Question

Use the following information for questions 17 to 26 Egon Spengler is planning a charity benefit gala for his Save the CityCrash Duration Time Description Activ Cost/Week (weeks) Preceding Crashing Activity ity(ies) (weeks) Determine $900 gala themPurchase supplies, including Stay C Puff marshmallows $700 Pick musical act and sign contract 4 D $550 Sell tickets in $690 pWhat is the slack time for activity D? Enter your answer as a numerical whole number.What is the minimum completion time for the project after crashing (until no more crashing is possible)? 27 weeks 28 weeks 29If Egon has a budget of only $2,000 for crashing costs, what is the shortest possible completion time? 27 weeks 28 weeks 29 wHow much will it cost Egon to reduce the original total project time by three weeks? $1,530 $2,510 $3,550 $4,150How much did crashing that last (third) week cost Egon? $630 $900 $980 $1000

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The critical path is the path which takes longest time to complete the project. Following is the calculation of critical path

A-B-D-G-J - 23

A-B-C-E-H-J - 30

A-B-C-E-I-J - 31 -----> Critical path

A-B-C-F-J - 27

A-B-C-E-I-J is a critical path because it takes maximum time to complete project.

a) Following is the calculation of slack

Task Predecessor Early Start DurationEarly Finish Late Finish Late Start Slaclk 12 19 18 25 26 12 19 19 26 26 12 12 12 19 19

Early Finish = Early Start + Duration

= 12 + 6

= 18

Late Finish = Early finish of Predecessor (Max time)

= 19

Slack = Late Finish - Early finish

= 19 - 18

= 1

The slack time of the activity D is 1

Following is the calculation of crashing project

Difference Crashing Time Optimal Duration Crashing (week) Activity (1) (2)Cost (4 Crashed Project Cost (Weeks) (week) (Week)

A-B-C-E-I-J is a critical path because it takes maximum time to complete project. Therefore, crashing of the project will be done for this path.

b) From the above table, the minimum completion time for the project after crashing is 31 - 3 = 28 weeks.

c) If the company has the budget of $2,000, then minimum completion of the project will be 31 - 2 = 29 weeks.

Difference Crashing Time Optimal Duration Crashing Activity (1) (2)Cost (4 Crashed Project Cost (Weeks) (week) (week) (Week)

d) The total cost for crashing the project is 900 + 980 + 630 = $2,510

e) Crashing the last week cost $630 (Activity E)

Add a comment
Know the answer?
Add Answer to:
Use the following information for questions 17 to 26 Egon Spengler is planning a charity benefit...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Use the following information for questions 15 to 24. Egon Spengler is planning a charity benefit...

    Use the following information for questions 15 to 24. Egon Spengler is planning a charity benefit gala for his “Save the City” campaign. However, because one of his partners, Peter Venkman, has difficulty staying on task, the project is scheduled and they are running out of time. Egon has used project management principles to lay out the task relationships and he finds that if they follow the traditional schedule, as outlined below, they will not have enough time to get...

  • How much did crashing that last (fifth) week cost Egon? $750 $1,000 $1,250 $1,500 Use the...

    How much did crashing that last (fifth) week cost Egon? $750 $1,000 $1,250 $1,500 Use the following information for questions 17 to 26. Egon Spengler is planning a charity benefit gala for his "Save the City" campaign. Hawever, because one of his partners, Peter Venkman, has difficulty staying on task, the project is scheduled and they are running out of time. Egon has used project management principles to lay out the task relationships and he finds that if they follow...

  • You have recently been hired to help with planning for a music festival in Sydney, Australia...

    You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Immediate Predecessor Activity A B С D E...

  • You have recently been hired to help with planning for a music festival in Sydney, Australia...

    You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Activity A B C D E F G...

  • A senior manager has finished reviewing the latest draft of an upcoming project. the following table...

    A senior manager has finished reviewing the latest draft of an upcoming project. the following table provides information about the project including the normal time for each activity, activity sequence and information about costs to shorten some of the activities and therefore the project duration. As he prepares ro review rhe proposal with the owners he is concerned about the project duration and expects the owners will want the project shortened. Activity Precedes Normal Time. (week) Crashing Costs ($000) 1st...

  • Use the following information to answer question 17 through 19: 17. Doherty & Puthoff, Inc. produces...

    Use the following information to answer question 17 through 19: 17. Doherty & Puthoff, Inc. produces quality BGSU hats for fashion-conscious students. During the year, its highest and lowest production levels occurred in April and October, respectively. In April, it produced 6,000 units at a total cost of $120,000. In October, it produced 2,000 units at a total cost of $80,000. Using the high/low method of estimating costs, the average variable cost of producing a hat would be: a. $10.00...

  • After reading the article, answer the questions that follow. Turning Off, Dining In Last night at...

    After reading the article, answer the questions that follow. Turning Off, Dining In Last night at dinner, I suddenly realized that no one around our table had said anything for quite a while. I looked at my son, who had headphones on and whose face was aglow with the white-blue light of this phone on which he was watching a YouTube video. My daughter was also bathed in this same glow, but a tap-tap-tap was coming from her phone as...

  • Read the Article posted below, then answer the following questions: 1. As a junior member of...

    Read the Article posted below, then answer the following questions: 1. As a junior member of your company’s committee to explore new markets, you have received a memo from the chairperson telling you to be prepared at the next meeting to discuss key questions that need to be addressed if the company decides to look further into the possibility of marketing to the BOP segment. The ultimate goal of this meeting will be to establish a set of general guidelines...

  • Analyze the case the answer the questions: introduction of the case assess the financial reporting landscape...

    Analyze the case the answer the questions: introduction of the case assess the financial reporting landscape considering the user needs, constraints, and business environment, identify the issues, analyze the issues (qualitatively and quantitatively), and provide a recommendation and conclusion. Original content only no copy-paste, please INTRODUCTION Jaden McCoy operated a dairy goat farm in Soddy-Daisy, Tennessee, and was considering expanding the rental of his goats for land clearing. In early 2011, McCoy successfully bid on a job to clear a...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT