |
Crashing cost/week |
A |
4 |
2 |
8 |
14 |
2 |
3 |
B |
3 |
2 |
9 |
11 |
0 |
2 |
C |
4 |
4 |
10 |
10 |
0 |
0 |
D |
5 |
3 |
10 |
15 |
2 |
2.5 |
E |
4 |
1 |
11 |
14 |
1 |
1 |
F |
1 |
1 |
6 |
6 |
0 |
0 |
54 |
20.
Critical path is the path having maximum duration here critical path is A-C-D-F
21. Available week for crashing for D = 2
22. Available week for crashing for B = 0
23. Available week for crashing for C= 0
24. Crashing cost per week for activity A = 3
25. Crashing cost per week for activity E = 1
26. Crashing cost per week for activity F = 0
27. If a decision is made to crash activity D in Table 7.7 by one week, what is the cost for this one week of crashing? Ans is 2.5
28. Which activity should be crashed first for the project shown in Table 7.7? Ans is Activity D
21) Determine the information missing from Table 7.7; then answer the following questions. How many week(s)...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Duration (weeks) Activity A (start) Precedes B, C Crash Cost/Week $400 $100 $200 $300 $400 F F (end) 2 Suppose that Rafay is only given 5 weeks (instead of 7) to complete the project. By how many weeks should each activity be crashed in order to...
I ONLY need help on letters G and I. According to the answers I've tried for these, it is NOT Activity G for the letter G and not $2,120 for letter I. M5_A5. A computer installation project is being reviewed. Assume the project has to be completed in 16 weeks. Crash the project as necessary (crashing one week at a time). The relevant information is in the table below. CRASH STANDARD STANDARD CRASH IMMEDIATE ACTIVITY TIME TIME COST PREDECESSORS COST...
Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,0003,300B...648,0009,000CA114,0004,000 DA543,5004,000EB434,7505,500FC222,0002,000 GD114,0004,000HD,F323,5003,750IE,G323,0004,250JE215,0007,000Since no indirect cost nor penalty cost information is offered, please consider the schedule and crash cost issues only.1. Using Table of Crashing Decision, what is the earliest completion time of this project if normal times are used for all activities?A. fewer than 13 weeks; B. 13 weeks; C. 14 weeks; D. more than 14 weeks2. Using Table of Crashing Decision, what is the minimum time schedule for this project?A. fewer than 8 weeks; B. 8...
Use the following information for questions 15 to 24. Egon Spengler is planning a charity benefit gala for his “Save the City” campaign. However, because one of his partners, Peter Venkman, has difficulty staying on task, the project is scheduled and they are running out of time. Egon has used project management principles to lay out the task relationships and he finds that if they follow the traditional schedule, as outlined below, they will not have enough time to get...
Use the following crashing table to answer Project time Period cost Cumulative cost A B C D E F G H I J 37 0 0 36 60 120 1 35 80 200 1 1 34 80 280 2 2 33 80 360 3 2 32 135 495 3 1 2 1 31 180 675 1 4 1 2 1 30 180 855 2 5 1 2 1 29 733.33 1588.33 1 2 5 1 2 1 28 983.33 2571.67...
Use the following crashing table to answer Project time Period cost Cumulative cost A B C D E F G H I J 37 0 0 36 60 120 1 35 80 200 1 1 34 80 280 2 2 33 80 360 3 2 32 135 495 3 1 2 1 31 180 675 1 4 1 2 1 30 180 855 2 5 1 2 1 29 733.33 1588.33 1 2 5 1 2 1 28 983.33 2571.67...
Suppose that Rafay is only given 7 weeks (instead of 10) to complete the project . By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Activity Each Activity Should be Reduced BY (weeks) A (weeks)- ? B (weeks)- ? C (weeks)- ? D (weeks)- ? E (weeks)- ? F (weeks)- ? What is the total crashing cost ? The following is a...
Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...
Kampel Products makes a vento comerciales C related data are in the following table o ng r eso de Nom e Act Crash Time Normal wek) Court $1.000 $2300 SD 51.000 5900 $4500 $1,300 Cost with dia Casing Predeces) 100 $100 $100 5700 51125 $5500 52 300 thing the activities a) Based on the given information regarding the activities for the project the project completion date wooks b) To reduce the duration of the project 10 weeks at the least...
I just need the last two parts of the question answered. PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) $1,050 $2,000 $2,560 $2,600 $1,300 $2,600 $2,200 $1,800 $2,400 4 $4,200 $5,540 $2,050 4...