How much did crashing that last (fifth) week cost Egon?
$750
$1,000
$1,250
$1,500
Answer: $1,250
Explanation: First calculate the duration of all the paths that are required to start activity J
Paths |
Time taken by path until activity J |
Duration |
|||
Crash A |
Crash E |
Crash B by 2 weeks |
Crash I |
||
ABCEHJ |
7+5+7+6+4= 29 |
28 |
27 |
25 |
25 |
ABCEIJ |
7+5+7+6+5= 30 (Critical path) |
29 |
28 |
26 |
25 |
ABCFJ |
7+5+7+7= 26 |
25 |
25 |
23 |
23 |
ABDGJ |
7+5+6+4= 22 |
21 |
21 |
19 |
19 |
Total cost of crashing |
0 |
550 |
550+800= $1350 |
1350+2000= $3350 |
3350+ 1250= $4600 |
Crashing fifth week cost Egon $ 1,250
How much did crashing that last (fifth) week cost Egon? $750 $1,000 $1,250 $1,500 Use the...
Use the following information for questions 15 to 24. Egon Spengler is planning a charity benefit gala for his “Save the City” campaign. However, because one of his partners, Peter Venkman, has difficulty staying on task, the project is scheduled and they are running out of time. Egon has used project management principles to lay out the task relationships and he finds that if they follow the traditional schedule, as outlined below, they will not have enough time to get...
Use the following information for questions 17 to 26 Egon Spengler is planning a charity benefit gala for his "Save the City" campaign. However, because one of his partners, Peter Venkman, has difficulty staying on task, the project is scheduled and they are running out of time. Egon has used project management principles to lay out the task relationships and he finds that if they follow the traditional schedule, as outlined below, they will not have enough time to get...