Question

Use the following information for questions 15 to 24. Egon Spengler is planning a charity benefit...

Use the following information for questions 15 to 24.

Egon Spengler is planning a charity benefit gala for his “Save the City” campaign. However, because one of his partners, Peter Venkman, has difficulty staying on task, the project is scheduled and they are running out of time. Egon has used project management principles to lay out the task relationships and he finds that if they follow the traditional schedule, as outlined below, they will not have enough time to get everything done before the weekend of the gala. Egon has created a list of tasks, their time requirements, and their relationships. He has also begun a network diagram, but needs to know what to do next. He knows that he needs to reduce the total time by five weeks.

Activity

Duration (weeks)

Crash Time (weeks)

Description

Preceding Activity(ies)

Crashing Cost/Week

A

7

6

Determine gala theme

-

$550

B

5

3

Reserve portal location for gala

A

$1,000

C

7

7

Create Marketing Plan

B

$1,500

D

6

5

Ray Parker, Jr. to audition musical acts

B

$1,300

E

6

5

Determine ticket sales method

C

$800

F

7

4

Purchase supplies, including Stay Puff marshmallows

C

$750

G

4

4

Pick musical act and sign contract

D

$400

H

4

1

Sell tickets in person

E

$500

I

5

4

Sell tickets online

E

$1,250

J

1

 

Gala!

H, I, F, G

 

  1. What is the slack time for activity F?
  1. 1
  2. 2
  3. 4
  4. 6
  1. What is the earliest start time for activity J?
  1. 22
  2. 26
  3. 29
  4. 30
  1. What is the latest finish time for activity E?
  1. 22
  2. 25
  3. 26
  4. 30
  1. Which of the following is the critical path at the beginning of the analysis?
  1. ABCFJ
  2. ABDGJ
  3. ABCEIJ
  4. ABCEHJ
  1. What is the first activity that Egon should crash?

a) A

b) B

c) C

d) E

e) I

  1. Activity B can be crashed how many times?

a) 0

b) 1

c) 2

d) 3

e) Infinite

  1. What is the minimum completion time for the project after crashing (until no more crashing is possible)?

a) 23 weeks

b) 26 weeks

c) 27 weeks

d) 29 weeks

  1. If Egon has a budget of only $3,000 for crashing costs, what is the shortest possible completion time?

a) 26 weeks

b) 27 weeks

c) 28 weeks

d) 29 weeks

  1. How much will it cost Egon to reduce the original total project time by four weeks?

a) $550

b) $1,350

c) $2,350

d) $3,350

  1. How much did crashing that last (fifth) week cost Egon?

a) $750

b) $1,000

c) $1,250

d) $1,500

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Use the following information for questions 15 to 24. Egon Spengler is planning a charity benefit...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Use the following information for questions 17 to 26 Egon Spengler is planning a charity benefit...

    Use the following information for questions 17 to 26 Egon Spengler is planning a charity benefit gala for his "Save the City" campaign. However, because one of his partners, Peter Venkman, has difficulty staying on task, the project is scheduled and they are running out of time. Egon has used project management principles to lay out the task relationships and he finds that if they follow the traditional schedule, as outlined below, they will not have enough time to get...

  • How much did crashing that last (fifth) week cost Egon? $750 $1,000 $1,250 $1,500 Use the...

    How much did crashing that last (fifth) week cost Egon? $750 $1,000 $1,250 $1,500 Use the following information for questions 17 to 26. Egon Spengler is planning a charity benefit gala for his "Save the City" campaign. Hawever, because one of his partners, Peter Venkman, has difficulty staying on task, the project is scheduled and they are running out of time. Egon has used project management principles to lay out the task relationships and he finds that if they follow...

  • Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens...

    Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table: Activity A Normal Time (weeks) 3 Crash Time (weeks) 2 B 2 1 1 Normal Cost $1,200 $2,000 $400 $1,500 $950 $4,500 $1,600 Total Cost with Immediate Crashing Predecessor(s) $1,800 $2,800 $400 $1,820 A $1,250 B $5,500 с $2,300...

  • PM.62 The US government has recently contracted with Boeing to build its fleet of airborne tankers....

    PM.62 The US government has recently contracted with Boeing to build its fleet of airborne tankers. The project has been laid out with durations (in weeks), predecessors, and costs included: Activity   Normal Time (weeks)   Crashed Time (weeks)   Normal Cost   Crashed Cost   Predecessor(s)   A 11 10 $1,500 $1,650 - B 7 5 $1,200 $2,490 - C 5 4 $900 $1,200 B D 4 2 $2,100 $3,000 A E 2 1 $550 $1,250 B F 4 3 $660 $1,050 E G 10...

  • Kimpel Products makes pizza ovens for commercial use. James​ Kimpel, CEO, is contemplating producing smaller ovens...

    Kimpel Products makes pizza ovens for commercial use. James​ Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following​ table:                                                                                                                                   Activity Normal Time​(weeks) Crash Time​(weeks) Normal Cost Total Cost with Crashing    Immediate​ Predecessor(s) A 3 2 $ 1,200 $1,800 — B 2 1 $2,100 $2,900    __ C 1 1 $400 $400 — D 7 3 $1,300...

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • I ONLY need help on letters G and I. According to the answers I've tried for...

    I ONLY need help on letters G and I. According to the answers I've tried for these, it is NOT Activity G for the letter G and not $2,120 for letter I. M5_A5. A computer installation project is being reviewed. Assume the project has to be completed in 16 weeks. Crash the project as necessary (crashing one week at a time). The relevant information is in the table below. CRASH STANDARD STANDARD CRASH IMMEDIATE ACTIVITY TIME TIME COST PREDECESSORS COST...

  • 21) Determine the information missing from Table 7.7; then answer the following questions. How many week(s)...

    21) Determine the information missing from Table 7.7; then answer the following questions. How many week(s) of crashing are available for activity D in Table 2.9? 22) How many week(s) of crashing are available for activity B in Table 7.7?23) How many weeks of crashing are available for activity C in Table 7.7? 24) What is the crashing cost per week for activity A in Table 7.7? 25) What is the crashing cost per week for activity E in Table...

  • Use the following crashing table to answer Project time Period cost Cumulative cost A B C...

    Use the following crashing table to answer Project time Period cost Cumulative cost A B C D E F G H I J 37 0 0 36 60 120 1 35 80 200 1 1 34 80 280 2 2 33 80 360 3 2 32 135 495 3 1 2 1 31 180 675 1 4 1 2 1 30 180 855 2 5 1 2 1 29 733.33 1588.33 1 2 5 1 2 1 28 983.33 2571.67...

  • Kampel Products makes a vento comerciales C related data are in the following table o ng...

    Kampel Products makes a vento comerciales C related data are in the following table o ng r eso de Nom e Act Crash Time Normal wek) Court $1.000 $2300 SD 51.000 5900 $4500 $1,300 Cost with dia Casing Predeces) 100 $100 $100 5700 51125 $5500 52 300 thing the activities a) Based on the given information regarding the activities for the project the project completion date wooks b) To reduce the duration of the project 10 weeks at the least...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT