Question

PM.62 The US government has recently contracted with Boeing to build its fleet of airborne tankers....

PM.62 The US government has recently contracted with Boeing to build its fleet of airborne tankers. The project has been laid out with durations (in weeks), predecessors, and costs included:

Activity   Normal Time (weeks)   Crashed Time (weeks)   Normal Cost   Crashed Cost   Predecessor(s)  
A 11 10 $1,500 $1,650 -
B 7 5 $1,200 $2,490 -
C 5 4 $900 $1,200 B
D 4 2 $2,100 $3,000 A
E 2 1 $550 $1,250 B
F 4 3 $660 $1,050 E
G 10 6 $560 $1,040 C, D, F

What is the critical path of the project?

B-C-G

A-D-G

B-E-F-G

If you wanted to shorten the overall duration of the project, which activity would you crash first?

B

E

C

G

What would be the weekly crashing cost of the activity you selected in the previous question? (Display your answer to two decimal places.)

   

Crash the project by 5 weeks. What is the total cost of crashing the project (just the additional cost, not total project cost)? (Display your answer to two decimal places.)  

   

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Critical path is longest path of the project = A-D-G = 25 weeks

We will crash activity G first as it is on critical path.

Weekly crashing cost = (1040-560) /(10-6) = $120 / week

Now to crash project by 5 weeks, we first crash G by 4 weeks. This shortens all paths by 4 weeks. Next we crash A by 1 week. The project duration now is 20 weeks. We Crash A as it has lower weekly crash cost compared to D.

Total additional cost = Crash cost - Normal cost = (1040-560) +(1650-1500) = $630

Add a comment
Know the answer?
Add Answer to:
PM.62 The US government has recently contracted with Boeing to build its fleet of airborne tankers....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The US government has contracted with Raytheon to build its new Peacekeeper 2 ballistic missile. The...

    The US government has contracted with Raytheon to build its new Peacekeeper 2 ballistic missile. The project has been laid out with durations (in weeks), predecessors, and costs included: Activity   Normal Time (weeks)   Crashed Time (weeks)   Normal Cost   Crashed Cost   Predecessor(s)   A 8 6 $3,600 $4,250 - B 4 3 $2,250 $3,500 A C 12 10 $6,150 $6,650 B How much would it cost to crash the project by one week?     How much would it cost to crash the...

  • I just need the last two parts of the question answered. PM.66 Real estate developer Russell Call was working with a fe...

    I just need the last two parts of the question answered. PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) $1,050 $2,000 $2,560 $2,600 $1,300 $2,600 $2,200 $1,800 $2,400 4 $4,200 $5,540 $2,050 4...

  • Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's...

    Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: To Cost Normal Time (weeks) Crash Time Normal with Activity (weeks) Cost Crashing Immediate Predecessor(s) $2.700 A $2,000 7 $2,300 S3,100 3 $500 $500 S2,300 $2,580 A E 5900 $1.275 F F $3.400 2 S4,800 C G $1,500 $2.100 D, E a) Based on...

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None...

    Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None None B Cost Normal Crash 1000 1600 2000 2700 300 300 1300 1600 2 1 С 1 1 D A 7 3 E 6 3 B с 1000 5000 F 2 850 4000 1500 NA G D. E 4 2000 What's the normal project completion time? Identify the critical path If you'd like to shorten the project by one week, which activity should you...

  • I ONLY need help on letters G and I. According to the answers I've tried for...

    I ONLY need help on letters G and I. According to the answers I've tried for these, it is NOT Activity G for the letter G and not $2,120 for letter I. M5_A5. A computer installation project is being reviewed. Assume the project has to be completed in 16 weeks. Crash the project as necessary (crashing one week at a time). The relevant information is in the table below. CRASH STANDARD STANDARD CRASH IMMEDIATE ACTIVITY TIME TIME COST PREDECESSORS COST...

  • What is the minimum cost of crashing the following project that Roger Solano manages at Slippery...

    What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4​ days? A)By how many days should each activity be crashed to reduce the project completion time by 4​ days? Fill in the table below. ​(Enter your responses as whole numbers.​) B) The total cost of crashing the project by 4 days is $. (Enter your response as a whole number.) Normal Crash Time Normal Total Cost Activity Time (days) (days)...

  • Kimpel Products makes pizza ovens for commercial use. James​ Kimpel, CEO, is contemplating producing smaller ovens...

    Kimpel Products makes pizza ovens for commercial use. James​ Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following​ table:                                                                                                                                   Activity Normal Time​(weeks) Crash Time​(weeks) Normal Cost Total Cost with Crashing    Immediate​ Predecessor(s) A 3 2 $ 1,200 $1,800 — B 2 1 $2,100 $2,900    __ C 1 1 $400 $400 — D 7 3 $1,300...

  • Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens...

    Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table: Activity A Normal Time (weeks) 3 Crash Time (weeks) 2 B 2 1 1 Normal Cost $1,200 $2,000 $400 $1,500 $950 $4,500 $1,600 Total Cost with Immediate Crashing Predecessor(s) $1,800 $2,800 $400 $1,820 A $1,250 B $5,500 с $2,300...

  • Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's...

    Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity A Normal Time Crash Time Normal (weeks) (weeks) Cost 4 3 $2,000 2 $2,100 $750 Total Cost with Immediate Crashing Predecessor(s) $2,650 - $2,800 - $750 B 2 3 $2.400 $2,680 Ā $900 3 § $1,200 3 $900 $3,200 § $4,600 $9,500 $2,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT